Review by the supervision unit of project execution plans and (special) construction method statements: basis, content and procedure (GB/T 50319-2013)

Supervision review of project execution plans/special method statements: the contractor's technical responsible person checks, certifies and signs, and affixes the official seal, before submission with the review-and-approval form (Table B.0.1); the Engineer (chief supervising engineer under China's supervision regime) organizes the professional supervising engineers to review, and after certification and sign-off reports to the employer; the works must not commence before the supervision review confirmation. Five review items for the project execution plan (compliance of the compilation-and-approval procedure; construction schedule, method statement and quality assurance measures conforming to the construction contract; resource-supply plans; safety-technical measures conforming to mandatory standards; general site layout) plus the emergency plan; special method statements for sub-divisional works involving significant hazards require the Engineer's review signature + practice seal, and works exceeding the prescribed scale additionally require checking the expert panel review and safety verification results; where patrols find implementation not in accordance with the method statement, issue a supervising engineer's notice / instruction, and in serious cases order suspension of the works and report.

Applicable Codes

  • GB/T 50319-2013 建设工程监理规范
  • 住建部令第37号 危险性较大的分部分项工程安全管理规定
  • 建办质〔2018〕31号

Topic Positioning

The basis, review content, submission-and-certification procedure, and special requirements for special method statements for sub-divisional works involving significant hazards when the supervision unit (project supervision body) reviews project execution plans and (special) construction method statements. Basis: GB/T 50319-2013 Clauses 5.1.6, 5.5.3, 5.5.5 and MOHURD Order No. 37.

Core Conclusions

Submission procedure: the contractor's technical responsible person checks, certifies and signs, and affixes the official seal, before submission with the review-and-approval form (Table B.0.1); the Engineer (chief supervising engineer under China's supervision regime) organizes the professional supervising engineers to review — where revision is needed, written opinions are issued and the submission is returned for re-submission; where requirements are met, the Engineer certifies and signs and reports to the employer; the works must not commence before the supervision review confirmation; group works and phased drawing release may be submitted for approval by stages; where adjustment is needed, the review procedure is re-entered. Five review items for the project execution plan: (1) compliance of the compilation-and-approval procedure; (2) construction schedule, construction method statement and quality assurance measures conforming to the construction contract; (3) funds, labour, materials and equipment resource-supply plans meeting construction needs; (4) safety-technical measures conforming to the mandatory standards for engineering construction; (5) scientific and reasonable general site layout. The work-safety accident emergency plan (organization system, responsibilities, early-warning and prevention systems, emergency measures) must also be reviewed. Special method statement review: compliance of the compilation-and-approval procedure and safety-technical measures conforming to mandatory standards; for sub-divisional works involving significant hazards that exceed the prescribed scale, additionally check the expert panel review and the safety verification results. Special method statements for sub-divisional works involving significant hazards may be implemented only after the contractor's technical responsible person checks, certifies and signs + the company official seal, and the Engineer reviews, certifies and signs + the practice seal. Where patrols find implementation not in accordance with the method statement, issue a supervising engineer's notice / instruction; in serious cases order suspension of the works and report to the employer; where correction is refused, promptly report to the competent authorities.

Applicable Boundaries

This card is a general framework for building and municipal works; the contractor's internal compilation-and-approval authority, determination of the scope of sub-divisional works involving significant hazards, and organization of expert panel reviews are set out in the cited cards; local regulations refine submission time limits, forms and seals — follow the locality.

Further Reading

GB/T 50319-2013 Clauses 5.1.6, 5.5.3, 5.5.5 and Table B.0.1; MOHURD Order No. 37 Articles 11-13; Jianban Zhi [2018] No. 31; DB13(J)/T 8161-2019 Clauses 6.2.5, 8.4.13; T/HAEC 003-2020 Section 10.29.