Local expansion thresholds for the scope of dangerous sub-part works (T XCIA 3-2023 Shaanxi/Xi'an detailed rules example)

Determining dangerous sub-part works requires stacking the "national list + local detailed rules": MOHURD Order No. 37 Article 3 authorizes provincial housing departments to supplement the scope per local conditions (only tightening/expanding, never shrinking). The Shaanxi/Xi'an rules (T XCIA 3-2023, Clause 3.3.3, per Shaan Jian Fa [2019] No. 1116) add beyond Annex 2 of Document No. 31: high-slope protection categories (rock cut > 30 m, soil cut/embankment > 20 m, landslide volume > 100,000 m3), formwork supports with slab thickness >= 350 mm or beam section >= 0.45 m2, non-standard foundation/wall-attached tower crane and hoist installation, erecting-machine assembly/disassembly, and demolition above Class C blasting; over-scale items require expert demonstration.

Applicable Codes

  • T XCIA 3-2023《危险性较大的分部分项工程施工安全管理规程》第3.3.3条
  • 住建部令第37号《危险性较大的分部分项工程安全管理规定》第三条
  • 建办质〔2018〕31号附件1/2
  • 陕建发〔2019〕1116号
  • 市建质发〔2018〕26号

Topic Positioning

When determining the scope of dangerous sub-part works, how provincial/local rules expand the national list (Jianban Zhi [2018] No. 31, Annexes 1/2) — using T XCIA 3-2023 (Shaanxi/Xi'an) as the example, listing the over-scale determination thresholds added beyond the national list, to prevent "checking only the national list and missing judgments".

Core Conclusions

Per MOHURD Order No. 37 Article 3, provincial housing departments may "supplement" the local dangerous-works scope per local conditions — only tightening/expanding, never shrinking; determination must first check Annexes 1/2 of Document No. 31 and then stack the provincial rules. Typical local expansions (over-scale, expert demonstration required): (1) formwork supports: concrete slab thickness >= 350 mm or beam section >= 0.45 m2 (absent from the national list); (2) high-slope protection (no such national category): rock cut slope height > 30 m, soil cut/embankment slope > 20 m, landslide bodies of medium scale or above with volume > 100,000 m3; (3) lifting machinery: tower cranes and hoists installed with non-manual foundations or wall attachments, roof cranes dismantling tower cranes, erecting-machine assembly/disassembly and girder erection; (4) deep pits: depth < 5 m but complex geology/environment or toxic/harmful gases; (5) demolition: blasting works above Class C; (6) scaffolds: attached cantilevered scaffolds and special-shaped work gondolas; (7) covert excavation: pipeline works including horizontal directional drilling crossing existing roads/structures; (8) manual dug piles in complex environments and confined-space operations in complex environments.

Applicable Boundaries

The specific items are per T XCIA 3-2023 (formulated per Shaan Jian Fa [2019] No. 1116 and Shi Jian Zhi Fa [2018] No. 26), applicable to Shaanxi/Xi'an; other provinces must check their own rules, which may similarly expand. This card lists only locally added items; all items of the national list in Annexes 1/2 of Document No. 31 remain concurrently applicable. Works within the protection zones of operating tunnels, metro, airports, bridges, and waterways must also submit special schemes to the relevant authorities for approval per regulations.

Further Reading

T XCIA 3-2023 "Regulation for construction safety management of sub-divisional works with larger dangers" Clause 3.3.3; MOHURD Order No. 37 Article 3; Jianban Zhi [2018] No. 31 Annexes 1/2; Shaanxi implementation rules (Shaan Jian Fa [2019] No. 1116), Xi'an implementation rules (Shi Jian Zhi Fa [2018] No. 26); the full national-list thresholds in the cited card "determining the scope of dangerous sub-part works and those exceeding a certain scale".