Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Method for judging obvious omissions in a construction method statement: lock the statement type -> check against the framework -> four-dimension depth review

Three steps to judge whether a construction method statement has obvious omissions: (1) lock the statutory content framework by statement type — for sub-divisional works involving significant hazards (China's 危大工程 regime), check against the 9-item framework of Jianban Zhi [2021] No. 48 (missing any single item is an obvious omission); ordinary method statements are checked against the 8 basic contents of GB/T 50502-2009 chapter 6; (2) check item by item; (3) use four dimensions — procedural, completeness, relevance, compliance — to review substantive depth and identify hidden omissions where "a section exists but has no substance" (parameters, verification calculations, monitoring, staffing, emergency, seasonal measures).

Applicable Codes

  • GB/T 50502-2009 建筑施工组织设计规范
  • GB/T 50903-2013 市政工程施工组织设计规范
  • 建办质〔2021〕48号 危险性较大的分部分项工程专项施工方案编制指南
  • 住房和城乡建设部令第37号 危险性较大的分部分项工程安全管理规定
  • T/XCIA 3-2023 危险性较大的分部分项工程施工安全管理规程
  • GB/T 50319-2013 建设工程监理规范
  • T/HAEC 003-2020 工程监理资料管理标准化与信息化工作指南(房屋建筑工程)
  • JGJ 59-2011 建筑施工安全检查标准

Topic Positioning

A systematic method for judging whether a construction method statement is "obviously incomplete": first lock the statement type and check item by item against the statutory content framework, then review substantive depth on the four dimensions of procedural validity/completeness/relevance/compliance, identifying hidden omissions where "a section exists but has no substance". For method-statement compilers' self-checks and supervising-engineer review.

Core Conclusions

Three-step judgment:

  1. Lock the type: ordinary construction method statements are checked against GB/T 50502-2009 chapter 6 and GB/T 50903-2013 chapter 5; dedicated method statements for high-risk works add technical parameters, safe-operation requirements, inspection requirements etc. on top of ordinary method statements (e.g. the 7-item framework for crane dedicated method statements in JGJ 33-2012); dedicated method statements for sub-divisional works involving significant hazards are checked against the 9-item framework of Jianban Zhi [2021] No. 48 — project overview (incl. hazard identification and grading), basis of preparation, construction plan (programme of works + materials and equipment + labour), construction process technology (technical parameters/process flow/construction methods/operation requirements/inspection requirements), construction safeguard measures (organizational/technical/monitoring), staffing and division of management and operating personnel, acceptance requirements, emergency-response measures (incl. emergency supplies, rescue hospital and owner-unit contact numbers), calculation sheets and drawings. A dedicated method statement for high-risk works missing any single item is obviously incomplete.
  2. Check against the framework: ordinary method statement 8 basic contents — basis of preparation, project overview, construction arrangements (construction sequence/flow sections), programme of works (bar chart or network diagram), construction preparation and resource allocation, construction methods and process requirements (process flow/key operation points/quality inspection criteria), quality assurance, safety assurance measures.
  3. Review depth with the four properties — procedural (compile-review-approve chain compliant), completeness (all elements present), relevance (consistent with design documents/site conditions/project execution plan), compliance (no violation of mandatory provisions of codes). Typical hidden omissions: missing technical parameters; missing verification calculations; missing monitoring (no monitoring items/frequencies/alarm values); missing certified special-operation personnel staffing; missing emergency supplies and rescue information; missing winter/rainy/flood-season seasonal measures; generic templates copied without relevance.

Applicable Boundaries

Applies to omission review of ordinary construction method statements, dedicated method statements for high-risk works and dedicated method statements for sub-divisional works involving significant hazards for building and municipal works; does not apply to overall review of overall project execution plans or execution plans for individual structures (their framework is the eight parts of GB/T 50502-2009 clause 3.0.4). Determining the scope of sub-divisional works involving significant hazards and the expert panel review procedure for works exceeding larger thresholds are separate topics. Local standards may add refining requirements on top of the 9-item framework; the current local rules of the project location prevail.

Further Reading

The 9-item framework for sub-divisional works involving significant hazards: Jianban Zhi [2021] No. 48 "Guide for compiling dedicated method statements for sub-divisional works involving significant hazards", T/XCIA 3-2023 clauses 5.2.3 and 8.2.1, MOHURD Order No. 37; supervising-engineer review points: GB/T 50319-2013 clauses 5.5.3/5.5.5, T/HAEC 003-2020 clause 9.19.3, T/HAEC 011-2024 clause 9.19.3; safety-technical-measure inspection and rating: JGJ 59-2011 clause 3.1.3; dynamic method-statement adjustment: DB11/T 1745-2020 chapter 7, DB37/T 5164-2020 clause 3.4.3.

Keywords

Cited By