AI-assisted preparation of construction method statements: statutory sign-off responsibility chain and key manual review points
AI can only serve as a drafting tool: the overall project execution plan is approved by the technical responsible person of the main (general) contractor; the execution plan for individual structures is approved by the technical responsible person of the construction contractor; general method statements are approved by the project's technical responsible person; dedicated method statements for high-risk works (sub-divisional works involving significant hazards) may only be implemented after the technical responsible person of the construction contractor has reviewed and signed them and affixed the company official seal, and the Engineer (chief supervising engineer under China's supervision regime) has reviewed and signed and affixed the practice seal. AI output may never be implemented without statutory sign-off; in content terms, four categories must be manually re-checked item by item: calculation verification, project overview and site data, current validity of the basis of preparation, and method statement specificity.
Applicable Codes
- GB/T 50502-2009 建筑施工组织设计规范
- 住建部令第37号 危险性较大的分部分项工程安全管理规定
- T/XCIA 3-2023 危险性较大的分部分项工程施工安全管理规程
- 建办质〔2018〕31号
Topic Positioning
When AI assists in preparing construction method statements, clarify which steps must be completed by humans — the statutory sign-off procedure (irreplaceable by AI) and the content-review priorities (AI high-risk zones) — to prevent the violation of 'AI-generated means implementable'.
Core Conclusions
(1) Statutory sign-off responsibility chain (GB/T 50502-2009, Clause 3.0.5): the overall project execution plan is approved by the technical responsible person of the main (general) contractor; the execution plan for individual structures is approved by the technical responsible person of the construction contractor or an authorized technician; general method statements are approved by the project's technical responsible person; key, difficult, and dedicated method statements are subject to expert review organized by the technical department of the construction contractor and approved by the technical responsible person. (2) Dedicated method statements for high-risk works (sub-divisional works involving significant hazards) (Ministry of Housing and Urban-Rural Development Order No. 37, Article 11): before implementation they must be reviewed and signed by the technical responsible person of the construction contractor with the company official seal affixed, and reviewed and signed by the Engineer (chief supervising engineer under China's supervision regime) with the practice seal affixed; method statements prepared by a subcontractor must be jointly reviewed, signed, and sealed by the technical responsible persons of both the main (general) contractor and the subcontractor. (3) AI output may not be implemented without going through the above sign-off process; legally it is only a 'draft', and the responsible entity is always the signatory. (4) Four priorities of manual review: calculation verification (load values, calculation diagrams, and stability and bearing capacity must be re-calculated by qualified personnel); project overview and site conditions (AI has no on-site perception and can easily fabricate plausible details); current validity of the basis of preparation (to prevent citing repealed versions, e.g., Order No. 37 must be read with the Order No. 47 amendment); method statement specificity and operability (to prevent template boilerplate). Personnel organization, emergency plans, and review and sealing of construction drawings likewise must be completed manually.
Applicable Boundaries
Applies to preparation-and-approval scenarios for project execution plans, execution plans for individual structures, general construction method statements, and dedicated method statements for high-risk works (sub-divisional works involving significant hazards); sub-divisional works involving significant hazards that exceed a certain scale additionally require a separate expert panel review (see the scope in Jianban Zhi [2018] No. 31). AI-generated drawings may not be used directly for construction and must be reviewed, signed, and sealed by registered personnel. This card does not cover site instructions / variation records or settlement matters beyond method statement sign-off.
Further Reading
GB/T 50502-2009 'Code for project execution plan of building engineering' Clause 3.0.5; MOHURD Order No. 37 'Safety management provisions for sub-divisional works with relatively high safety risks' Article 11 (later amended by Order No. 47); T/XCIA 3-2023 'Regulation for construction safety management of sub-divisional works with relatively high safety risks' Clause 5.1.2; for the content framework and scope determination of dedicated method statements for high-risk works, see the related dedicated card.
Keywords
- AI辅助编制施工方案
- 施工方案审批签字
- 危大工程专项施工方案
- 人工复核
- 施工组织设计审批
- 签字盖章责任链