Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Decomposing responsibility cost to departments, work zones, and crews: two-line cross cutting and the responsibility matrix (GB/T 50903-2013 Clause 6.5.1)

Responsibility cost is decomposed by "two-line cross cutting": vertically by organizational level (department → work zone → crew) and horizontally by cost element (labor / materials / machinery / expenses), crossing into a responsibility matrix. Departments manage by element, work zones account profit and loss independently by work location, crews contract by process (per GB/T 50903-2013 Clause 6.5.1 and RISN-TG 012-2011 Clause 8.2.2); six operating steps: set the envelope → cut by location → assign by element → crew contracting → cross-check (Σdepartments = Σwork zones = Σcrews = total envelope) → sign the project management responsibility statement; assessment uses the responsibility target cost reduction amount / rate (RISN-TG 012-2011 Clause 8.5.2), supported by the accounting ledgers of GB/T 50326-2017 Clause 11.4.1.

Applicable Codes

  • GB/T 50903-2013 市政工程施工组织设计规范
  • GB/T 50326-2017 建设工程项目管理规范
  • RISN-TG 012-2011 建设工程项目经理执业导则
  • GB/T 50502-2009 建筑施工组织设计规范

Topic Positioning

This card covers the concrete operation of decomposing responsibility cost from the project envelope down to departments, work zones, and crews — the "two-line cross cutting" forming the responsibility cost matrix, plus the supporting accounting and assessment mechanisms. The hands-on sequel to the concept chain "target cost / planned cost / responsibility cost".

Core Conclusions

  • Overall structure (GB/T 50903-2013 Clause 6.5.1): build the cost control system centered on the project manager — vertical decomposition by work location (providing the basis for work-section accounting), horizontal decomposition by cost item (labor, materials, machinery machine-shifts, other direct costs, construction management fees); the crossing is the responsibility matrix.
  • Three-level cutting: departments by cost element (e.g., materials department assessed on main-material price-difference and wastage rates, equipment department on machine-shift utilization, finance on indirect costs); work zones / crews by work location (unit works → work-section items, RISN-TG 012-2011 Clause 8.2.2), with independent profit/loss accounting; crews contract by process (labor on "unit price × quantity" contracts, materials on quota-based requisition plus over/under-saving rewards and penalties).
  • Six operating steps: ① set the envelope from the responsibility cost total; ② cut level by level along unit works → work sections (prioritizing the large items covering 80%+ of cost); ③ split each location's cost into labor/materials/machinery + expenses assigned to functional departments; ④ issue process contract prices and quota-based requisition slips to crews; ⑤ cross-check (Σdepartments = Σwork zones = Σcrews = total envelope); ⑥ sign the project management responsibility statement.
  • Assessment indicators (RISN-TG 012-2011 Clause 8.5.2): responsibility target cost reduction = responsibility target cost − actual cost; reduction rate = reduction ÷ responsibility target cost × 100%, rewards and penalties honored by the reduction rate. GB/T 50326-2017 Clause 11.4.1 requires sound accounting ledgers (labor attendance + material requisition + machine-shift records per work zone / crew) — without them the decomposition cannot be assessed.

Applicable Boundaries

  • Crews contract only what they can control: labor cost, material consumption, and incidental machinery costs are contractable; uncontrollable items (material price rises, major variations) must not be pushed onto crews.
  • Decomposition granularity must match ledger capacity: without location-level accounting, cut only to work zones / crews first, using "quota-based requisition + contract unit prices" instead of independent accounting, and cut deeper as accounting matures.
  • Applies to internal responsibility management within construction project departments, not to external contract pricing.

Further Reading

See GB/T 50903-2013 Code for Project Execution Plans of Municipal Works, Clause 6.5.1; GB/T 50326-2017 Code for Management of Construction Projects, Clauses 11.1.1, 11.2.2, 11.2.4, 11.4.1, 11.6.1; RISN-TG 012-2011 Guideline for Practice of Construction Project Managers, Clauses 8.1.3, 8.2.2, 8.5.2; GB/T 50502-2009 Clauses 2.0.15, 7.6.2.