Rolling forecast method for a project's estimated total cost, estimated gross profit and funding gap

Rolling forecast = each month replace forecast figures with actuals and extend the forecast window forward to completion: estimated total cost EAC = AC + ETC (item-by-item re-estimate of remaining work); estimated gross profit = estimated total revenue minus EAC; funding gap = the lowest point of the cumulative monthly net cash flow; cadence: monthly routine re-estimation plus event-triggered immediate re-estimation upon major variations, price swings beyond plus or minus 5%, or schedule slippage past thresholds.

Applicable Codes

  • GB/T 50358-2017 建设项目工程总承包管理规范

Topic Positioning

A rolling-forecast methodology for the three lines of cost, gross profit and funding on engineering projects: replace forecast figures with actuals monthly, extend the forecast window to completion, and keep answering 'what it finally costs, what it earns, and how much funding is still short'.

Core Conclusions

Core chain: EAC (estimate at completion) = AC (actual cost) + ETC (re-estimate to complete); estimated gross profit = estimated total revenue minus EAC; funding gap = the minimum point of the cumulative monthly net cash flow.

  • Three EAC formulas: (i) BAC / CPI (remaining work homogeneous with completed work and deviation stable); (ii) AC + (BAC - EV) / CPI (recommended; to-date deviation is representative); (iii) AC + sum of item-by-item re-estimates of remaining work (most accurate when variations are frequent and material prices volatile). CPI = EV / AC; CPI below 1 means cost overrun.
  • Each month, ask three questions of every remaining work item: has the remaining quantity changed (variations); do material prices still hold at the original levels (price differentials); does the productivity of remaining processes still match the original norms (idle time, rework, crashing) - the sum of the three corrections is the ETC.
  • Profit forecasting uses 'estimated total revenue' (including estimated variations, certified site records and claims), not the original contract amount.
  • Funding gap: inflows (advance payment, progress payments by payment nodes plus approval terms, variation payments, retention recovery) minus outflows (labor, materials, plant, subcontracting, taxes, deposits) rolled month by month; the employer's payment terms and the materials-financing ratio are the key sensitivity variables.
  • Cadence: monthly routine 'accumulate actuals - compute EV/CPI - re-estimate ETC'; immediate triggered re-estimation upon major variations, material price swings beyond plus or minus 5%, or schedule slippage past thresholds.

Applicable Boundaries

Applies to whole-process control of construction/engineering projects that have a budget baseline (BAC) and an actual-cost accumulation system, where remaining quantities are estimable and contract revenue recognizable. Not applicable where there is no budget baseline, where actual-cost accumulation is distorted, or for purely advisory estimates. CPI extrapolation assumes stable deviation - with frequent variations, item-by-item re-estimation is mandatory, otherwise EAC is badly distorted.

Further Reading

Basis: the earned-value (EVM) definitions and funding-risk management provisions of GB/T 50358-2017, Code for Management of Engineering Procurement Construction (EPC) Projects. Implementation can rely on the four-layer account-and-statement closed loop: construction-drawing budget (revenue baseline) - construction budget (cost baseline BAC) - actual cost (monthly AC accumulation) - profit-and-loss analysis (EAC and gross profit output).