Procedure for synchronously adjusting the responsibility-centre cost after a major change to the project execution plan (construction methodology and site organization) (trigger conditions → re-approval of the revised scheme → cost re-estimation → revision report → re-issue)
A scheme change does not automatically adjust the responsibility-centre cost — only a "major adjustment" triggers it (GB/T 50502-2009, Clause 3.0.6). Five-step procedure: ① revise the project execution plan (construction methodology and site organization)/construction method statement; ② obtain re-approval of the revised scheme under the original approval procedure (mandatory per GB 55032-2022 Clause 3.1.4; GB/T 50358-2017 Clause 7.2.4); ③ recalculate labour, materials, machinery and preliminaries under the new scheme; ④ prepare a revision report synchronously updating the target cost/planned cost/responsibility-centre cost (DBJ/T 15-153-2019, Clause 5.1.5); ⑤ re-issue as the new assessment baseline after approval by the enterprise's authorised person (GB/T 50326-2017, Clause 11.2.4). Internal adjustment and external adjustment of the contract price run in parallel as two channels; where scheme optimization is caused by the contractor itself, the internal assessment baseline must still be adjusted.
Applicable Codes
- GB/T 50502-2009 第3.0.6条
- GB 55032-2022 第3.1.4条
- GB/T 50358-2017 第7.2.4条
- DBJ/T 15-153-2019 第5.1.5条
- GB/T 50326-2017 第11.2.4条
- GB/T 50500-2024 第8.9.6条
Topic Positioning
This card answers "how the project responsibility-centre cost (the internal assessment baseline) is adjusted in a compliant and synchronised way after the project execution plan (construction methodology and site organization)/construction method statement changes", setting out the trigger conditions, the five-step adjustment procedure, the three layers of impact estimation, and the internal/external dual-channel rules.
Core Conclusions
Adjustment is not a matter of casually changing numbers — the full chain must be followed:
- Trigger test: only a "major adjustment" triggers it — major adjustment of principal construction methods, major adjustment of principal resource allocation, major change to the construction environment, major design modification, changes in laws, regulations and standards (GB/T 50502-2009, Clause 3.0.6); ordinary minor tuning need only be explained in the monthly cost analysis.
- Five-step procedure: ① revise the project execution plan (construction methodology and site organization)/specialised method statement; ② obtain re-approval of the revised scheme under the original approval procedure (GB 55032-2022 Clause 3.1.4 is mandatory; GB/T 50358-2017 Clause 7.2.4 requires major changes to go through the approval procedure); ③ recalculate the labour, material and machinery consumption and prices of the affected BOQ items under the new scheme; ④ prepare a revision report explaining the revisions and the reasons, synchronously updating the target cost, planned cost and responsibility-centre cost (DBJ/T 15-153-2019, Clause 5.1.5); ⑤ the revised responsibility-centre cost is issued after approval by the enterprise's authorised person as the new assessment baseline (GB/T 50326-2017, Clause 11.2.4).
- Three layers of impact estimation: direct costs (labour, materials, machinery); preliminaries (most commonly triggered by scheme changes — GB/T 50500-2024 Clause 8.9.6: changes to preliminary items require the scheme to be submitted before implementation and adjusted after confirmation by the other party); on-costs (indirect costs) and time-related costs (temporary works and site establishment costs, management fees and acceleration costs varying with the programme).
- Dual channels: externally, apply for an adjustment of the contract price per the contract procedure; internally, revise the responsibility-centre cost and submit it for approval in parallel; where scheme optimization is due to the contractor's own reasons, the contract price may not be adjustable externally, but internally it must be adjusted — otherwise the assessment baseline is distorted.
Applicable Boundaries
Applies to scenarios in which the internal responsibility-centre cost management of a construction project interacts with scheme changes; only a "major adjustment" triggers it, ordinary optimization does not; an internal adjustment is not necessarily accompanied by an external adjustment of the contract price; each adjustment must leave a written trace such as a revision report; for the object of adjustment (the definition and decomposition of responsibility-centre cost) see the related concept card.
Further Reading
See GB/T 50502-2009, Code for the Project Execution Plan of Building Engineering, Clause 3.0.6 (trigger situations for ongoing (dynamic) cost management); GB 55032-2022, General Code for Construction Quality Control of Buildings and Municipal Engineering, Clause 3.1.4 (changes follow the original approval procedure); GB/T 50358-2017, Code for Management of Engineering Procurement Construction (EPC) Projects, Clause 7.2.4; DBJ/T 15-153-2019, Guangdong Code for Whole-Process Cost Management of Construction Projects, Clause 5.1.5 (revision report); GB/T 50326-2017, Code for Construction Project Management, Clauses 11.2.2 and 11.2.4 (preparation and approval of the cost plan); GB/T 50500-2024, China National Pricing Standard for Bills of Quantities, Clause 8.9.6 (adjustment of preliminaries).