Determining personnel allocation in construction method statements: quantity x quota norms (prescribed resource consumption standards) for labour demand, back-calculating headcount from duration, and compiling the labour plan table
Personnel are allocated at two levels: management personnel per management functions; workers per specialty, trade, and batch based on quantities, programme (of works), and economic principles. Four-step headcount method: (1) compute quantity Q (unit of measurement consistent with the quota norms) -> (2) derive labour demand P from labour quota norms: P = Q x H (unit labour-time norm) or P = Q / S (output norm) -> (3) back-calculate headcount from duration R = P / (D x B) (D = duration, B = shifts per day) -> (4) compile the staged, by-trade labour allocation table per the programme (of works) (preferably refined to specialty trades). Special method statements for sub-divisional works involving significant hazards must specify, category by category in accordance with Jianban Zhi [2021] No. 48, the allocation and division of duties among construction management personnel, full-time production safety management personnel, special operation personnel, and other workers.
Applicable Codes
- GB/T 50502-2009 建筑施工组织设计规范
- GB 51114-2015 露天煤矿施工组织设计规范
- GB/T 51111-2015 露天金属矿施工组织设计规范
- GB/T 50795-2012 光伏发电工程施工组织设计规范
- GB/T 51310-2018 地下铁道工程施工标准
- 建办质〔2021〕48号 危大工程专项施工方案编制指南
- 住建部令第37号 危险性较大的分部分项工程安全管理规定
Topic Positioning
Methods for determining personnel allocation/labour plans in construction method statements (and project execution plans (construction methodology and site organization)): computing labour demand, back-calculating headcount from duration, compiling the labour plan table, plus staffing requirements of special method statements for sub-divisional works involving significant hazards.
Core Conclusions
Personnel are allocated at two levels: management personnel per management functions; workers per specialty, trade, and batch based on quantities, programme (of works), and economic principles. Headcount is determined in four steps: (1) compute quantities Q per construction methods and construction section division (unit of measurement consistent with the quota norms); (2) derive labour demand P from labour quota norms: P = Q x H (unit labour-time norm) or P = Q / S (output norm); (3) back-calculate headcount from duration: R = P / (D x B) (D = duration, B = shifts per day); (4) compile the staged, by-trade labour allocation table per the programme, preferably refined to specialty trades. The deliverable is the labour plan table (stage/trade x headcount x mobilisation/demobilisation times), which must match the programme, avoid idle labour, and stay balanced and continuous.
Applicable Boundaries
Applies to project execution plans/construction method statements compiled under the GB/T 50502 system for building, municipal, open-pit mine, and PV projects; where work items are not covered by the quota manuals, contractor's in-house norms may be used for estimation. The allocation and division of duties for workers in special method statements for sub-divisional works involving significant hazards must be specified category by category (management personnel, full-time production safety management personnel, certified special operation personnel, others), per MOHURD Order No. 37 and Jianban Zhi [2021] No. 48. Headcounts are theoretical values to be checked against working faces and interfacing of construction sequences; for crash-programme scenarios see the cited cards.
Further Reading
GB/T 50502-2009 Clauses 4.4.4, 5.4.2, 6.4.2; GB 51114-2015 Clause 8.2.12 (formula D = P/(R x B)); GB/T 51111-2015 Clause 6.4.1 (labour input plan table format); GB/T 50795-2012 Clause 4.4.3; GB/T 51310-2018 Clause 4.7.1; for special method statements see Jianban Zhi [2021] No. 48 and MOHURD Order No. 37.
Keywords