Rescue organization for poisoning/asphyxiation in confined-space work: protection-first principles, response procedure, and code basis
When workers are poisoned or asphyxiated in a confined space, rescuers must wear isolation-type respiratory protection (long-tube or positive-pressure air breathing apparatus) to enter - unprotected rescue is prohibited, and at least one person must remain outside for watch and liaison (GB/T 50484-2019 Clause 3.4.15). Response: call emergency services (119/120) first and stop work; untrained, unequipped persons are forbidden to enter (T/CAS 752-2023 Clause 7.2). Prevention red line: confined-space work with H2S/CO poisoning risk that lacks identification, ledger and warning signs, approval, "ventilate-test-then-work", or on-site attendants is judged a major accident hazard (MEM Order No. 10, Article 13).
Applicable Codes
- GB/T 50484-2019 石油化工建设工程施工安全技术标准 第3.4.13、3.4.15条
- GB 51201-2016 沉管法隧道施工与质量验收规范 第14.2.4条
- T/CAS 752-2023 城镇排水管道有限空间作业技术规程 第7.2条
- DB33/T 1149-2018 城镇供排水有限空间作业安全规程 第6.3.3条
- 应急管理部令第10号 工贸企业重大事故隐患判定标准 第十三条
Topic Positioning
How to organize rescue when workers are poisoned or asphyxiated in confined spaces (towers, tanks, reactors, pipe shafts, tunnel elements, ship holds, etc. - restricted entry/exit, poor ventilation) in construction, primarily petrochemical but also immersed-tube tunnels and municipal drainage - covering three protection-first lines, the standard response procedure, and the code basis.
Core Conclusions
[Three iron rules of rescue organization] (1) Call for help and stop work first; blind rescue is strictly forbidden (nearly all casualty escalation stems from unprotected rescue); (2) rescuers must wear isolation-type breathing apparatus (long-tube or positive-pressure air SCBA) to enter; (3) at least one person stays outside for watch and liaison, keeping communication open and attending throughout.
[Code clauses]
- GB/T 50484-2019 Clause 3.4.15: "In poisoning/asphyxiation emergencies, rescuers shall enter the confined space wearing long-tube breathing apparatus; unprotected rescue is prohibited, and at least one person shall remain outside for watch and liaison."
- Same standard 3.4.13: "When entering confined spaces that may contain H2S or other toxic/asphyxiating gases, workers shall wear positive-pressure air breathing apparatus and carry gas alarms, and evacuate immediately upon alarm."
- GB 51201-2016 "Code for construction and acceptance of immersed tube tunnels", Clause 14.2.4: hazard identification and risk assessment before work with defined roles of leader, workers, and outside attendant; work permits with strict approval; the "three no-entry" rule (no permit, no implemented safety measures, no attendant - no entry); gas sampling 30min before entry with oxygen 19.5%-23.5% acceptable, re-analysis at least every 2h for long jobs, stop and evacuate on exceedance; ventilate continuously but never inject oxygen; rotate shifts; lighting not above 36V, below 12V in damp or confined spaces, with damp/explosion-proof fittings and tools; stock positive-pressure SCBA and emergency torches in elements; hot work inside requires oxygen and combustible-gas testing with continuous monitoring; attendants shall never leave post and keep contact - "in poisoning/asphyxiation emergencies, rescuers must wear isolation-type apparatus and at least one person liaises outside; blind rescue without conditions is prohibited to avoid escalation"; on changing conditions endangering safety, evacuate at once, and re-approval is required to resume; after completion, workers, attendants, and the construction lead jointly confirm no persons or debris remain before closing.
- T/CAS 752-2023 "Technical regulation for confined-space operations in urban drainage pipelines", Clause 7.2: after an incident, the site lead immediately stops work, checks trapped workers' status, reports to the unit lead, and organizes safe rescue where conditions allow. "Entry by untrained personnel or those without rescue equipment is prohibited. Dial 119/120 or seek other professional rescue promptly; the unit lead organizes rescue and reporting per the emergency plan."
- DB33/T 1149-2018 "Safety regulation for confined-space operations in urban water supply and drainage", Clause 6.3.3: "In an incident, the attendant shall report promptly; rescuers shall protect themselves with necessary breathing apparatus and equipment. Blind rescue causing escalation is strictly prohibited." Rescuers entering must ensure their own safety first.
- MEM Order No. 10 "Criteria for determining major accident hazards in industrial and trade enterprises", Article 13 (statutory prevention red line): for enterprises with H2S/CO poisoning risk in confined-space work, any of the following is a major hazard: (1) no identification, no safety ledger, and no clear warning signs; (2) no work approval, no "ventilate-test-then-work", or no on-site attendant.
[Standard response procedure] (1) On discovery: attendant immediately calls 119/120 and reports to the lead, stops work, guards the entrance, and never enters or urges others in rashly; (2) Assess and report: the site lead ascertains trapped workers' status, the hazard gas (H2S, CO, oxygen deficiency), and the space geometry, reports upward, and the unit lead activates the emergency plan; (3) Protected rescue: only trained, equipped personnel enter with long-tube or positive-pressure apparatus, safety belts and lifelines, tripods and rescue ropes as needed, with at least one outside watcher; (4) Treat and transport: on extraction, immediate first aid (fresh air, airway, CPR) and hospital transport, briefing 120 on injuries. When protection cannot be confirmed, wait for professional 119 rescue rather than risk unprotected entry.
Applicable Boundaries
Applies to rescue organization and pre-control of poisoning/asphyxiation in confined spaces of petrochemical construction, immersed-tube tunnels, and urban drainage. The codes differ by sector/region (GB/T 50484-2019 petrochemical; GB 51201-2016 immersed tunnels; T/CAS 752-2023 drainage; DB33/T 1149-2018 Zhejiang) but the rescue principles (protected entry, outside watch, no blind rescue) are universal. Rescue presupposes compliance - "ventilate-test-then-work", approval, and on-site attendants are statutory and the material basis of effective rescue; this card omits detailed ventilation/testing parameters (except the 19.5%-23.5% oxygen window and re-test intervals) - see the codes for details.
Further Reading
See GB/T 50484-2019 Clauses 3.4.13 and 3.4.15; GB 51201-2016 Clause 14.2.4; T/CAS 752-2023 Clause 7.2 (emergency response); DB33/T 1149-2018 Clause 6.3.3; MEM Order No. 10, Article 13. This card summarizes rescue organization only; full clauses per the official texts.