Preparation and approval of project execution plans: three-level division, responsibility for leading preparation, and tiered approval authority

Project execution plans divide into three levels by object: the overall project execution plan, the execution plan for individual structures, and construction method statements (GB/T 50502-2009, Clause 3.0.1). Each level is led in preparation by the project manager and may be prepared and approved in stages; the overall plan is approved by the general contractor's technical responsible person, the execution plan for individual structures by the contractor's technical responsible person (delegation allowed), general method statements by the project's technical responsible person, and specialist contractors' method statements by the specialist contractor's technical responsible person with review and filing by the general contractor's project technical lead; dedicated method statements for sub-divisional works involving significant hazards require the contractor's technical responsible person's signature plus the review signature of the Engineer (chief supervising engineer under China's supervision regime), and those above a specified scale additionally require expert panel review.

Applicable Codes

  • GB/T 50502-2009 建筑施工组织设计规范
  • DB22/JT 127-2017 建筑工程资料管理标准
  • DB22/T 5016-2019 市政工程资料管理标准
  • DB11/T 1745-2020 建筑工程施工技术管理规程

Topic Positioning

Project execution plans and construction method statements are different levels of the same system. This card sets out the three-level division, responsibility for leading preparation, and a comparison of tiered approval authority (building-works system), answering "who prepares, who approves".

Core Conclusions

Per GB/T 50502-2009, Clause 3.0.1, project execution plans divide into three levels by object: the overall project execution plan (group projects/mega projects, overall planning); the execution plan for individual structures (unit (sub-unit) works, guiding and governing the whole process); construction method statements (divisional (sub-divisional) or dedicated works, the detailed elaboration of the project execution plan). Leadership in preparation: each level is led in preparation by the project manager and may be prepared and approved in stages as needed (Clause 3.0.5, item 1); the overall project execution plan is additionally drafted under the organization of the project technical lead with the production manager, commercial manager, and functional departments participating (DB11/T 1745-2020, Clause 6.2.1). Approval authority: the overall plan is approved by the general contractor's technical responsible person; the execution plan for individual structures by the contractor's technical responsible person or an authorized technician; general method statements by the project's technical responsible person; key, difficult, and dedicated method statements by the contractor's technical department organizing expert panel review and the technical responsible person approving; specialist contractors' method statements are approved by the specialist contractor's technical responsible person and, under a general contractor, reviewed and filed by the general contractor's project technical lead. Dedicated method statements for sub-divisional works involving significant hazards require the contractor's technical responsible person's review signature + the review signature of the Engineer (chief supervising engineer under China's supervision regime), with those above a specified scale additionally requiring expert panel review. Local document-management standards generally require the project execution plan to bear the enterprise seal, and method statements for sub-divisional works involving significant hazards to bear the unit seal and the Engineer's practice seal.

Applicable Boundaries

Applies to the building-works system; municipal terminology differs slightly (GB/T 50903-2013 defines method statements as prepared separately for divisional (sub-divisional) works) but the levels are the same. Do not confuse with the four-level quality-acceptance division of GB 50300. Dedicated method statement content for sub-divisional works involving significant hazards, scope determination, and expert panel review procedures are in the dedicated card.

Further Reading

GB/T 50502-2009 Clauses 2.0.3, 2.0.4, 3.0.1, 3.0.5; DB22/JT 127-2017 Clause 6.2.2; DB22/T 5016-2019 Clause 7.2.3; DB11/T 1745-2020 Clause 6.2.1; GB/T 50903-2013 Clause 2.0.2; Jianban Zhi [2021] No. 48.