Building traceable engineering calculation working papers: a six-step management system (scope and granularity, unique numbering, version control, review sign-off, archiving, AI traces)
Traceability = a three-way closed loop: tracing sources forward, tracking destinations backward, and viewing changes across the process. Implementation in six steps: define scope and granularity -> unique numbering of calculation items -> version control (no overwriting; record changer/time/reason) -> three-level management with two-level review (reviewers must be registered cost engineers; review ratio at least 10%) -> process-document archiving (separate from deliverables, seven-document set, retention at least 5 years, signed handover) -> AI traces (model version + draft-to-final diff + intermediate calculation chain). Basis: GB/T 51095-2015, DB42/T 823-2021, GB 50860-2013, etc.
Applicable Codes
- GB/T 51095-2015 建设工程造价咨询规范
- DB42/T 823-2021 建设工程造价咨询质量控制规范
- GB 50860-2013 构筑物工程工程量计算规范
- GB/T 50328-2014 建设工程文件归档规范
- GB/T 50931-2013 医药工程建设项目设计文件编制标准
Topic Positioning
How to build engineering calculation processes into a traceable, re-checkable, auditable working-paper management system. Unlike "which intermediate processes to retain" (what to keep), this card solves "after keeping, how to number, manage versions, sign off, and archive".
Core Conclusions
The acceptance criteria of traceability are closed loops in three directions: forward (drawing basis -> formula -> result), backward (BOQ quantity -> working paper -> drawing rule -> calculator), process (who handled each version, what changed, why). Six implementation steps:
- Define scope and granularity: regular items keep "formula + source"; high-volume, high-value, dispute-prone items (foundations/rebar/concrete/doors-windows/earthwork) keep full derivation + cross-footing verification; the compilation basis is limited to approved construction design drawings and specifications (GB 50860-2013, Clause 3.0.1).
- Unique numbering: each calculation item gets a "project number - unit work - BOQ code - sequence - version" style identifier; without a number, nothing can be located.
- Version control: overwriting is forbidden; one change, one version; record changer/time/reason/content and maintain a version ledger.
- Review sign-off: three-level management (compile -> review -> approve) with two-level review (GB/T 51095-2015, Clause 3.3.2); the reviewer must be a registered cost engineer (DB42/T 823-2021, Clause 4.4.10), re-checking at no less than 10% with records (Clause 3.3.4); calculation-book covers carry design/proofread/review signatures (GB/T 50931-2013, Clause 5.3.6).
- Archiving: working papers are process documents, archived separately from deliverables (Clause 3.4.2); collected as a seven-document set — contract, handover checklist, implementation outline, consultation/inspection records, review record sheets, working papers, follow-up sheets (DB42/T 823-2021, Clause 4.5.5); retention of at least 5 years from archiving (Clause 4.5.7); handover signed and sealed by both parties (GB/T 50328-2014, Clause 6.0.6); the project leader manages the archive catalogue and borrowing records (Clause 3.4.4).
- AI traces: record tool/model version, generation time, and prompts; retain the diff between the AI draft and the human-approved final; keep the intermediate calculation chain alongside manual recalculation.
Applicable Boundaries
Applies to working-paper management of quantity calculation and cost-consultancy deliverables; granularity layering can be adjusted to project scale; 5 years is the minimum retention period — longer contractual or state provisions govern; this card does not cover the specific quantity-calculation rules themselves.
Further Reading
GB/T 51095-2015 "Code for construction cost consultancy" Clauses 3.3.2, 3.3.4, 3.4.2~3.4.4; DB42/T 823-2021 "Specification for quality control of construction cost consultancy" Clauses 4.4.10, 4.5.5, 4.5.7; GB 50860-2013 "Code for measurement of constructional works" Clause 3.0.1; GB/T 50328-2014 "Code for archiving of construction project documents" Clause 6.0.6; GB/T 50931-2013 Clause 5.3.6.