The project management planning system of GB/T 50326-2017 chapter 5: planning composition (planning outline + implementation plan + supporting planning), the six planning steps, and the implementation plan's bases / steps / 17 content items and file quality requirements

GB/T 50326-2017 chapter 5 splits project management planning into 'management plan planning + supporting planning', the plan comprising the project management planning outline and the project management implementation plan. The six planning steps: identify the management scope -> work breakdown -> fix the implementation methods -> prescribe resources -> estimate project cost -> plan each management process (5.1.4). The outline preferably holds 15 items and may be omitted in three cases, going straight to the implementation plan (5.2.4); the implementation plan refines the outline with 17 content items (5.3.4), 8 bases (5.3.3) and 5 steps (5.3.2); in general the contractor's project execution plan equals the project management implementation plan (5.3.1).

Applicable Codes

  • GB/T 50326-2017 建设工程项目管理规范 第5.1.1~5.1.5条、第5.2.4~5.2.5条、第5.3.1~5.3.5条、第5.4.1条及表1
  • RISN-TG 012-2011 建设工程项目经理执业导则 第5.2.1条
  • GB/T 50502-2009 建筑施工组织设计规范

Positioning

The complete frame of chapter 5 'project management planning' of GB/T 50326-2017: which documents make up the planning, the procedure and steps, what the outline and the implementation plan each contain, and what quality a document must reach. For compiling and evaluating planning documents of construction, EPC and agency-construction projects.

Core conclusions

1. Composition (5.1.1) Project management planning consists of management plan planning and supporting planning. The management plan comprises the planning outline and the implementation plan; supporting planning covers all planning content beyond the management plan. Outputs: the management plan (outline + implementation plan) and the supporting results. Management-plan content may alternatively appear as management plans of various kinds (quality, schedule, cost, work-safety, communication, risk, and the EPC project management plan) - see 5.3.4; such plans centre on specialist management and form important parts of the implementation plan.

2. System and duties (5.1.2) The organisation shall establish a planning management system fixing duties, procedures and control requirements. EPC and agency-construction 'project management plans' must include financing, survey-design management, tendering and procurement, process control and commissioning preparation - the planning documents must first answer 'who compiles, reviews, approves, and when'.

3. Four management processes (5.1.3) 1 analyse and fix the content and scope; 2 coordinate, study and form the results; 3 check, supervise and evaluate the process; 4 perform other duties.

4. Six planning steps (5.1.4) 1 identify the management scope; 2 work breakdown; 3 fix implementation methods; 4 prescribe resources; 5 estimate project cost; 6 plan each management process.

5. Six rules for the process (5.1.5) 1 the scope covers everything to complete the project, coordinated with all parties; 2 the WBS is built on deliverables per the scope, detailed to need; 3 resources are compared for quality assurance and cost reduction; 4 scheduling forms the master programme, preferably visualised; 5 cost is estimated by separating quantity from price, on physical and non-physical consumption; 6 tracking checks and necessary adjustments, with a closing summary.

6. The planning outline (5.2.4, 5.2.5) Preferably 15 items, selectable: 1 project overview; 2 scope management; 3 management objectives; 4 organisation; 5 procurement and tendering; 6 schedule; 7 quality; 8 cost; 9 work safety; 10 green construction and environment; 11 resources; 12 information; 13 communication and stakeholders; 14 risk; 15 closing. Omittable, going straight to the implementation plan, in three cases: small, technically simple buildings; projects whose tenders accept an implementation plan; element works or specialist subcontracts. Outline documents carry three things (5.2.5): objectives and duties; procedures and methods; resource provision and arrangement.

7. The implementation plan (5.3.1~5.3.5) Position (5.3.1): it refines the outline, compiled on the outline and carrying its decisions into execution. In general the contractor's project execution plan equals the implementation plan. It is developed against task decomposition and the body's functional division, with specialist, sub-project and collaborative planning. 8 bases (5.3.3): laws and standards; the contract; the outline; design documents; the works' conditions and features; resources and conditions; useful historical data; the team's capability. 5 steps (5.3.2): understand stakeholders' requirements; analyse features and environment; know the codes and documents; compile; obtain approval. 17 items (5.3.4): overview; overall arrangement; organisation scheme; design and technical measures; schedule plan; quality plan; cost plan; safety plan; green construction and environment plan; resource and procurement plan; information plan; communication plan; risk plan; closing plan; site layout; target-control plan; techno-economic indicators. File quality (5.3.5): 1 the outline fully deepened and made concrete; 2 the scope meets the real needs of the objectives; 3 the risks of implementing the plan acceptable - the three basic qualitative criteria for judging quality.

8. Supporting planning (5.4.1) Supporting planning is the planning process linked to the management plan, taken as its support and included in the system; it covers all planning beyond the plan documents (see 5.4.3's three items); its results need not form documents, subject to law and organisational rules.

Applicable boundaries

  • The frame and required content only - no inference to any firm's internal rules; check the firm's own documents.
  • 'Execution plan equals implementation plan' holds generally, provided the 17 items and the three quality criteria are met; where both are compiled, keep them consistent (methods, schedule, resources).
  • The outline may be omitted only in the three cases; others keep the outline then refine.
  • Supporting results may be unwritten unless law or rules require documents.
  • Cost estimating here is a management-decision basis (physical / non-physical, quantity-price separation) - not the tendering or settlement basis; never mix.

Further reading

GB/T 50326-2017 chapter 5 clauses 5.1.1~5.1.5, 5.2.4-5.2.5, 5.3.1~5.3.5, 5.4.1 and Table 1 (scope and compilers); EPC document levels: GB/T 50358-2017 chapter 4; execution plan division and approval: GB/T 50502-2009; the manager organising planning: RISN-TG 012-2011 clause 5.2.1.