Three-layer conditions for adjusting the target cost: trigger situations, non-adjustment constraints, and the re-approval procedure

Adjusting the target cost must simultaneously satisfy the trigger, constraint, and procedure layers: trigger situations exist (major variations, changes in laws/regulations/policies, abnormal price fluctuations, force majeure, etc.); the red lines are not touched (not caused by the contractor itself, no adjustment of management fee and profit, and the adjusted cost still below the same-stage cost); and the procedure is performed (impact review → re-calculation of affected items → revision report → re-approval under the original approval procedure). Ordinary minor tuning does not trigger adjustment.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准
  • GB/T 50502-2009 建筑施工组织设计规范
  • GB/T 50358-2017 建设项目工程总承包管理规范
  • DBJ/T 15-153-2019 广东省建设项目全过程造价管理规范
  • DB37/T 5096-2017 建设工程项目管理咨询规范

Topic Positioning

The target cost (including the cost plan and the responsibility target cost) is not fixed once and for all — the codes explicitly require it to "advance step by step, continuously adjusted and optimized" (DBJ/T 15-153-2019, Clause 5.7.4). This card gives the trigger, constraint, and procedure layer conditions that a target cost adjustment must simultaneously satisfy.

Core Conclusions

All three layers are indispensable:

  • Trigger conditions: ① major changes in design/works scope or construction standards (GB/T 50502-2009, Clause 3.0.6); ② major adjustment of principal construction methods; ③ changes in laws, regulations, and policies (newly added/revised/repealed/reinterpreted, GB/T 50500-2024, Clause 8.8.1); ④ abnormal price fluctuations beyond the contractually agreed adjustment scope or risk band (Section 8.7); ⑤ force majeure (Clause 8.11.14); ⑥ the employer initiates changes to construction content or the schedule (DB37/T 5096-2017, Clause 8.4.1).
  • Constraint conditions: for extensions caused by the contractor, upward adjustments are not made and downward adjustments are (Clause 8.8.2); construction consumables, preliminaries, overheads and profit, and costs due to the contractor itself are generally not adjusted for price changes (Clause 8.7.6); when laws and policies change, the overheads and profit do not move (Clause 8.8.5); ordinary minor tuning and routine optimization do not trigger adjustment; after adjustment the target cost should in principle still be lower than the same-stage estimate/preliminary estimate/budget/tender price ceiling (DBJ/T 15-153-2019, Clause 5.7.6).
  • Procedure conditions: review the impact scope and degree (GB/T 50358-2017, Clause 7.2.4) → re-calculate only the affected items → prepare a revision report stating the reasons and circumstances (DBJ/T 15-153-2019, Clause 5.1.5) → implement after re-approval under the original approval procedure (GB/T 50502-2009, Clause 3.0.6), synchronously updating the assessment baseline.

Applicable Boundaries

For judging adjustments of implementation-stage target costs/cost plans; the details of contract price adjustment (the four elements of material price adjustment, provisional price differences, etc.) are in related special cards. Responsibility attribution (whether caused by the contractor itself) is the key watershed for adjustability; for specific projects, the contract terms and local cost management provisions prevail.

Further Reading

GB/T 50500-2024 Sections 8.7, 8.8, 8.11; GB/T 50502-2009 Clause 3.0.6; GB/T 50358-2017 Clause 7.2.4; DBJ/T 15-153-2019 Clauses 5.1.5, 5.7.4, 5.7.6; DB37/T 5096-2017 Clause 8.4.1; RISN-TG 012-2011 Chapter 8 (cost management).