Re-approval of construction schemes after construction-condition changes: ordinary schemes re-follow the procedure under the original authority; major adjustments of dangerous sub-part special schemes require re-demonstration
Construction schemes are under dynamic management; upon major changes of the construction environment/conditions they must be revised and supplemented in time, and the approval procedure must be re-performed under the original approval authority; special schemes for dangerous sub-part works must not be modified without authorization; where a major adjustment is genuinely needed, the revised scheme must be re-reviewed (dual signature of the contractor's technical responsible person + the chief supervision engineer), and for dangerous sub-part works exceeding a certain scale, or for major revisions after demonstration, the expert demonstration must be re-organized; construction must not continue under the new conditions without re-approval.
Applicable Codes
- DB11/T 1745-2020 建筑工程施工技术管理规程
- DB37/T 5164-2020 建筑施工现场管理标准
- T/XCIA 3-2023 危险性较大的分部分项工程施工安全管理规程
- GB 51114-2015 露天煤矿施工组织设计规范
- 住建部令第37号 危险性较大的分部分项工程安全管理规定
- DB23/T 1318-2020 黑龙江省建设施工现场安全生产标准化实施标准
Topic Positioning
After construction conditions/environment change, must the construction scheme (including special schemes) be revised and re-approved — the dynamic-management question of "how the scheme goes through the procedure after changes".
Core Conclusions
- Schemes are under dynamic management: major adjustments of the project execution plan, major design changes, major adjustments of main methods or resource allocation, major changes of the construction environment, etc. require timely revision and supplementation (DB11/T 1745-2020 Clause 7.1.3), and after revision the approval procedure must be re-performed under the original approval authority (Clause 7.2.6; GB 51114-2015 Clause 11.0.2); the list of revision situations is in DB37/T 5164-2020 Clause 3.4.3.
- Dangerous sub-part special schemes are stricter: no modification without authorization; where a major adjustment is genuinely needed, the revised scheme must be re-reviewed, re-examined, and re-demonstrated (T/XCIA 3-2023 Clause 6.2.2); for dangerous sub-part works exceeding a certain scale (duration over one year, drawing changes, major environment changes, technology changes, etc.), the scheme must be re-compiled and the expert demonstration re-organized (Clause 5.3.10); major revisions after demonstration require re-demonstration.
- Upon major changes of the surroundings around excavations or of construction conditions, the special scheme must be revised and pass review and demonstration before construction may continue (DB23/T 1318-2020 Clause 9.1.3).
Applicable Boundaries
Applies to scheme-change management at the implementation stage. Whether "major" is judged per project reality; ordinary fine-tuning goes through dynamic-revision records and does not necessarily trigger re-demonstration; re-demonstration targets only dangerous sub-part works exceeding a certain scale or major revisions after demonstration. Local standards differ in detail — the current regulations at the project location govern.
Further Reading
DB11/T 1745-2020 (dynamic management and re-approval); DB37/T 5164-2020 (list of revision situations); T/XCIA 3-2023 (re-demonstration for dangerous sub-part adjustments); MOHURD Order No. 37 Article 11; GB 51114-2015 Clause 11.0.2; DB23/T 1318-2020 Clause 9.1.3.