Compiling emergency measures in construction schemes: three blocks for ordinary schemes and 11 items of emergency-response measures for dangerous sub-part special schemes

Emergency measures of ordinary construction schemes (GB/T 50903-2013 Clause 6.9.2) contain three blocks: (1) emergency-rescue organization and responsibilities; (2) accident risk analysis + emergency-response procedures and on-site disposal measures + regular drill plans; (3) emergency supplies and equipment support (type, quantity, performance, storage location, responsible custodian, and contact information). Special schemes for dangerous sub-part works must have a separate "emergency-response measures" chapter, compiled completely with 11 items per Jianban Zhi [2021] No. 48 / T/XCIA 3-2023 Clause 8.2.1. The construction general contractor is the project's emergency-rescue organizing unit (MOHURD Order No. 37, Article 22).

Applicable Codes

  • GB/T 50903-2013 第6.9.2条
  • 建办质〔2021〕48号
  • T/XCIA 3-2023 第8.1.3、8.2.1条
  • 住建部令第37号 第22条
  • GB 50720-2011 第6.1.6条
  • GB 50656-2011 第13.0.4条
  • GB/T 29639
  • 交通运输部令2017年第25号 第25条

Topic Positioning

This card answers what emergency measures in construction schemes should contain, distinguishing the two compilation calibers of ordinary construction schemes and dangerous sub-part special schemes, with accompanying emergency organization and drill requirements.

Core Conclusions

Three blocks of emergency measures for ordinary construction schemes (GB/T 50903-2013 Clause 6.9.2): (1) emergency-rescue organization: form the team and clarify responsibilities; (2) accident risk analysis and emergency response: assess the possible accident locations and consequences, formulate emergency-response procedures (alarm, measure activation, rescue and guidance, interface with superior plans), on-site disposal measures (targeting fire, explosion, collapse, flooding, machinery injury, etc.), and regular drill plans; (3) emergency supplies and equipment support: clarify type, quantity, performance, storage location, responsible custodian, and contact information. The "emergency-response measures" of dangerous sub-part special schemes are a statutorily required chapter (Jianban Zhi [2021] No. 48; T/XCIA 3-2023 Clause 8.2.1), with 11 items in full: scope of application; risk locations, accident types, likelihood, severity, and impact scope; organization, division of responsibilities, and contact information; accident reporting procedures, methods, and content; action measures upon accident warning signs or occurrence; disposal flow (including casualty rescue) and precautions; communication contacts (including pipeline owner units and rescue hospital information); safeguard measures (monitoring, evacuation, traffic control, security cordon); interface with related measures; emergency-drill organization and implementation; emergency-supply preparation and management requirements.

Applicable Boundaries

Ordinary schemes are compiled per the three blocks; dangerous sub-part special schemes per the complete 11 items. Do not mix adjacent calibers: fire-extinguishing and emergency-evacuation plans (GB 50720-2011 Clause 6.1.6), enterprise emergency-rescue plans (GB 50656-2011 Clause 13.0.4, which shall comply with GB/T 29639), and the highway/waterway comprehensive + special + on-site disposal plan system (Ministry of Transport Order No. 25 of 2017). The construction general contractor is the project's emergency-rescue organizing unit (MOHURD Order No. 37, Article 22).

Further Reading

See GB/T 50903-2013 Clause 6.9.2; Jianban Zhi [2021] No. 48; T/XCIA 3-2023 Clauses 8.1.3, 8.2.1; MOHURD Order No. 37 Article 22; GB 50720-2011 Clause 6.1.6; GB 50656-2011 Clause 13.0.4; GB/T 29639.