Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Re-review and re-demonstration procedures when a special scheme for dangerous sub-part works must be adjusted due to design or construction-condition changes

Per MOHURD Order No. 37 (as amended by Order No. 47) Article 16: a dedicated method statement for high-risk works must not be modified without authorization; where adjustment is genuinely required due to planning adjustment, design change (designer-issued variation), etc., the revised statement must be re-reviewed and re-verified by the expert panel under the original procedure. For ordinary adjustments, re-performing the Article 11 sign-off after revision suffices (technical responsible person of the contractor + official seal; the Engineer (chief supervising engineer under China's supervision regime) + practice seal); for major adjustments (affecting structural safety, fundamental change of working conditions, change of technology, duration over one year, and other significant changes), the statement must be re-compiled and the expert panel review re-organized (no fewer than 5 experts, unanimous opinion), with the sign-off re-performed after the panel review passes; construction must not continue until re-verification by the expert panel is completed.

Applicable Codes

  • 住房和城乡建设部令第37号/第47号《危险性较大的分部分项工程安全管理规定》
  • T/X CIA 3-2023 危险性较大的分部分项工程施工安全管理规程
  • 建办质〔2018〕31号
  • DB37/T 5164-2020 建筑施工现场管理标准

Topic Positioning

When a dedicated method statement for high-risk works needs modification during construction due to design changes (designer-issued variations), changes in construction conditions, technology adjustments, etc.: which situations require only re-review and sign-off, which require re-organizing the expert panel review, and the procedure red lines before and after the adjustment.

Core Conclusions

The contractor must not modify the dedicated method statement for high-risk works without authorization (MOHURD Order No. 37 Article 16; the same article as amended by Order No. 47 of 2019); where adjustment is genuinely required due to planning adjustment, design change (designer-issued variation), or external environment change, the revised statement must be re-reviewed and re-verified under the original procedure. Two tiers: (1) ordinary adjustments (not changing structural safety or the technological principle): after revision, re-perform the sign-off — check-and-sign by the technical responsible person of the contractor + company official seal, and review-and-sign by the Engineer (chief supervising engineer under China's supervision regime) + practice seal; (2) major adjustments (affecting structural safety, fundamental change of working conditions, change of construction technology, duration over one year, and other significant changes, see the corresponding clauses of the association standard): the statement must be re-compiled and the expert panel review re-organized — experts selected from the housing and construction authorities' expert pool, no fewer than 5, with recusal of interested parties; the panel must form a unanimous conclusion of "pass / pass after revision / fail"; after passing, the sign-off procedure is re-performed, and any fund or duration adjustment involved is handled by the employer as agreed. Construction must not continue until re-verification by the expert panel is completed.

Applicable Boundaries

Applies to process management of sub-divisional works involving significant hazards in building and municipal infrastructure works. This card targets "statement adjustments triggered by condition changes during construction"; first-time compilation and panel review, and the follow-up handling of "fail / pass after revision" conclusions, are adjacent procedures (see the cited cards). Provincial detailed rules may tighten and expand the scope of sub-divisional works involving significant hazards (stricter only), and local requirements take priority over the national list in execution.

Further Reading

MOHURD Order No. 37 (as amended by Order No. 47) Articles 16, 11, 12, 13; T/XCIA 3-2023 "Regulation for Construction Safety Management of Sub-divisional Works with Relatively High Safety Risks" Clauses 5.3.8, 5.3.10, 6.2.2; Appendices 1/2 of Jianban Zhi [2018] No. 31; DB37/T 5164-2020 management process for sub-divisional works involving significant hazards (compilation -> review -> expert panel review -> revision -> approval -> disclosure -> implementation -> inspection -> acceptance -> archiving).

Keywords

Cited By