Depth requirements for compiling construction methodology in construction method statements: four elements for ordinary statements and deepening for dedicated statements
The yardstick of methodology depth is "able to concretely guide the construction process" — the operation level can directly organise construction, inspection, and acceptance per the statement. An ordinary statement must state four elements clearly: methodology flow (flowchart preferred), operating methods, quality inspection standards, and control of important methodology nodes; dedicated method statements for high-risk works deepen further to quantified technical parameters + calculation sheets + operation/use/inspection requirements + special tools and equipment requirements; key processes, four-new technologies, and seasonal construction require special explanation.
Applicable Codes
- GB/T 50502-2009 建筑施工组织设计规范
- GB/T 50903-2013 市政工程施工组织设计规范
- T/CBDA 35-2019 建筑装饰装修工程施工组织设计标准
- T/CREA 021-2022 建筑与市政地基基础通用标准
- T/XCIA 3-2023 危险性较大的分部分项工程施工安全管理规程
- 建办质〔2021〕48号 危大工程专项施工方案编制指南
Topic Positioning
Answers "to what depth the construction methodology in a construction method statement should be written": gives the graded depth requirements and self-check criteria for the methodology content of ordinary construction method statements and dedicated method statements for high-risk works, for depth control in statement compilation, review, and briefing.
Core Conclusions
The depth yardstick is "able to concretely guide the construction process" — the operation level can directly organise construction, inspection, and acceptance per the statement, rather than stopping at "what method to use". An ordinary statement's methodology should contain four elements: (1) construction methodology flow (clarify the construction starting point, direction, sequence, and process connection, preferably shown as a flowchart); (2) operating methods (specific operating key points of each process); (3) quality inspection standards (cited codes, tolerances (permissible deviations), inspection methods); (4) attention items, control measures, and technical requirements for important methodology nodes (T/CBDA 35-2019 Clause 6.1.7). Dedicated method statements for high-risk works deepen on this basis: quantified technical parameters, calculation sheets and related drawings, safe-operation requirements, special tools and equipment requirements, and inspection requirements (T/CBDA 35-2019 Clause 7.1.2; T/XCIA 3-2023 Clause 5.2.3; Jianban Zhi [2021] No. 48). Necessary technical verification should also be performed; processes prone to common quality defects, with high safety risk, high difficulty, or high technical content are explained with emphasis; four-new technologies are tested or demonstrated with plans formulated; seasonal construction has specific requirements (T/CREA 021-2022 Appendix L).
Applicable Boundaries
Applies to compiling building construction method statements and municipal construction methodology statements. Depth increases with the document level: the overall project execution plan and the execution plan for individual structures reach only the method-and-principle level; construction method statements must reach the process-operation level (GB/T 50903-2013 Clause 5.4.1: construction methods should be more detailed than the project execution plan); dedicated method statements for high-risk works must reach the level of "parameters verifiable by calculation and executable by the operation level". Dedicated method statements for sub-divisional works involving significant hazards must also satisfy the 9-item content framework of MOHURD Order No. 37 and Jianban Zhi [2021] No. 48; this card targets only the depth of "construction methodology" within that framework.
Further Reading
See T/CBDA 35-2019 "Standard for construction organisation planning of building decoration engineering" Clauses 6.1.7, 7.1.2; GB/T 50903-2013 "Code for construction organisation plan of municipal engineering" Clauses 4.5.2, 5.4.1; T/CREA 021-2022 "General standard for building and municipal foundations" Appendix L; T/XCIA 3-2023 "Regulation for construction safety management of sub-divisional works with larger dangers" Clause 5.2.3; GB/T 50502-2009 "Code for construction organisation plan of building engineering" Chapter 6 construction method statements (Clause 6.5.1).
Keywords
- construction method statement
- 施工工艺
- 编制深度
- 工艺流程
- 操作方法
- 质量检验标准
- dedicated method statement for high-risk works
- 技术参数
- 计算书