the Engineer (chief supervising engineer under China's supervision regime)
- 01
Organisers, required attendees and pass criteria of the four-level construction quality acceptance of building works (GB 50300-2013 chapters 5 and 6; GB 55032-2022 section 4.3)
The four levels advance step by step: inspection lot (smallest unit) - s…
GB 50300-2013 · Unified Standard for Constructional Quality Acceptance of Building Engineering 第4.0.1~4.0.7、5.0.1~5.0.4、6.0.1~6.0.6条及App. B、App. DGB 55032-2022 · General Code for Construction Quality Control of Building and Municipal Engineering 第4.1.1、4.3.1、4.3.3、4.3.4条GB/T 2828.1-2012《计数抽样检验程序 第1部分:按接收质量限(AQL)检索的逐批检验抽样计划》2026-10-25 - 02
Commencement conditions and the issuing procedure of the commencement order: GB/T 50319-2013 Article 5.1.8's four conditions and Beijing's pre-start checks (DB11/T 382-2017 Article 3.1.10)
GB/T 50319-2013 Code for Construction Project Management (Supervision)…
《建设工程监理规范》GB/T 50319-2013 第5.1.8条《北京市建设工程监理规程》DB11/T 382-2017 第3.1.10条《建筑工程施工许可管理办法》(住房和城乡建设部令第52号)第四条2026-10-12 - 03
Review by the supervision unit of project execution plans and (special) construction method statements: basis, content and procedure (GB/T 50319-2013)
Supervision review of project execution plans/special method statements…
GB/T 50319-2013 建设工程监理规范住建部令第37号 危险性较大的分部分项工程安全管理规定建办质〔2018〕31号2026-09-25 - 04
Supervision plan and supervision implementation details — the preparation/approval responsibility chain and their relationship (GB/T 50319-2013 cl. 4.2.2, 4.3.2)
Per GB/T 50319-2013: the supervision plan is compiled by the chief super…
GB/T 50319-2013 建设工程监理规范(第4.2.2条、第4.3.2条)住建部令第37号 危险性较大的分部分项工程安全管理规定DB11/T 382-2017 建设工程监理规程2026-09-25 - 05
Compilation, review, and approval responsibility chain for dedicated method statements for high-risk works concerning sub-divisional works involving significant hazards (MOHURD Order No. 37)
The dedicated method statement for high-risk works concerning sub-divisi…
住房和城乡建设部令第37号(2019年47号令修正)第十、十一、十二条建办质〔2018〕31号 附件1/2建办质〔2021〕48号 专项施工方案编制指南2026-09-25 - 06
Regulation on Quality Management of Construction Works art. 37: without the supervision engineer's / chief supervision engineer's signature, materials may not be used, the next process may not proceed, progress payments are not made, and completion acceptance is not held
Art. 37 of the Regulation (2019 revision, Decree No. 714) sets a two-tie…
《建设工程质量管理条例》第三十七条(国务院令第279号发布,第714号修改,2019年修订)《铁路建设工程质量监督管理规定》第三十九条(交通运输部令2021年第35号)2026-09-25 - 07
The Engineer in FIDIC contracts: an employer-appointed contract-administration office, the 1999->2017 neutralization of its role, and its functional mapping onto the domestic supervision/chief supervision engineer system
The FIDIC Engineer is not a professional title or the designer: it is a…
FIDIC Conditions of Contract for Construction (Red Book) First Edition 1999, Sub-Clause 3.1/3.2FIDIC Conditions of Contract for Plant and Design-Build (Yellow Book) First Edition 1999, Sub-Clause 3.1FIDIC Conditions of Contract 2017 (Second Edition) 红/黄皮书 Sub-Clause 3.1/3.4/3.72026-09-25 - 08
Management of sub-divisional works involving significant hazards - overview: scope determination, dedicated method statement with dual-signature approval, expert review, implementation, monitoring and acceptance, three-party liabilities (MOHURD Order No. 37 framework)
The hazardous-works chain: scope per MOHURD Order No. 37 plus the Jian B…
住建部令第37号(第47号令修正)危险性较大的分部分项工程安全管理规定(第十至十三、二十一、三十六、三十七条)建办质〔2018〕31号 关于实施危大工程安全管理规定有关问题的通知(范围清单与论证组织)GB/T 50319-2013 建设工程监理规范2026-09-25 - 09
Rights to propose, compile and approve design variations: any of four parties may propose, only the original designer may modify, three-level approval
Any of the employer, designer, contractor or supervisor may propose a de…
《建设工程勘察设计管理条例》(国务院令第687号,2017修订)CJJ/T 91-2017 风景园林基本术语标准DB13(J)/T 8161-2019 建设工程监理工作标准2026-09-25 - 10
On-site acceptance of sub-divisional works involving significant hazards (China's safety-management regime for high-risk works, MOHURD Order No. 37): composition of the acceptance personnel, organising parties and the dual-signature pass requirement
Under Article 21 of MOHURD Order No. 37 (as amended by Order No. 47) and…
住建部令第37号《危险性较大的分部分项工程安全管理规定》第二十一条、第三十五条(47号令修正)建办质〔2018〕31号第三条DB22/T 5115-2022 第5.15节2026-09-25