Fixing crew counts and total duration in multiplied-rhythm (uneven-rhythm) flow construction: the step as greatest common divisor, crews bi = ti/K0, total duration = preparation + flow + closeout, and the stepwise differences from even-rhythm flow
Multiplied-rhythm flow: K0 = the greatest common divisor of the rhythms (not the smallest rhythm); bi = ti/K0 crews per process; total crews n' = sum bi (>= the number of processes); flow duration T = (m + n' - 1)K0 + sum technical intervals + sum organisational intervals - sum overlaps; total duration = preparation + flow + closeout. Worked example (m = 4, rhythms 2/4/6/2 days): K0 = 2, bi = 1/2/3/1, n' = 7, flow duration 20 days; plus 1.5 technical + 0.5 organisational - 1 overlap = 21 days; plus 5 preparation + 4 closeout = 30 days total.
Applicable Codes
- GB/T 50502-2009 · Code for Construction Organization Planning of Building Works 第 5.2.2 条
- GB/T 50502-2009 · Code for Construction Organization Planning of Building Works 第 6.2.2 条
- GB/T 50502-2009 · Code for Construction Organization Planning of Building Works 第 3.0.2 条
- GB/T 50903-2013 · Code for Construction Organization Planning of Municipal Works 第 4.2.4 条
- JGJ/T 121-2015 · Specification for Engineering Network Planning Technology
Positioning
The complete identification and computation chain for multiplied-rhythm flow: judge whether the organisation holds, fix the flow step and crew counts, then add preparation and closeout into the total duration, with the stepwise differences from even-rhythm flow. For flow organisation at the site-deployment (scheduling) stage of the project execution plan.
Core conclusions
1. Judge whether it holds (three conditions, all required)
- Each process has equal (or near-equal, after balancing) rhythms across sections; the rhythm ti = Qi / (Si x Ri x Ni) in days per section (Q quantity, S output norm,R crew size or machines, N shifts per day);
- the rhythms share a common divisor above 1 - a K0 > 1 making every ti/K0 integral (the rhythms in integer multiples);
- sections m >= total crews n', with bi per process usually within 3~4 (bounded by faces, machines, supply). Failing condition 2 (e.g. rhythms 2, 3, 4 days) the multiplied-rhythm formula cannot apply - switch to non-rhythmic flow with the cumulative stagger-subtraction maximum-difference method, or the duration distorts.
2. Fixing the step and crews (the correction: the divisor is the gcd)
- Step: K0 = gcd(t1, t2, ..., tn).
- Crews: bi = ti/K0 (exact division is the formula's precondition); total n' = sum bi. A process may field several same-trade crews, so n' >= n (n = number of processes).
- The common misremembering "bi = ti / smallest rhythm" - only when the rhythms are integer multiples and the smallest divides them all does gcd equal the smallest, making the two coincide; in general the gcd must be the divisor or neither the division nor the crews stand.
- Fractional rhythms: unify the time unit (say 0.5 day) before taking the gcd, else 2.5 / 3.5-day rhythms cannot multiply.
- Checks: m >= n' (else crews wait for faces); an oversized bi means that process's rhythm is relatively slow - add resources to shorten the rhythm or add sections rather than stacking crews.
3. Rounding when division fails (an engineering judgement, never default rounding)
- Round up bi = ceiling(ti/K0): the process's rhythm is pressed down to bi x K0 - add resources to make that real, then compute on the new crews;
- round down: the rhythm stretches, technical gaps appear within the crew, the formula fails - recompute on actual rhythms and add to sum Z;
- the proper course is to adjust the rhythms into multiples (change R, N or the sectioning so Qi shifts); otherwise run non-rhythmic flow.
4. Total duration (with preparation and closeout) Flow duration: T = (m + n' - 1) x K0 + sum Z-technical + sum Z-organisational - sum C
- technical intervals (curing, masonry settlement, testing ages) - additive only;
- organisational intervals (face handover, inspection, per-section face preparation and clean-up) - additive only;
- C - overlaps between adjacent trades (the next starting before the previous fully ends) - subtractive only. Total duration = preparation + flow + closeout
- preparation: mobilisation, temporary works, setting out, testing, orders and deliveries to the first section;
- closeout: cleaning, testing, trial runs, documentation and completion acceptance after the last section;
- only the parts on the critical path that cannot run parallel with the flow count. Parallel-capable preparation / closeout is never double-counted, nor is face preparation / clean-up already inside sum Z-organisational.
5. Worked example (m = 4 sections, four processes at 2, 4, 6, 2 days)
- K0 = gcd(2, 4, 6, 2) = 2 days;
- bi = 2/2, 4/2, 6/2, 2/2 = 1, 2, 3, 1; n' = 7 (above the 4 processes);
- pure flow duration T = (4 + 7 - 1) x 2 = 20 days;
- +1.5 technical +0.5 organisational -1 overlap: T = 20 + 1.5 + 0.5 - 1 = 21 days;
- +5 preparation +4 closeout: total = 5 + 21 + 4 = 30 days. Contrast: at even 2-day rhythms, T = (4 + 4 - 1) x 2 = 14 days - multiplied rhythm trades more crews (7 versus 4) for a shorter duration than non-rhythmic organisation and continuous working.
6. Stepwise differences from even-rhythm flow
| Item | Even (fixed) rhythm | Multiplied (uneven) rhythm |
|---|---|---|
| Rhythm condition | all t equal, all sections | ti differ but in integer multiples |
| Step | K = t, no gcd needed | K0 = gcd(ti), an extra judging step |
| Crews | one per process, n' = n | bi = ti/K0, n' = sum bi > n |
| Duration | T = (m + n - 1)t | T = (m + n' - 1)K0 |
| Intervals / overlaps | +sum Z - sum C | same, with finer per-section organisational items |
| Even rhythm needs "fix K, compute T"; multiplied rhythm needs six steps: judge, gcd for K0, round for bi/n', check m >= n', compute T, add preparation and closeout. |
Applicable boundaries
- Only for uneven-rhythm flow meeting the three conditions; non-integer-multiple rhythms must run non-rhythmic flow (cumulative stagger subtraction), or the duration distorts.
- The formulas assume continuous flow and stable in-section rhythms; m < n' forces idling - split sections, merge processes or cut crews; the formula itself does not price idle loss.
- Preparation and closeout include only non-parallel, critical-path parts; double counting is the commonest source of overstated duration.
- These are the theoretical flow computations - the codes set principles only (order, sectioning, balanced flow); check critical path, floats and compression with network methods.
- Rounding is an approximation requiring matching resource or section changes - never change crews without changing rhythms.
Further reading
GB/T 50502-2009 clauses 5.2.2, 6.2.2, 3.0.2; GB/T 50903-2013 clause 4.2.4 (municipal); JGJ/T 121-2015 (network checking); textbooks, "principles of flow-line construction" (even-rhythm, multiplied-rhythm and non-rhythmic derivations and examples).