Full pre-construction technical and safety procedure chain for dangerous sub-part works (identification -> compilation -> dual sign-off -> expert demonstration -> two-stage disclosure -> condition verification -> site announcement -> acceptance)

Before construction of sub-divisional works involving significant hazards, the following must be completed in order: (1) identify and build the list against Appendices 1/2 of Jianban Zhi [2018] No. 31 and the provincial detailed rules; (2) prepare the dedicated method statement for high-risk works; (3) check-and-sign by the technical responsible person of the contractor (signature + company official seal) and review-and-sign by the Engineer (chief supervising engineer under China's supervision regime) (signature + practice seal); (4) for works exceeding a certain scale, the main (general) contracting unit organizes the expert panel review (no fewer than 5 experts, recusal of interested parties); the review conclusion is pass / pass after revision / fail — the latter two respectively require re-performing the sign-off or re-verification by the expert panel; (5) two-stage briefing (preparer -> site management personnel on the method statement; site management personnel -> workers on safety-technical matters, both signed by both parties plus the full-time safety officer); (6) verification of work-safety conditions (contractor self-check -> supervision review -> employer confirmation); (7) on-site announcement of the name / time / responsible persons of the sub-divisional works involving significant hazards plus warning signs; (8) where acceptance is required, the next process may be entered only after passing acceptance (signatures of the project technical responsible person + the Engineer), with an acceptance sign plate erected.

Applicable Codes

  • 住建部令第37号《危险性较大的分部分项工程安全管理规定》(47号令修正)
  • 建办质〔2018〕31号
  • T/XCIA 3-2023
  • DB32/T 2618-2023
  • DB22/T 5115-2022
  • DBJ41/T 228-2019
  • DB37/T 5164-2020

Topic Positioning

A one-card overview of the "technical + safety" procedure timeline that must be completed before construction of sub-divisional works involving significant hazards — from work identification, method statement preparation, dual sign-off, and expert panel review for exceeding-scale works, through two-stage briefing, verification of work-safety conditions, and on-site announcement and warning, to acceptance — showing the complete pre-construction compliance process, the responsible persons, and the sequence.

Core Conclusions

Pre-construction procedure chain (MOHURD Order No. 37; Jianban Zhi [2018] No. 31): (1) Identification: determine the list of sub-divisional works involving significant hazards against Appendices 1/2 of Document No. 31, superimposed with the provincial detailed rules. (2) Prepare the dedicated method statement for high-risk works (organized by the main (general) contracting unit; where subcontracted, it may be prepared by the specialty subcontractor). (3) The technical responsible person of the contractor checks and signs with the company's official seal affixed. (4) The Engineer (chief supervising engineer under China's supervision regime) reviews and signs with the practice seal affixed (when prepared by a subcontractor, the technical responsible persons of both the main (general) contractor and the subcontractor jointly check, sign, and seal). (5) For sub-divisional works involving significant hazards exceeding a certain scale, the main (general) contracting unit organizes the expert panel review — experts are selected from the expert pool of the housing and construction authorities, no fewer than 5, with recusal of interested parties; the review report conclusion is "pass / pass after revision / fail": "pass after revision" requires revision per the report and re-performing the sign-offs of (3) and (4); "fail" requires re-verification by the expert panel. (6) Two-stage briefing (Article 15 of Order No. 37): the preparer or the project technical responsible person briefs the site management personnel on the method statement, and the site management personnel then give the workers the safety-technical briefing; both stages must be jointly signed and confirmed by both parties together with the project's full-time work-safety management personnel. (7) Verification of work-safety conditions: self-check by the contractor, review by supervision, confirmation by the employer; re-verification is required when conditions change. (8) Announce the name, construction time, and responsible persons of the sub-divisional works involving significant hazards at a prominent on-site location, and set safety warning signs in hazardous areas. (9) For sub-divisional works involving significant hazards requiring acceptance as stipulated, the next process may be entered only after passing acceptance and confirmation by signature of the contractor's project technical responsible person and the Engineer, with an acceptance sign plate erected.

Applicable Boundaries

Applies to building and municipal infrastructure works. Expert panel review is mandatory only for sub-divisional works involving significant hazards exceeding a certain scale; ordinary sub-divisional works involving significant hazards need only complete the dual sign-off. Provincial detailed rules may supplement and expand the scope (only tightening, never reducing); some provinces add requirements such as special-inspection frequency during construction for exceeding-scale sub-divisional works involving significant hazards (e.g., no fewer than 2 per month) and require an archive of sub-divisional works involving significant hazards to be established. The method statement must not be modified without authorization during implementation; where adjustment is genuinely needed (planning adjustment, design change (designer-issued variation), external environment change), re-review and re-verification by the expert panel are required.

Further Reading

MOHURD Order No. 37 (as amended by Order No. 47) Articles 3, 10, 11, 12, 13, 15; Appendices 1/2 of Jianban Zhi [2018] No. 31; T/XCIA 3-2023 Clauses 5.3.3, 6.5.1, 6.5.2 (review participants, two-stage briefing content); DB32/T 2618-2023 Clause 4.6.2 (verification of work-safety conditions); DB22/T 5115-2022 Section 5.15 (archive of sub-divisional works involving significant hazards, announcement, acceptance, special inspections); DBJ41/T 228-2019 Clause 7.1.9 (acceptance personnel composition); DB37/T 5164-2020 Clause 4.4.6 (full-process management steps).