Linking project cost indicators with the schedule plan: preparation binding → earned value monitoring → synchronized adjustment (GB/T 50502 7.6, GB/T 50326 11.2, GB/T 50358 2.0.8)

Three bonds link cost and schedule: ① preparation — the cost management plan is prepared on the basis of the construction budget and the construction schedule plan (GB/T 50502-2009, Clause 7.6.1), cost targets are decomposed by implementation stage (foundation/structure/installation/finishing or month/quarter/year, GB/T 50326-2017, Clause 11.2.2), and the funds utilization plan aligns with the schedule plan and the contract payment nodes (Clause 14.6.1; DB37/T 5130-2018, Clause 7.2.1); ② execution — earned value CV = BCWP − ACWP and SV = BCWP − BCWS jointly identify "false overspending when ahead of schedule, false savings when behind" (GB/T 50358-2017, Clause 2.0.8), supported by three-cost comparison (GB/T 51235-2017, Clause 9.3.1) and collecting actual costs by physical progress; ③ adjustment — when the schedule changes, costs are recalculated in sync, and target cost adjustment must satisfy the three-layer conditions of trigger, constraint, and re-approval.

Applicable Codes

  • GB/T 50502-2009 建筑施工组织设计规范
  • GB/T 50326-2017 建设工程项目管理规范
  • GB/T 50358-2017 建设项目工程总承包管理规范
  • GB/T 51235-2017 建筑信息模型施工应用标准
  • JGJ/T 121-2015 工程网络计划技术规程
  • DB37/T 5130-2018 建设工程造价咨询服务规范
  • DBJ/T 15-153-2019 广东省建设项目全过程造价管理规范
  • RISN-TG 012-2011 建设工程项目经理执业导则

Topic Positioning

This card answers "how cost indicators are linked with the schedule plan": the code bases and method chain of time-dimension binding at preparation, joint earned value monitoring at execution, and synchronized recalculation at adjustment.

Core Conclusions

Linking proceeds in three steps: ① Preparation binding — the cost management plan is based on the project construction budget and construction schedule plan (GB/T 50502-2009, Clause 7.6.1); cost targets are decomposed by implementation stage (foundation, structure, installation, finishing, or month, quarter, year — GB/T 50326-2017, Clause 11.2.2; GB/T 50502-2009, Clause 7.6.2, item 2); the funds utilization plan aligns with the schedule plan and the contractually agreed payment method, amounts, and times (GB/T 50326-2017, Clause 14.6.1; DB37/T 5130-2018, Clause 7.2.1); network plan optimization simultaneously targets schedule, cost, and resources (JGJ/T 121-2015, Clause 6.1.1) — count the cost account when scheduling. ② Execution monitoring — earned value's three parameters BCWS/BCWP/ACWP: CV = BCWP − ACWP judges cost, SV = BCWP − BCWS judges schedule; only joint judgment can identify "false overspending when ahead of schedule, false savings when behind" (GB/T 50358-2017, Clause 2.0.8); supported by three-cost comparison (budget/target/actual cost, GB/T 51235-2017, Clause 9.3.1) and collecting actual costs of completed works by physical progress (RISN-TG 012-2011, Clause 8.4.1). ③ Synchronized adjustment — when the schedule changes, costs are recalculated accordingly; target cost adjustment must simultaneously satisfy the three layers: trigger situations, constraints such as non-contractor causes, and the re-approval procedure.

Applicable Boundaries

Applies to the coupled preparation and dynamic control of cost plans and schedule plans in construction projects; the earned value method requires quantifiable decomposition of budget and schedule. The "dual-basis closure of the funds utilization plan by cost item and by contract" comes from Guangdong's DBJ/T 15-153-2019 — a regional requirement, note the jurisdiction when citing. Linking does not change the substance of managing the two lines separately; it relies on parameter and node binding.

Further Reading

GB/T 50502-2009 Clauses 7.6.1–7.6.2; GB/T 50326-2017 Clauses 11.2.2, 11.3.2, 14.6.1; GB/T 50358-2017 Clause 2.0.8 (earned value); GB/T 51235-2017 Clause 9.3.1 (three-cost comparison); JGJ/T 121-2015 Clause 6.1.1 and GB 51114-2015 Clause 8.1.3 (network plan optimization); DB37/T 5130-2018 Clause 7.2.1 and DBJ/T 15-153-2019 Clauses 5.11.2–5.11.4 (funds utilization plan); RISN-TG 012-2011 Clause 8.4.1.