Commencement conditions and the issuing procedure of the commencement order: GB/T 50319-2013 Article 5.1.8's four conditions and Beijing's pre-start checks (DB11/T 382-2017 Article 3.1.10)
GB/T 50319-2013 Code for Construction Project Management (Supervision), Article 5.1.8, sets the commencement conditions: design briefing and drawing review completed; the project execution plan signed by the chief supervising engineer; the builder's site quality and safety management systems established with staff, plant and materials in place; access roads and water, power and communications meeting commencement needs - and, upon the employer's approval, the chief supervising engineer issues the commencement order. Beijing adds DB11/T 382-2017 Article 3.1.10's pre-start checks: the construction permit issued; design briefing and drawing review done; the execution plan reviewed by the chief supervising engineer; survey control pegs checked and passed; special protection measures for adjoining buildings and underground pipelines in place.
Applicable Codes
- 《建设工程监理规范》GB/T 50319-2013 第5.1.8条
- 《北京市建设工程监理规程》DB11/T 382-2017 第3.1.10条
- 《建筑工程施工许可管理办法》(住房和城乡建设部令第52号)第四条
- 《建设工程质量管理条例》(国务院令第279号)第十三条
Scope of the question
The statutory and code conditions for commencing works and who issues the commencement order under what procedure - for checking formalities and documents at the commencement-preparation stage.
Core conclusions
1. National standard (nationwide) GB/T 50319-2013 Code for Construction Project Management (Supervision), Article 5.1.8, commencement conditions:
- Design briefing and drawing review completed;
- The project execution plan signed by the chief supervising engineer;
- The builder's site quality and safety management systems established, with staff, plant and materials in place;
- Access roads and water, power and communications meeting commencement needs. Once met, upon the employer's approval, the chief supervising engineer issues the commencement order.
2. Beijing refinements DB11/T 382-2017 Code for Construction Project Management (Supervision) of Beijing, Article 3.1.10, details the pre-start checks: the construction permit issued by the authority; design briefing and drawing review completed; the execution plan reviewed by the chief supervising engineer; survey control pegs checked and passed; special protection measures for adjoining buildings and underground pipelines in place.
Applicability limits
- This article settles whether works may start on the supervision procedure and the order may issue - not whether all statutory formalities are done: the construction permit and quality-safety supervision follow the Construction Law, the Quality Management Regulation and the Measures for Construction Permit Administration - both must hold together.
- DB11/T 382-2017 is a Beijing local standard; other provinces use their local supervision rules (check items and forms may differ).
- The commencement date follows the order or start report; contract-time computation and condition checking are independent; sector works (railway, water, highway) have their own start-report regimes.
Further reading
- GB/T 50319-2013, Article 5.1.8 (commencement conditions and order), and Chapter 5 documents and forms.
- DB11/T 382-2017, Article 3.1.10.
- Companion checks: Measures for the Administration of Construction Permits, Article 4; Quality Management Regulation, Article 13.
Keywords
- 开工条件
- 工程开工令
- the Engineer (chief supervising engineer under China's supervision regime)
- 建设工程监理规范
- GB/T 50319
- DB11/T 382
- 开工前核查