Determining the construction sequence in a construction method statement: where it is compiled, the basis, principles, and operating steps (GB/T 50502-2009 site deployment strategy framework)
The construction sequence is determined within the "site deployment strategy (construction arrangement)": the core basis is the logical relationships between processes, the item description (work item specification) and spatial organization, and the programme requirements; the principles include "each preceding process creates the construction conditions for the following process, and the following process preserves the finished product of the preceding one", "underground before aboveground, deep before shallow", and "balanced flow". Compilation steps: analyse the item description (work item specification) and identify the critical path -> arrange the order according to technical logic -> combine with spatial organization -> divide flow sections and state the basis and flow direction -> arrange connection and overlapping (flowchart preferred) -> check the programme; if it is not met, adjust the overlapping relationships. Basis: GB/T 50502-2009 Clauses 2.0.6, 5.2.2, 5.3.1; GB/T 50903-2013 Clauses 4.2.4, 4.5.2.
Applicable Codes
- GB/T 50502-2009 建筑施工组织设计规范
- GB/T 50903-2013 市政工程施工组织设计规范
- T/CBDA 35-2019 建筑装饰装修工程施工组织设计标准
Topic Positioning
This card answers "how the construction sequence is determined" in a project execution plan (construction methodology and site organization)/construction method statement: where it is compiled, on what basis, by what principles, and how to operate. It applies to compiling project execution plans and method statements for building and municipal works.
Core Conclusions
- Compilation location: the construction sequence is core content of the "site deployment strategy (construction arrangement)" (GB/T 50502-2009 Clause 2.0.6: site deployment strategy includes the main objectives, the construction sequence and spatial organization, and the organizational arrangements); the programme (of works), resource allocation, construction methods, and site layout are all compiled around the site deployment strategy; the programme (of works) is the deployment expressed in time (Clause 5.3.1) and shall be balanced, coordinated, and scientifically arranged.
- Determination basis: the logical relationships between processes (the most fundamental constraint), the item description (work item specification) (key and difficult divisional works), spatial organization (underground before aboveground, deep before shallow), and programme requirements (arranged on the premise of meeting the contract programme).
- Principles: the completion of each preceding process creates the construction conditions for the following process, and the construction of the following process preserves the integrity of the preceding finished product; flow sections are divided reasonably according to the item description (work item specification) and quantities, with the division basis and flow direction stated, ensuring balanced flow; the construction starting point, flow direction, and sequence are preferably shown in the form of a flowchart (GB/T 50903-2013 Clause 4.5.2).
- Operating steps: analyse the item description (work item specification) and identify the key points, difficulties, and the critical path -> arrange the order according to technical logic (foundation -> main structure -> decoration -> M&E installation) -> combine with spatial organization -> divide flow sections -> arrange work connection and cross-overlapping -> check the programme; if it is not met, adjust the overlapping relationships.
Applicable Boundaries
Applies to project execution plans/method statements compiled per GB/T 50502-2009 (building) and GB/T 50903-2013 (municipal); the construction sequence is not a standalone chapter but a component of the site deployment strategy; single small works may simplify; tunnels, bridges, pipelines, and other specialty works must be deepened in combination with spatial relationships, and the construction starting point, flow direction, and sequence must be clarified in the construction technology method statement.
Further Reading
GB/T 50502-2009 Clauses 2.0.6, 3.0.1, 3.0.4, 5.2.2, 5.3.1, 5.5.1; GB/T 50903-2013 Clauses 3.0.4, 4.2.4, 4.5.2; T/CBDA 35-2019 Clause 6.1.5. For flow-section division details, see the "construction flow-section division" card.