Construction cost management and responsibility-centre cost overview: the six-link closed loop, cost-plan preparation and three cost bases, responsibility decomposition and assessment
Cost management is the six-link closed loop of forecasting, planning, control, accounting, analysis and assessment (GB/T 50326-2017 cl. 2.0.21). The construction cost plan is compiled by the construction enterprise around the project execution plan, unfolds along three bases — cost composition, project structure and stage of execution — and follows the six-step procedure from forecasting to tiered approval (cl. 11.2.4), with eight content items and implementation after the enterprise's authorised person approves. The cost management plan rests on the construction budget and the programme (GB/T 50502-2009 cl. 7.6.1); accounting keeps the "three synchronisations"; assessment runs on the cost reduction amount and rate; and target cost, responsibility-centre cost and planned cost interlock, responsibility being decomposed crosswise along the organisational system and the works breakdown.
Applicable Codes
- GB/T 50326-2017 建设工程项目管理规范(第2.0.21、11.2.2~11.2.4条)
- GB/T 50502-2009 建筑施工组织设计规范(第7.6.1、7.6.2条)
- GB/T 50903-2013 市政工程施工组织设计规范(第6.5.1条)
- RISN-TG 012-2011 建设工程项目经理执业导则
An entry card for the construction cost-management domain: starting from the six-link closed loop of cost management, it opens up the compilation procedure, contents and measurement bases of the construction cost plan, and the decomposition and implementation of responsibility-centre cost. What readers look up most: what the six links are; what procedure the cost plan follows; how to choose among the three compilation bases; how target cost, responsibility-centre cost and planned cost differ; and how monthly cost analysis and assessment run. The card sets up the framework and navigates the cost-domain cards.
Concept and mechanism
The six-link closed loop. Cost management comprises the forecasting, planning, control, accounting, analysis and assessment of cost carried out to achieve the project's cost target (GB/T 50326-2017 cl. 2.0.21); the six links run head to tail, with assessment findings feeding the next round of forecasting and planning. The municipal formulation condenses them into cost planning, cost control, cost analysis, cost assessment and summary stages. Note that this domain takes the construction enterprise's (contractor's) perspective — distinct from the employer-side estimate → design estimate → budget → target cost system.
Compiling the construction cost plan. The construction enterprise compiles the plan around the project execution plan (or related documents), unfolding it singly or in combination along three bases: cost composition (direct costs / on-costs / other charges), project structure (each unit works or single-item works), or stage of execution (foundation / superstructure / installation / fit-out, or month / quarter / year) (cl. 11.2.2). The six-step procedure (cl. 11.2.4): forecast project cost → set the overall cost target → compile the overall cost plan → the project management body and functional departments set and decompose targets within their responsibility-cost scopes → draw up control measures → tiered approval; the resulting cost plan is implemented after approval by the enterprise's authorised person. Eight content items: the separation of tender price from internal target cost; the overall cost target; the overall cost plan; decomposition of responsibility scopes; dedicated cost plans (per unit works / sub-divisional works); control methods (including execution-plan and method-statement measures); the project management responsibility agreement; and resource allocation and cost-responsibility limits.
Control, accounting and assessment. The cost management plan is compiled on the basis of the project construction budget and the programme (GB/T 50502-2009 cl. 7.6.1), with five content classes: target setting, staged decomposition, organisation and rules, technical/organisational/contractual measures, and analysis methods with corrective and risk measures (cl. 7.6.2). Control cycles through "set layered targets → collect data and monitor → locate deviations and analyse causes → countermeasures and correction → improve methods"; deviation analysis should apply value engineering and the earned-value method. Accounting adheres to the "three synchronisations" — physical progress, output-value statistics and cost accumulation in step. Assessment uses the cost reduction amount and reduction rate as the principal indicators. At planning stage, break-even output value = fixed cost ÷ contribution-margin ratio gives a quick break-even figure, and the margin-of-safety ratio = (tender price − break-even output value) ÷ tender price measures the profit buffer (a static simplification that ignores the time value of money).
Responsibility cost. Target cost (the enterprise's control line over the project), responsibility-centre cost (the execution line decomposed to departments / work zones / crews) and planned cost (the compilation basis) occupy different positions but interlock (embedded in the cl. 11.2.4 procedure); responsibility-cost decomposition follows the two baseline axes of project-cost decomposition — by works component and by cost element — with the cuts carried through to the responsible units (GB/T 50903-2013 cl. 6.5.1). After a major adjustment of the project execution plan, responsibility cost must follow the "re-approve the plan → re-measure the cost → revise the report → re-issue" sequence in step.
Card-group navigation
The three costs and the target system
- Target cost, responsibility-centre cost, planned cost: positioning and the interlocking chain (card_b27da2fe)
- Three-layer conditions for adjusting target cost: triggers, no-adjustment constraints, re-approval (card_fa5f1678)
- The cost baseline system to lock first at the planning (early) stage (card_ab33dadc)
- Cost indicators linked to the programme: bind at compilation → monitor by earned value → adjust in step (card_283fa2ec)
Responsibility decomposition and assessment
- Decomposing responsibility-centre cost to departments, work zones and crews: two-axis crosswise cutting and the responsibility matrix (card_00ae7b70)
- Setting the assessment baseline value: baseline = the approved responsibility target cost (card_a8929e7a)
- The assessment indicator system of the project management responsibility agreement (card_7f444428)
- The synchronised adjustment procedure for responsibility-centre cost after a major execution-plan change (card_df70f057)
Accounting and analysis
- The monthly project cost analysis template: required elements, block structure, estimate-budget-final account comparison (card_df6fed81)
- Judging cross-period cost-data adjustments: accrual basis + "three synchronisations" twin yardsticks (card_9ec2a9d6)
- Cost-deviation attribution: three-factor decomposition into quantity, price and efficiency variances (card_b2b9f0f1)
- Identifying the principal profit and loss points in cost planning (card_242aadf3)
- Diagnosing the real cause of a sudden drop in project gross margin (card_8b423643)
- Railway measurement and valuation for payment mapped to cost and revenue: coding plus estimate-budget-final account comparison (card_3a8d4dc8)
Cross-domain links
- Rolling forecast of estimated total cost, estimated gross margin and the funding gap (card_2783bcdd)
- Attributing the cost of funds to operating analysis under two bases (card_5616776f)
- The FIDIC term "Cost" defined; the three payment bases (Cost / Cost Plus Profit) (card_0145d120)
This domain has no standing card group yet; the cards above are cross-linked related cards (cost target system / responsibility decomposition / accounting and analysis / funding links).
Keywords
- 施工成本计划
- 成本管理闭环
- responsibility-centre cost
- separation of tender price from internal target cost
- 成本管理计划
- target cost
- 成本考核
- 保本点测算
- 三同步核算