Content composition of the execution plan for individual structures: seven parts of Chapter 5 of GB/T 50502-2009 and refinement requirements

The execution plan for individual structures (GB/T 50502-2009 Chapter 5) should contain: project overview; construction deployment (milestones + flow sections, stages divided into foundation/substructure, main structure, decoration, and M&E installation); construction schedule; construction preparation and resource allocation (labor preferably refined to trades); main construction method statements (divided per GB 50300 into divisional/sub-divisional works); site layout (drawn separately by stage); construction management plans (schedule/quality/safety/environment/cost) — more specific than the overall project execution plan.

Applicable Codes

  • GB/T 50502-2009 建筑施工组织设计规范
  • GB 50300 建筑工程施工质量验收统一标准
  • GB/T 50903-2013 市政工程施工组织设计规范
  • DB22/T 127-2017 建筑工程资料管理标准

Topic Positioning

Content composition and refinement requirements of the execution plan for individual (sub-unit) structures, per Chapter 5 of GB/T 50502-2009.

Core Conclusions

The execution plan for individual structures concretizes the overall project execution plan and contains seven parts:

  1. Project overview — main situation (name, nature, location, participating units, contracting/subcontracting scope, key contractual and tender requirements), brief introduction of the discipline designs, construction conditions;
  2. Construction deployment — coordinate the main divisional/sub-divisional and special works, state milestones, divide flow sections with the basis and direction stated; stages are generally foundation/substructure, main structure, decoration, and M&E installation;
  3. Construction schedule — compiled per the deployment, balanced and coordinated;
  4. Construction preparation and resource allocation — technical preparation (technical documents, method statement compilation plan, testing and equipment commissioning, mock-ups), site preparation, funding preparation; labor preferably refined to trades, materials determined per the schedule;
  5. Main construction method statements — prepared per the GB 50300 divisional/sub-divisional division principle;
  6. Construction site layout — drawn separately for different construction stages;
  7. Construction management plans — schedule, quality, safety, environment, cost, etc. Content may be added or removed per the project's actual conditions; chapter order is not mandatory.

Applicable Boundaries

Applies to compiling and reviewing execution plans for individual structures of building works; the eight basic items of Clause 3.0.4 apply to all levels — this card is the individual-structure-level refinement (see the cited card for the general framework). Municipal works follow GB/T 50903-2013. Does not cover dedicated method statements for high-risk works.

Further Reading

GB/T 50502-2009: Clauses 3.0.1, 3.0.4, 5.1-5.6, Chapter 7, 4.6.1/4.6.2; GB 50300 divisional/sub-divisional division; GB/T 50903-2013 Clause 3.0.4 table of contents; approval per DB22/T 127-2017 Clause 6.2.2.