The two-plan system of EPC project planning: the project management plan (10 items) and the project implementation plan (four blocks) - their positioning, content, compilers and acceptance, and the merger rule
GB/T 50358-2017 clause 4.1.1 requires the EPC project department to plan in the initial stage and produce a project management plan and a project implementation plan: the management plan is the enterprise's internal control document and the basis of the implementation plan, with 10 items - overview, scope, objectives, implementation-condition analysis, management mode / organisation / duties, basic principles, coordination procedures, resource plans, risk analysis and countermeasures, contract management (4.3.3) - plus tax planning and the organisational mode; the implementation plan concretises the objectives in four blocks - overview, overall implementation scheme, implementation essentials (17 items) and the preliminary programme (nine classes of control points) (4.4.3) - compiled by the project manager, accepted by the employer, drawn up after the management plan is approved and required to be workable (4.4.1); project planning otherwise has seven main contents (4.2.2), the resource plan built on the WBS. Where the project allows, the management plan may merge into the implementation plan.
Applicable Codes
- GB/T 50358-2017 · Code for Management of Engineering Procurement Construction (EPC) Projects 第4.1.1条、第4.2.2条、第4.3.3条、第4.4.1条、第4.4.3条
Positioning
Under EPC, 'project planning' differs from construction contracting: chapter 4 of GB/T 50358-2017 has the project department plan in the initial stage and produce two documents - the project management plan and the project implementation plan - with their positioning, content lists, compilers and acceptance. Answers: which two documents, what goes in each, who compiles and approves, and whether they may merge.
Core conclusions
1. Positioning and relation (4.1.1): 'The project department shall carry out project planning in the initial stage and compile the project management plan and the project implementation plan.' The management plan is the enterprise's key internal document for governing the project and the basis of the implementation plan; the implementation plan concretises and deepens the objectives, setting work essentials and control points for resources, cost, schedule, interfaces and risk, and normally undergoes the employer's review and confirmation. 'Per the project's actual conditions, the management plan content may be merged into the implementation plan.'
2. Seven main contents of planning (4.2.2): 1 planning principles; 2 technical, quality, safety, cost, schedule, health and environment objectives with management procedures; 3 management mode, organisation and duties; 4 resource plans; 5 coordination procedures; 6 the risk plan; 7 the subcontracting plan. Commentary: the resource plan fixes the types and quantities of people, equipment, materials, technology, funds and information, built on the WBS; the firm provides qualified staff, facilities and funds to deliver the contract; coordination procedures are fixed at planning to keep information timely and accurate.
3. The management plan's ten items (4.3.3): overview; scope; objectives; implementation-condition analysis; management mode, organisation and duties; basic principles; coordination procedures; resource plan; risk analysis and countermeasures; contract management. Commentary: basic content - sectors adjust to their features and the project's scale; the plan also describes tax planning and the organisational mode.
4. The implementation plan's four blocks (4.4.3): overview; overall implementation scheme; implementation essentials; preliminary programme. Details: overview - brief introduction, scope, contract type, features, special requirements; scheme - objectives, organisational form, phase division, WBS, implementation requirements, communication and coordination, document requirements per phase, subcontracting plan; essentials - 17 items: design, procurement, construction, commissioning, contract, resource, quality, schedule, cost estimating and control, safety, health, environment, communication and coordination, finance, risk, documents and information, reporting; programme - control points for nine classes: gathering source data, issuing management rules, the project plan, the programme, the design / procurement / construction / commissioning execution plans, and completing and issuing the internal cost estimate, budget and cost-schedule plan.
5. Compiler and acceptance (4.4.1): 'The implementation plan shall be compiled under the project manager and accepted by the employer.' It is the concrete means of delivering the contract, planning and enterprise objectives, reflecting the department's execution of the enterprise's requirements; compiled after the management plan is approved, and it must be workable.
Practice: the management plan faces inward (enterprise control: scope, objectives, organisation, conditions, tax planning, contracts); the implementation plan faces outward for review (employer acceptance; essentials and control points across design, procurement, construction and commissioning). Small projects may merge, but the merged document must still satisfy both content lists, and employer acceptance is never skipped.
Applicable boundaries
- For EPC (design-procurement-construction) projects; construction contracting follows the GB/T 50326-2017 chapter 5 system of outline + implementation plan + supporting planning - the names and levels must not be mixed (GB/T 50326-2017 clause 5.1.1 lists the EPC management plan as one form of management plan).
- The ten items are basic and adjustable by sector and scale; the 17 essentials are tailored to scope (projects without design may drop the design essentials, stating so in scope and interfaces).
- Merging is conditional, not default; once merged, the 'management plan as basis' approval chain stays traceable inside the document.
- Employer acceptance of the implementation plan is contractual review, not the enterprise's internal audit; the management plan stays internal and unapproved by the employer.
- Resource plans must rest on the WBS - experience-based resourcing without it fails the clause.
Further reading
- GB/T 50358-2017 chapter 4: 4.1.1, 4.2.2, 4.3.3, 4.4.1, 4.4.3.
- Construction comparison: GB/T 50326-2017 clauses 5.1.1, 5.2.4, 5.3.1~5.3.4.
- Cost-schedule linkage: GB/T 50326-2017 clauses 11.2.2, 11.2.4; early cost baselines: DBJ/T 15-153-2019.
Keywords
- 工程总承包项目策划
- 项目管理计划
- 项目实施计划
- GB/T 50358-2017
- EPC项目策划
- 资源配置计划
- 项目工作分解结构
- 发包人认可