Back-calculating labour and machinery required for catch-up from remaining work quantities (two-step method + six-step workflow)
Two-step back-calculation: ① total worker-days/machine-shifts = Σ(remaining quantity × unit labour-time norm / machine-shift consumption quota norms (prescribed resource consumption standards)), using construction quota norms or contractor's in-house norms; ② daily average demand = total ÷ remaining constructible days (calendar days minus non-workable days, multi-shift multiplied by the shift factor); increment required = daily demand − current input; machines rounded up. Must check work-face constraints, add resources only on the critical path, derate for efficiency, and never arbitrarily compress a reasonable duration.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准
- GB/T 50875-2013 工程造价术语标准
- JGJ/T 121-2015 工程网络计划技术规程
- GB 51114-2015 露天煤矿施工组织设计规范
- GB 55032-2022 建筑与市政工程施工质量控制通用规范
- DB11/T 1710-2019 智慧工地技术规程
Topic Positioning
The resource back-calculation method for catch-up (acceleration) scenarios: multiply remaining quantities by consumption under quota norms to derive total worker-days/machine-shifts, divide by remaining constructible days to get daily demand, then compare with current input to obtain the labour and machinery increments. For programme-recovery correction, duration back-planning, and resource reallocation.
Core Conclusions
Two-step method: ① total demand = Σ(remaining quantity × unit labour-time norm or machine-shift consumption quota norms), in worker-days/machine-shifts; ② daily demand = total ÷ remaining constructible days (calendar days minus non-workable days from rain/snow, water/power outages, etc.; multi-shift systems multiplied by the shift factor); increment = daily demand − current input; machine counts rounded up. Six-step workflow: inventory remaining quantities (based on qualified quantities that have passed measurement of the works, certification and sign-off, GB/T 50500-2024 Clause 7.1.2) → fix remaining constructible days → look up consumption under quota norms (prefer construction quota norms/contractor's in-house norms — GB/T 50875-2013 makes construction quota norms the basis for organizing production; budget quota norms contain range differences and should not be used directly for site labour) → sum item by item → compute daily demand → compare with current input. Five cautions: adding labour under work-face constraints is non-linear — check against accommodable headcount; resources added only on critical-path activities are effective (GB 51114-2015 duration-optimization steps); newly mobilized crews have a learning curve — theoretical values should be inflated by dividing by 0.85–0.95; machinery needs mobilization lead time and rental availability; a reasonable duration must not be arbitrarily compressed, and major programme adjustments require employer/supervisor approval (GB 55032-2022, Clause 2.0.6).
Applicable Boundaries
Applies to programme recovery and resource estimating during construction, assuming remaining quantities and quota norms are clear and remaining workdays can be classified as constructible. This is a scheme-estimation method and does not replace pricing on a bill of quantities basis; labour should be computed by trade (rebar/carpentry/concrete crews differ in output); where the work face is limited, adding labour alone is futile — switch to more machinery, more shifts, or process changes (the "limited resources, shortest duration" ranking-optimization idea of JGJ/T 121-2015).
Further Reading
GB/T 50500-2024, Clause 7.1.2 (measurement of the works); GB/T 50875-2013, Section 2.3 (labour quota norms, worker-day consumption, construction quota norms/budget quota norms hierarchy); JGJ/T 121-2015, Section 6.3 (limited-resources shortest-duration optimization); GB 51114-2015, Clause 8.1.3 (network duration/cost/resource optimization); GB 55032-2022, Clause 2.0.6 (no arbitrary duration compression); DB11/T 1710-2019, Clause 9.1.2 (programme (of works) preparation incl. labour quantities and machine-shift quantities).
Keywords
- 剩余工程量
- 资源反算
- 赶工
- unit labour-time norm
- 工日
- 台班
- 可施工天数
- 进度纠偏