Engineering Knowledge Cards.
Confidence HighUpdated 2026-10-25

Three-parameter calculation of flow construction: flow rhythm, flow lag (K), and duration formulas (equal rhythm / multiple rhythm / non-rhythm)

Flow rhythm t = Q/(S·R·N). Under the three organizational modes: equal rhythm K = t, T = (m+n−1)t+ΣZ−ΣC; multiple rhythm K₀ = greatest common divisor of all rhythms, n′ = Σbᵢ, T = (m+n′−1)K₀+ΣZ−ΣC; non-rhythm uses the accumulated-number staggered-subtraction maximum-difference method (Pantkovsky method) to find K, T = ΣK + sum of rhythms of the last process + ΣZ−ΣC. Intervals are added (+), overlaps subtracted (−).

Applicable Codes

  • GB/T 50502-2009 · Code for Construction Organization Planning of Building Works 第 5.2.2 条、第 6.2.2 条
  • GB/T 50903-2013 · Code for Construction Organization Planning of Municipal Works 第 4.2.4 条
  • JGJ/T 121-2015 · Specification for Engineering Network Planning Technology

Topic Positioning

The core parameter calculation methods for flow-construction scheduling — the general formulas for flow rhythm, flow lag (step distance K), and flow duration, covering the equal-rhythm, multiple-rhythm, and non-rhythm organizational modes, verified with typical worked examples.

Core Conclusions

  • Flow rhythm t: the duration of one construction process on one section, t = P/R = Q/(S·R·N), where P = labour/machine-shift quantity, R = number of workers or machines deployed, S = output quota, Q = work quantity, N = shifts per worker-day.
  • Equal-rhythm flow (rhythm of every process on every section is a constant t): lag K = t, duration T = (m+n−1)·t+ΣZ−ΣC (m = number of sections, n = number of processes).
  • Multiple-rhythm flow (each rhythm is an integer multiple of the same constant K₀): take the greatest common divisor of the rhythms as the lag K₀; crew count per process bᵢ = tᵢ/K₀, total crews n′ = Σbᵢ; duration T = (m+n′−1)·K₀+ΣZ−ΣC.
  • Non-rhythm flow (most common in practice): find the lag by the accumulated-number staggered-subtraction maximum-difference method (Pantkovsky method) — accumulate rhythms by section order for each process into a number series, subtract adjacent series staggered by one position, and the maximum difference is K; duration T = ΣK + sum of rhythms of the last process + ΣZ−ΣC.
  • General points: technological plus organizational intervals extend the duration and are recorded as +ΣZ; parallel overlaps shorten it and are recorded as −ΣC; the two must be listed separately. In equal-rhythm flow each additional section adds one t to the duration — sectioning must balance idle-labour prevention against duration control.

Applicable Boundaries

Applies to preparing and reviewing project execution plans / schedule plans; this is a general-purpose calculation method (standards give only principled requirements; formulas follow the general textbook method). Equal-rhythm / multiple-rhythm flow suits works with strongly regular rhythms where specialist crews can work continuously; non-rhythm is the most general. When the number of sections m is smaller than the number of crews, idle time is inevitable; where critical-path and float analysis is needed, switch to network planning (JGJ/T 121-2015) for review. Resource leveling and optimization are not covered.

Further Reading

GB/T 50502-2009, Code for Project Execution Planning of Building Works, Clause 5.2.2 (balanced-flow requirements for scheduling and spatial organization) and Clause 6.2.2 (construction sequence and flow sections fixed in the construction arrangement); GB/T 50903-2013, Code for Project Execution Planning of Municipal Works, Clause 4.2.4 (continuity and balance of the overall construction arrangement); DB23/T 2995-2021, Green Construction Specification for Water Conservancy Projects in Heilongjiang Province, Clause 5.2.1 (site zoning to reduce cross operations). Formulas and worked examples: see the "principles of flow construction" chapters of project execution planning / schedule control textbooks; for network-plan review see JGJ/T 121-2015, Specification for Engineering Network Planning Technique.

Keywords

  • 非节奏流水
  • 异节奏流水
  • 错位相减取大差
  • 流水步距
  • 流水施工工期
  • 成倍节拍流水
  • 潘特考夫斯基法
  • 流水段划分

Cited By