Organisers, required attendees and pass criteria of the four-level construction quality acceptance of building works (GB 50300-2013 chapters 5 and 6; GB 55032-2022 section 4.3)

The four levels advance step by step: inspection lot (smallest unit) - subdivisional work - divisional work - unit work (completion acceptance). Organisers: inspection lots and subdivisional works are both organised by the professional supervising engineer; divisional works are organised by the chief supervising engineer, with the ground and foundation division additionally attended by the project leaders of the investigation and design units plus the heads of the contractor's technical and quality departments, and the main structure and energy conservation divisions additionally attended by the design unit's project leader plus the heads of the contractor's technical and quality departments; the unit work acceptance is organised by the employer's project leader with the project leaders of the investigation, design, supervision and contracting units (GB 50300-2013 clause 6.0.6 has been annulled by GB 55032-2022; apply item 5 of clause 4.3.4 of that code instead). Pass criteria: an inspection lot passes when all dominant items conform on sampling, general items pass sampling with a qualifying point rate meeting the relevant sector code and no serious defects, and complete construction operating bases and acceptance records exist; a subdivisional work passes when all its inspection lots pass with complete records; a divisional work passes when all its subdivisional works pass, quality control data are complete, sampling tests on safety, energy conservation, environmental protection and main service functions conform, and visual quality conforms; a unit work passes on five counts (all divisional works pass, quality control data complete, test data on safety, energy conservation, environmental protection and main service functions complete, spot checks of main service functions conforming, visual quality conforming).

Applicable Codes

  • GB 50300-2013 · Unified Standard for Constructional Quality Acceptance of Building Engineering 第4.0.1~4.0.7、5.0.1~5.0.4、6.0.1~6.0.6条及App. B、App. D
  • GB 55032-2022 · General Code for Construction Quality Control of Building and Municipal Engineering 第4.1.1、4.3.1、4.3.3、4.3.4条
  • GB/T 2828.1-2012《计数抽样检验程序 第1部分:按接收质量限(AQL)检索的逐批检验抽样计划》
  • GB/T 50319《建设工程监理规范》

Topic positioning

This card answers three execution-level questions about construction quality acceptance of building works - who organises each of the four levels, who must attend, and how a pass is judged - on the basis of GB 50300-2013 'Unified standard for construction quality acceptance of building works', chapter 5 (pass criteria) and chapter 6 (procedures and organisation), and the compulsory code GB 55032-2022 'General code for construction quality control of building and municipal works', section 4.3. The four-level division system itself is covered by a separate card.

Core conclusions

1. The acceptance chain (progressive levels) Construction quality is accepted level by level during construction along unit work - divisional work - subdivisional work - inspection lot, which in reverse forms the acceptance chain: the inspection lot is the smallest unit of work acceptance and the basis for acceptance of subdivisional, divisional and unit works; a subdivisional work consists of one or several inspection lots; a divisional work consists of several subdivisional works; unit work acceptance, also called completion quality acceptance, is the last and most important acceptance before the building is put into use. A single acceptance after completion is neither scientific nor reasonable, so checking and acceptance must proceed level by level.

2. Organiser and required attendees at each level (GB 50300-2013 chapter 6; GB 55032-2022 clauses 4.3.1, 4.3.3)

Level Organiser Attendees Basis
Inspection lot Professional supervising engineer The contractor's project quality inspector, trade foreman, etc.; the contractor must finish self-checking and rectifying before acceptance GB 50300-2013 6.0.1; GB 55032-2022 4.3.1
Subdivisional work Professional supervising engineer The contractor's project technical leader for the trade, etc. GB 50300-2013 6.0.2
Divisional work Chief supervising engineer The contractor's project leader and project technical leader, etc.; the ground and foundation division additionally requires the project leaders of the investigation and design units plus the heads of the contractor's technical and quality departments; the main structure and energy conservation divisions additionally require the design unit's project leader plus the heads of the contractor's technical and quality departments GB 50300-2013 6.0.3; GB 55032-2022 4.3.3
Unit work Employer's project leader Project leaders of the supervision, contracting, design and investigation units; the contractor's technical and quality heads should also attend GB 50300-2013 6.0.6 (annulled by GB 55032-2022 from 1 January 2022); GB 55032-2022 4.3.4 item 5

Operating detail of subdivisional work acceptance: under the professional supervising engineer's organisation, the contractor's project technical leader may compile the acceptance records of all inspection lots and submit them to the professional supervising engineer for review; once confirmed as conforming, the project technical leader for the trade signs the subdivisional work quality acceptance record, followed by the professional supervising engineer's sign-off; where the conclusion on an inspection lot is doubted or disputed, an on-site check shall be made.

The pre-procedure chain for unit work acceptance: the contractor self-checks after completion - the chief supervising engineer organises the completion pre-acceptance with the professional supervising engineers (project manager, project technical leader, etc. attending; method, procedure and requirements identical to completion acceptance) - defects are rectified by the contractor - after rectification the contractor submits the completion report to the employer and applies for completion acceptance - the employer's project leader organises the completion acceptance. GB 55032-2022 clause 4.3.4 further fixes each party's deliverable: the investigation unit prepares the investigation quality check report; the design unit checks the design documents and design changes and prepares the design quality check report; the contractor, after passing self-check, prepares the completion report; the supervision unit organises the completion pre-acceptance after self-check passes and prepares the quality assessment report once pre-acceptance passes; the employer, after pre-acceptance passes, organises the project leaders of the supervision, contracting, design, investigation and other relevant units for the completion acceptance; for municipal works the facility management unit shall attend the acceptance.

3. Pass criteria at each level (GB 50300-2013 chapter 5)

  • Inspection lot (5.0.1): (1) the quality of dominant items must pass sampling inspection in full (dominant items admit no non-conforming results); (2) the quality of general items must pass sampling inspection - with attribute sampling the qualifying point rate must meet the relevant sector acceptance code and no serious defects may exist; first and second sampling under normal inspection may be judged per Annex D; (3) complete operating bases for construction and quality acceptance records must exist.
  • Subdivisional work (5.0.2): (1) all constituent inspection lots must have passed acceptance; (2) the acceptance records of the constituent inspection lots must be complete.
  • Divisional work (5.0.3): (1) all constituent subdivisional works must have passed acceptance; (2) quality control data must be complete; (3) sampling test results concerning safety, energy conservation, environmental protection and main service functions must conform to the relevant provisions; (4) visual quality must conform to requirements.
  • Unit work (5.0.4): (1) all constituent divisional works must have passed acceptance; (2) quality control data must be complete; (3) the test data of constituent divisional works concerning safety, energy conservation, environmental protection and main service functions must be complete; (4) spot checks of main service functions must conform to the relevant sector acceptance codes; (5) visual quality must conform to requirements.

4. Quantified rules of attribute sampling in Annex D (commentary on 5.0.1) General items, normal inspection, first sampling: at a sample size of 20, up to 5 non-conforming specimens means a pass, 6 or more means a fail. Second sampling: of a first sample of 20, up to 3 non-conforming passes, 6 or more fails, 4 or 5 triggers a second sample (sample size again 20, 40 in total); a sum of non-conforming over the two samples of up to 9 passes, 10 or more fails. Sample sizes in the table are not continuous and the acceptance number must be rounded - e.g. at sample size 15 the table interpolation gives 3.571, rounded to acceptance number 4 and rejection number 5. The sampling plan shall follow the relevant sector acceptance code; where the code is silent, a single sampling plan may be used, or the employer, designer, supervisor and contractor may agree a double sampling plan according to the characteristics of the object tested (per GB/T 2828.1-2012).

5. The division plan must be approved first (GB 50300-2013 4.0.7) Before construction the contractor prepares the division plan for subdivisional works and inspection lots, which the supervision unit reviews; for subdivisional works and inspection lots not covered by Annex B or the relevant sector acceptance codes, the employer may organise the supervision and contracting units to agree them before construction according to the specifics of the works, and the construction technical documentation and acceptance follow accordingly. This is a must-check item in pre-start documentation checks.

Applicability boundaries

  • GB 50300-2013 applies to construction quality acceptance of building works; division and acceptance of municipal works (roads, bridges, pipelines, rail transit, utility tunnels, etc.) follow GB 55032-2022 and the relevant sector acceptance standards, and unit works may be divided by contract section combined with service function.
  • GB 50300-2013 clause 6.0.6 has been annulled by GB 55032-2022 (from 1 January 2022); the organisation of unit work completion acceptance is governed by GB 55032-2022 clause 4.3.4 (substantively continued and refined); GB 55032-2022 is a compulsory engineering code applicable in full, and where current standards disagree with it, it prevails.
  • Where a sector acceptance code sets stricter rules at any level (e.g. minimum sample sizes, lists of dominant items), those rules prevail; the pass criteria in this card are the level-generic conditions and do not contain the specific test indices of each trade item.
  • The 'sample size' and sampling number of an inspection lot are bounded below by the minimum sample sizes of the relevant sector acceptance code; they may be increased at acceptance but never reduced.
  • Visual quality is not concluded 'pass or fail' but graded 'good', 'fair' or 'poor'; 'poor' points must be rectified - do not force it into a pass-rate framework.
  • Pass criteria only settle whether acceptance is passed; the routes after a failed acceptance (rectification, testing and appraisal, strengthening) are covered by a separate card.

Further reading

  • GB 50300-2013 'Unified standard for construction quality acceptance of building works': chapter 4, clauses 4.0.1 (levels), 4.0.2 (unit works), 4.0.3 (divisional works), 4.0.4 (subdivisional works), 4.0.5 (inspection lots), 4.0.7 (division plan approval); chapter 5, clauses 5.0.1~5.0.4 (pass criteria at each level); chapter 6, clauses 6.0.1~6.0.6 (organisation at each level); Annex B (division tables of subdivisional and divisional works), Annex D (attribute sampling tables D.0.1-1, D.0.1-2).
  • GB 55032-2022 'General code for construction quality control of building and municipal works': 4.1.1 (four-level division), 4.3.1 (inspection lot organisation), 4.3.3 (divisional work organisation), 4.3.4 (unit work completion acceptance procedure and each party's reports).
  • GB/T 2828.1-2012 'Sampling procedures for inspection by attributes', part 1; GB/T 50319 code for construction project supervision (completion pre-acceptance requirements).