Definitions of the three flow construction parameters (construction section / flow beat / flow step distance), how each is determined, their relations to the flow duration formula, and the correct clause citation in GB/T 50502-2009 (chapter 2 terms does not include these three entries)
Chapter 2 'Terms' of GB/T 50502-2009 includes only project-execution-plan document concepts such as construction arrangement (2.0.6) and construction schedule (2.0.8); it does not include 'flow beat', 'flow step distance' or 'construction section', so the three definitions can serve only as the general treatment of construction organisation principles and must not be tagged as clause 2.0.x. The code's verbatim requirements on flow sections appear only in clause 5.2.2 (divide reasonably by the characteristics and quantities of the works, state the basis of division and the flow direction, ensure balanced flow construction) and clause 6.2.2 (the construction sequence and flow sections are fixed in the construction arrangement); for municipal works see GB/T 50903-2013 clauses 4.2.4 and 5.2.3. The parameter skeleton: t = Q/(S x R x N) = P/(R x N); K is derived from t (fixed-rhythm K = t; multiple-beat K0 = gcd(ti); varying-rhythm and non-rhythmic by staggered subtraction taking the largest difference); flow duration T = sum K + sum of the last process's beats over all sections + sum Z - sum C.
Applicable Codes
- GB/T 50502-2009 · Code for Construction Organization Planning of Building Works 第2.0.6、2.0.8、5.2.2、6.2.2条
- GB/T 50903-2013 · Code for Construction Organization Planning of Municipal Works 第4.2.4、5.2.3条
- JGJ/T 121-2015 · Specification for Engineering Network Planning Technology (时距表达流水步距)
Topic positioning
For project execution plan and construction method statement preparation and scheme defence scenarios, this card defines the three basic flow construction parameters - construction section (flow section), flow beat and flow step distance - their symbols, determination methods and interrelations, and gives the correct way to cite these three terms under GB/T 50502-2009 'Code for project execution plans of building works' (correcting the source of the terms).
Core conclusions
1. Correcting the source: chapter 2 does not include these three entries
Chapter 2 'Terms' of GB/T 50502-2009 defines project-execution-plan document concepts, for example:
- 2.0.6 construction arrangement: the overall planning and comprehensive arrangement for the implementation of the project, including the main targets of project construction, the construction sequence and spatial organisation, and the organisation of construction. The construction arrangement is the programme-setting content of the project execution plan; the constituent parts of the plan - the construction schedule, the preparation and resource allocation plans, the construction methods, the site layout of the construction site and the main construction management plans - should all be prepared around the principles of the construction arrangement.
- 2.0.8 construction schedule: the overall planning and arrangement of the construction sequence, start and finish times and interfacing relations of the construction processes made to meet the duration target set for the project. The construction schedule must ensure the proposed works are completed within the prescribed period, ensure continuity and balance of construction, and save construction costs. Preparing it relies on the objective laws and conditions of building construction, reference to duration norms, and consideration of the input of funds, materials, equipment, labour and other resources.
The chapter's terms contain no entries for 'flow beat', 'flow step distance' or 'construction section (flow section)'. Hence: the definitions of the three terms follow the general treatment of construction organisation principles (textbooks and construction handbooks); when writing schemes or defence papers they must not be tagged 'GB/T 50502-2009 clause 2.0.x' (that clause number does not exist - it is a miscitation). The correct formulation is 'divide the flow sections per clause 5.2.2 of GB/T 50502-2009'.
2. The code's verbatim requirements on flow section division
- GB/T 50502-2009 clause 5.2.2: 'Construction flow sections shall be divided reasonably according to the characteristics and quantities of the works; the basis of division and the flow direction shall be stated, and balanced flow construction shall be ensured.' The clause also says: 'the main construction content and its progress arrangements shall be clearly stated, and the construction sequence shall follow the logic of the processes'; 'construction flow sections shall be divided by stages in light of the specific conditions of the works; the construction stages of a building works generally comprise foundation, main structure, and decoration and mechanical and electrical equipment installation, in three stages'; 'the construction arrangement shall make overall arrangements for the main divisional (sub-divisional) works and dedicated works of this building works, and shall state the milestone nodes of the construction process'.
- GB/T 50502-2009 clause 6.2.2: 'The construction sequence and the construction flow sections shall be fixed in the construction arrangement.'
- GB/T 50903-2013 clause 4.2.4 (code for project execution plans of municipal works): 'The overall construction arrangement shall, according to the characteristics of the works, fix the construction sequence and spatial organisation, and arrange the interfacing of construction operations overall'; it shall also 'analyse the characteristics of the works, such as the key points and difficulties, and from the standpoint of overall implementation, on the premise of ensuring the duration, achieve continuity and balance of construction in the overall sense'; 'the overall construction arrangement shall be written in combination with the logic of construction sequence and spatial organisation'; 'specialist works such as bridges, underground pipelines and tunnels need spatial organisation in construction'.
- GB/T 50903-2013 clause 5.2.3: 'The construction arrangement shall fix the division of construction sections and the construction sequence.'
3. Comparison table of the three terms (general treatment of construction organisation principles, not code term clauses)
| Term | Definition | Symbol / unit | Determination method | Interrelation |
|---|---|---|---|---|
| Construction section (flow section) | A spatial stretch of the proposed works divided along structural boundaries and the principle of balanced quantities, on which the specialist crews work in turn and continuously; at any moment one section generally hosts only one specialist crew | m (number of sections), dimensionless | (1) Divide reasonably by the characteristics and quantities of the works; section boundaries should fall on natural divisions such as movement joints, expansion joints, post-cast strips and structural zoning; (2) keep the quantities (labour content) of the sections as balanced as possible; (3) the number of sections m should be no less than the number of crews n, otherwise crews inevitably stand idle; (4) fix the number of sections by the leading process (leading construction process) | The spatial parameter; the denominator effect on t (the total labour content of a process spread over m sections); with n it forms the independent variables of the flow duration formula |
| Flow beat | The duration a specialist crew needs to complete the corresponding construction process on one construction section | t (days per section), often written t(i,j) | t = Q/(S x R x N) = Q x H/(R x N) = P/(R x N): Q is the quantity in the section, S the output norm, H the unit labour-time norm (H = 1/S), P the labour content in the section (work days / machine-shifts), R the number of workers or machines, N the number of shifts; the result is rounded to whole or half days. Example: Q = 300 m3, S = 12 m3 per work day, R = 5 workers, N = 1 shift -> t = 300/(12 x 5) = 5 days per section | The base quantity of the time parameters; K is derived from t, and t falls as m rises - the start of the causal chain of the three parameters |
| Flow step distance | The minimum time interval between two adjacent specialist crews (two adjacent processes) entering construction in turn - the smallest interval that lets the later crew not disturb the earlier while both work continuously | K (days), often written K(i,i+1) | (1) Fixed-rhythm: K = t; (2) multiple-beat: K0 = greatest common divisor of the beats, gcd(ti), crews per process bi = ti/K0; (3) varying-rhythm / non-rhythmic: cumulative number sequences staggered and subtracted, taking the largest difference (cumulative sequence of the later process, sequence of the earlier process shifted right by one with 0 leading, subtract term by term, take the largest positive value) | A derived quantity of the time parameters; always K no more than the corresponding t (for multiple-beat, K0 = ti/bi); n processes have only n-1 step distances; sum K fixes when the last crew comes on |
4. Relations to the flow duration
General skeleton: T = sum K + sum tn + sum Z - sum C, where T is the flow duration, sum K is the sum of the flow step distances (n-1 of them), sum tn is the sum of the beats of the last construction process over its sections, sum Z the sum of process (technical) and organisational intervals, and sum C the sum of overlap (early insertion) times between adjacent processes. Special cases of the three organisation modes:
- Fixed-rhythm (equal-beat): K = t, T = (m+n-1)t + sum Z - sum C;
- Multiple-beat: T = (m + sum bi - 1)K0 + sum Z - sum C;
- Varying-rhythm / non-rhythmic: K found by staggered subtraction taking the largest difference, substituted into the general skeleton.
Applicability boundaries
- The definitions of the three terms in this card are for use as construction organisation principles only and cannot be cited as code clauses; when a code source is demanded, only GB/T 50502-2009 clauses 5.2.2 and 6.2.2 and GB/T 50903-2013 clauses 4.2.4 and 5.2.3 can be cited.
- The duration formula assumes beats equal between sections for each process (fixed-rhythm), or multiple-beat, or non-rhythmic organisation; where inter-floor relations, technical intervals and overlaps exist, sum Z and sum C must be counted - no omissions.
- Matching the number of sections m to the number of crews n is the precondition of 'no idle crews'; computing the duration by formula alone without checking m no less than n gives over-optimistic conclusions.
- Municipal works (bridges, underground pipelines, tunnels, etc.) follow the GB/T 50903-2013 treatment, where spatial organisation and operation interfacing are more prominent.
- This card gives no section counts or beat values for any specific project; these must be fixed backwards from quantities, quota norms and the contract duration.
Further reading
- GB/T 50502-2009 'Code for project execution plans of building works': clause 2.0.6 (term: construction arrangement), clause 2.0.8 (term: construction schedule), clause 5.2.2 (progress arrangement and spatial organisation within the construction arrangement; division of construction flow sections), clause 6.2.2 (construction method statement - construction arrangement).
- GB/T 50903-2013 'Code for project execution plans of municipal works': clause 4.2.4 (overall construction arrangement), clause 5.2.3 (construction method statement - construction arrangement).
- Further study: the flow construction organisation chapter of the current 'Building Construction Handbook' (organisation modes and derivation of duration formulas for fixed-rhythm, varying-rhythm, multiple-beat and non-rhythmic flow); the practice in JGJ/T 121-2015 'Specification for engineering network planning technique' of expressing flow step distances by FTS / STS / FTF / STF lags.