decomposition of cost targets
- 01
Decomposing responsibility cost to departments, work zones, and crews: two-line cross cutting and the responsibility matrix (GB/T 50903-2013 Clause 6.5.1)
Responsibility cost is decomposed by "two-line cross cutting": verticall…
GB/T 50903-2013 市政工程施工组织设计规范GB/T 50326-2017 建设工程项目管理规范RISN-TG 012-2011 建设工程项目经理执业导则2026-09-25 - 02
Linking project cost indicators with the schedule plan: preparation binding → earned value monitoring → synchronized adjustment (GB/T 50502 7.6, GB/T 50326 11.2, GB/T 50358 2.0.8)
Three bonds link cost and schedule: ① preparation — the cost management…
GB/T 50502-2009 建筑施工组织设计规范GB/T 50326-2017 建设工程项目管理规范GB/T 50358-2017 建设项目工程总承包管理规范2026-09-25 - 03
Positioning, distinguishing, and linking target cost, responsibility cost, and planned cost (the GB/T 50326-2017 Clause 11.2.4 procedure)
The three form a chain of "targets passed down level by level, responsib…
GB/T 50326-2017 建设工程项目管理规范 第11.2.2、11.2.4条GB/T 50502-2009 建筑施工组织设计规范 第2.0.15、7.6.2条DBJ/T 15-153-2019 广东省建设项目全过程造价管理规范 第5.7.3条2026-09-25