Compiling schedules in construction schemes: compilation procedure, duration calculation, and bar-chart/network-diagram selection
Schedules of construction schemes (divisional/sub-divisional/special) are compiled in eight steps: set schedule objectives -> work-structure breakdown -> compute quantities -> determine construction sequence and logic -> estimate resource input -> estimate durations -> form the schedule diagram (table) -> check duration and resource balance, then write notes and obtain approval. Duration D = P / (R x B), P = Q x H (unit labour-time norm) or P = Q / S (output quota). Divisional (sub-divisional) schedules must satisfy the project (general-contract) schedule and be dynamically adjusted; ordinary works use bar charts, large-scale or complex-process works preferably network diagrams to find the critical path.
Applicable Codes
- GB/T 50502-2009 建筑施工组织设计规范
- GB/T 50903-2013 市政工程施工组织设计规范
- GB/T 50326-2017 建设工程项目管理规范
- GB/T 50358-2017 建设项目工程总承包管理规范
- GB 51114-2015 露天煤矿施工组织设计规范
- T/CREA 021-2022(T/CBIMU 15-2022)建筑与市政地基基础通用标准
Topic Positioning
This card answers "how the schedule in a construction scheme is compiled": covering the compilation procedure, duration calculation, selection of expression forms (bar chart/network diagram), and checking points, applicable to schedule compilation at the construction-scheme (divisional/sub-divisional/special works) level.
Core Conclusions
- Compilation procedure (GB/T 50326-2017 Clause 9.2.4; GB/T 50358-2017 Clause 7.3.4): set schedule objectives -> work-structure breakdown (divisional/sub-divisional/process) -> compute quantities -> determine construction sequence and logic -> estimate resource input -> estimate process durations -> form the schedule diagram (table) -> check duration objectives and resource balance (loop back and adjust if not satisfied) -> write notes and submit for approval and release.
- Duration calculation (GB 51114-2015 Clause 8.2.12): labor demand P = Q x H (comprehensive unit labour-time norm, worker-days per m3 etc.) or P = Q / S (output quota); duration D = P / (R x B), where R is the number of workers or machines per shift and B is the number of shifts per day. Example: Q = 2000 m3, H = 0.5 worker-days/m3 -> P = 1000 worker-days; R = 40 persons, B = 1 shift -> D = 25 days.
- Key constraint: divisional (sub-divisional) construction schedules shall satisfy the project (general-contract) construction schedule and be dynamically adjusted with the construction arrangements (GB/T 50903-2013 Clause 5.2.4; T/CREA 021-2022 Appendix L, Clause L.0.6).
- Expression forms (GB/T 50502-2009 Clauses 5.3.2, 6.3.2): ordinary works use bar charts; larger-scale works with complex processes preferably use network diagrams (parameters can be computed and the critical path found); both carry necessary notes and may be represented together with resource plans.
Applicable Boundaries
Applies to schedule compilation at the construction-scheme level for building and municipal works; in special schemes for sub-divisional works involving significant hazards, the schedule is part of the "construction plan" (including material/equipment and labor plans), with the overall framework per Jianban Zhi [2021] No. 48. The duration formula is the quota/experience estimation method; actual compilation should be checked against working faces, resources, and seasonal conditions, and dynamically adjusted as construction proceeds; not applicable to macro bid-stage schedule planning.
Further Reading
GB/T 50502-2009 Sections 5.3 and 6.3; GB/T 50903-2013 Clause 5.2.4; GB/T 50326-2017 Clause 9.2.4 (compilation steps); GB/T 50358-2017 Clause 7.3.4 (compilation procedure); GB 51114-2015 Clause 8.2.12 (quantity, labor demand, and duration formulas, and schedule optimization and adjustment); T/CREA 021-2022 (T/CBIMU 15-2022) Appendix L, Clause L.0.6.
Keywords
- 施工方案进度计划
- 分部工程施工进度计划
- 进度计划编制程序
- 持续时间计算
- 劳动量
- unit labour-time norm
- 横道图
- 网络图