Linked verification method for the four quantities "procurement plan — site entry — acceptance — payment" of engineering materials (voucher anchors and three-way matching)

The four quantities are anchored on vouchers: the procurement plan quantity (plan approval form + contract) controls site entry; whatever enters must be accepted (acceptance records / material receipt notes / warehouse ledger); the payment quantity must be based on the accepted-qualified quantity. Before payment, finance performs three-way matching of purchase order x acceptance note x invoice and pays only on a match. Nothing enters beyond plan, nonconforming goods are not accepted, nothing is paid without acceptance — combined with segregation of duties, monthly stocktaking, and supplier reconciliation to close the loop.

Applicable Codes

  • GB/T 50430-2017 工程建设施工企业质量管理规范 第8.2.1/8.2.3/8.3.1条
  • T/CIAS-5-2022 数据中心机电工程技术规程 第5.2.1条
  • GB/T 50500-2024 建设工程工程量清单计价标准 第3.6.3条
  • GB/T 50326-2017 建设工程项目管理规范 第6.2.1条
  • DB37/T 5164-2020 建筑施工现场管理标准 第5.5.2/5.5.3条

Topic Positioning

The linked verification method for the four quantities "procurement plan — site entry — acceptance — payment" in construction enterprise material management: each quantity is anchored on a voucher and interlocked link by link, preventing over-procurement, short delivery, overpayment and mispayment. Applicable to project department material management, material accounting and financial reconciliation, and audit checks.

Core Conclusions

Definitions and vouchers of the four quantities: (1) procurement plan quantity = required quantity − opening stock + safety stock (procurement plan approval form and procurement contract; the contract must specify variety/specification/model/quantity/unit of measurement/delivery time/payment method); (2) entry quantity = the supplier's actual delivered quantity (delivery note, weighing slip); (3) acceptance quantity = counted/weighed quantity − nonconforming quantity (material entry acceptance record, material receipt note, warehouse ledger, reported to the employer/supervisor for confirmation); (4) payment quantity = accepted-qualified quantity (acceptance note + invoice + payment application). Three linked main lines: plan ↔ entry — when cumulative entry exceeds plan plus reasonable loss, stop receiving; materials entering without a contract basis are refused or booked as suspense; entry ↔ acceptance — if the quantity matches but the quality is nonconforming, it must not be counted into the acceptance quantity; missing quality-certification documents, mismatch between goods and documents, or expired shelf life triggers retesting per national sampling standards; acceptance ↔ payment — three-way matching (purchase order x acceptance note x invoice) must agree before payment; if the invoiced quantity exceeds the accepted quantity, refuse the difference or issue a credit note. Mechanism safeguards: segregation of plan/acceptance/payment duties, item-by-item registration in the warehouse ledger, monthly stocktaking with ledger-card-material agreement, written write-offs for returns/exchanges/compensation, and monthly reconciliation with suppliers signed and acknowledged.

Applicable Boundaries

Applies to project material management of construction contracting enterprises. The sharing of over-requisition and over-consumption costs (GB/T 50500-2024, Clause 3.6.3) can be applied in reverse for procurement control. This card covers only the linkage of quantity definitions and does not cover supplier evaluation and selection, comparison of payment terms and capital costs, material price adjustment, or downtime cost calculation. For material loss-rate benchmarks and quota-based material requisition see related cards.

Further Reading

GB/T 50430-2017 Clauses 8.2.1 (procurement plan preparation and approval), 8.2.3 (procurement contract content), 8.3.1 (entry acceptance and retest situations); T/CIAS-5-2022 Clause 5.2.1 (acceptance application, material receipt note, warehouse ledger); GB/T 50500-2024 Clause 3.6.3 (responsibility for over-requisitioned material costs); GB/T 50326-2017 Clause 6.2.1 (procurement plan content elements); DB37/T 5164-2020 Clauses 5.5.2, 5.5.3 (procurement and use plan, quota-based requisition).