Calculating schedule deviations by the earned-value method (SV/SPI) and the four-step analysis procedure
Schedule deviations are calculated by earned value: SV = BCWP − BCWS (negative = behind, positive = ahead), SPI = BCWP/BCWS (<1 behind, >1 ahead), CV = BCWP − ACWP judges cost overrun simultaneously; judging the effect on the total duration must return to the network plan, handling delays by their relation to free and total float — only a delay exceeding total float lengthens the total duration; the full procedure is: check and collect → compare (front-line / bar-chart / S-curve / banana-curve / list) → impact analysis → correction report.
Applicable Codes
- JGJ/T 121-2015 工程网络计划技术规程
- GB/T 50358-2017 建设项目工程总承包管理规范
- GB/T 50326-2017 建设工程项目管理规范
- GB/T 50500-2024 建设工程工程量清单计价标准
- DB37/T 5096-2017 建设工程项目管理咨询规范
Topic Positioning
The complete "calculation + analysis" workflow for construction schedule deviations: compute deviation magnitude by earned value (SV/SPI), return to the network plan to judge the effect on the total duration via floats and the critical path, and complete checking, comparison, impact analysis, and correction per the four-step code procedure. For monthly/weekly schedule control of construction projects.
Core Conclusions
① Calculation (earned-value method): basic parameters are budgeted cost of work scheduled (BCWS), budgeted cost of work performed (BCWP, i.e., earned value), and actual cost of work performed (ACWP). Schedule variance SV = BCWP − BCWS, negative behind and positive ahead; schedule performance index SPI = BCWP/BCWS, <1 behind and >1 ahead; cost variance CV = BCWP − ACWP judges overrun simultaneously. Earned value is intuitive but cannot determine the critical path and cannot replace network analysis. ② Four-step analysis procedure: a. check and collect — per statistical cycle, check completed quantities, timing, sequence, resource matching, and rectification of previous issues; b. compare — front-line (progress front) method, bar-chart comparison, S-curve, banana curve, tabular comparison; c. impact analysis — delay ≤ free float: neither successors nor total duration affected; free float < delay ≤ total float: local impact only; delay > total float: total duration lengthened — compress unfinished critical activities (choosing low resource intensity or low direct-cost rate) or recompile the unfinished portion as a new plan; d. correct and forecast — where deviations are significant, prepare a schedule deviation analysis report covering overall progress, actual vs planned comparison, causes, impacts, corrective measures, and forecasts. ③ Duration claims recognize only the excess over total float: critical delays claimable in full, non-critical delays claimable for the excess over total float, none within total float.
Applicable Boundaries
Applies to schedule management under AOA/AON/time-scaled network plans with logic and durations fixed; bar charts and milestone tables show no logic, so floats and the critical path cannot be computed. Earned value needs a cost baseline (BCWS/BCWP); without a cost basis only time comparison is possible. Checking is generally monthly, intensified to weekly when slippage is severe. Duration claims give priority to contract agreement.
Further Reading
See JGJ/T 121-2015, Clauses 7.2.1, 7.2.4, 7.3.2, 7.3.3; GB/T 50358-2017, Clauses 2.0.8 and 10.3.3; GB/T 50326-2017, Code for Construction Project Management, Clause 9.3.4; GB/T 50500-2024, Clause 8.11.8; DB37/T 5096-2017, Code for Construction Project Management Consulting, Clause 8.3.2; GB/T 50875-2013, schedule-variance terminology.
Keywords
- 进度偏差
- earned value
- 进度绩效指数
- 前锋线
- 横道图比较法
- 香蕉曲线
- critical path