Content composition of quality assurance measures in construction schemes: quality management measures + quality technical measures + linkage with inspection and acceptance
Quality assurance measures are a component of the scheme's "main construction safeguard measures" (municipal system) or "construction management plan — quality management plan" (building system), and must be compiled more specifically and operably than the project execution plan (construction methodology and site organization). Content runs on two tracks: quality management measures (organizational/institutional level: quality objectives, management systems, inspection and acceptance arrangements) and quality technical measures (workmanship level: process flow, operating methods, quality inspection criteria, prevention of common defects, key-node control, seasonal construction requirements), linked with the GB 50300 division/sub-division acceptance system.
Applicable Codes
- GB/T 50903-2013 市政工程施工组织设计规范
- GB/T 50502-2009 建筑施工组织设计规范
- T/CBDA 35-2019 建筑装饰装修工程施工组织设计标准
- T CREA 021-2022 建筑与市政地基基础通用标准
Topic Positioning
Answers "what content the quality assurance measures in a construction scheme should contain" — the section's position in the scheme system, the two-track (management/technical) content composition and required compilation depth; usable directly as a scheme-section checklist.
Core Conclusions
Position in the scheme: in the municipal system one of the "main construction safeguard measures" (GB/T 50903-2013 clause 3.0.4 reference contents, chapter 6 section 2); in the building system the "construction management plan — quality management plan" (GB/T 50502-2009 clause 7.1.1); compiled in more detail and more operably than the project execution plan (construction methodology and site organization). Content on two tracks:
- Quality management measures (organizational/institutional level): establish quality objectives, quality management systems, and inspection and acceptance arrangements, parallel with the schedule, safety, environmental and cost management plans (GB/T 50502-2009 clause 7.1.1).
- Quality technical measures (workmanship level): construction methods must define process flow, process requirements and quality inspection criteria (GB/T 50903-2013 clause 5.4.1); the construction technical scheme must define the process flow and methods of each division (sub-division) work, preferably shown by flow diagrams (clause 4.5.2); the construction process must include process flow, operating methods, quality inspection criteria, and cautions and control measures at key process nodes (T/CBDA 35-2019 clause 6.1.7); sub-division works prone to common quality defects, of high construction difficulty or high technical content must be highlighted, and seasonal construction requirements raised (T/CREA 021-2022 appendix L).
- Inspection/acceptance linkage: unit works should have construction schemes for main divisions/sub-divisions per GB 50300 division principles, with quality inspection criteria citing current acceptance codes (GB/T 50502-2009 clause 5.5.1).
Applicable Boundaries
Applies to scheme compilation for building and municipal works; the quality content of special schemes for sub-divisional works involving significant hazards must be merged into the 9-item general framework's "construction safeguard measures" (see Jianban Zhi [2021] No. 48); where local records-management standards stipulate otherwise on signatures/seals, follow them. This card gives the content framework — concrete measures must be tailored to the works; template boilerplate is prohibited.
Further Reading
GB/T 50903-2013 "Code for project execution plan of municipal works" clauses 3.0.4, 4.5.2, 5.4.1, section 6.2 (quality assurance measures); GB/T 50502-2009 "Code for project execution plan of building works" clauses 3.0.4, 5.5.1, 7.1.1; T/CBDA 35-2019 "Standard for project execution plan of building decoration works" clause 6.1.7; T/CREA 021-2022 "General standard for building and municipal foundations" appendix L.
Keywords
- 质量保证措施
- construction method statement
- 质量管理措施
- 质量技术措施
- 质量检验标准
- project execution plan (construction methodology and site organization)
- 质量通病
- 施工工艺