Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Four-quantity reconciliation (planned/purchased/issued/actually consumed) for materials and quota-based material issue control

Four-quantity reconciliation follows the chain "set plans by quota, control purchasing by plan, control issues by quota limit, verify consumption by inventory": planned quantity = work quantity x consumption quota (incl. loss); actual consumption = opening stock + current intake - closing stock - returns - scrap recovery; variance = actual consumption - planned quantity; closed-loop control via three-way matching of delivery notes/issue slips/inventory records + quota-based issue + progress-tracked comparison + over/under-consumption incentives.

Applicable Codes

  • GB/T 50326-2017 建设工程项目管理规范
  • GB/T 50640-2023 建筑与市政工程绿色施工评价标准
  • DB11/T 513-2018 绿色施工管理规程
  • T/HNCT 001-2022 湖南省建筑工程绿色施工评价标准技术细则
  • TSXCEAS 001-2022 城市综合管廊施工质量管理指南
  • TB/T 10821-2024 铁路工程基本定额

Topic Positioning

This card covers the definitions and reconciliation method of four quantity types in construction project material management—planned, purchased, issued, and actually consumed—how they link up and check against each other, suitable for material staff and cost engineers doing consumption control and over/under-consumption analysis.

Core Conclusions

Four-quantity reconciliation follows the chain "set plans by quota, control purchasing by plan, control issues by quota limit, verify consumption by inventory":

  • Planned quantity (requirement): work quantity x consumption quota (incl. site handling and operation wastage rate; consumables per amortization rules), computed from official construction drawings.
  • Purchased quantity: per the total requirement plan, net of opening stock plus safety stock, delivered in batches by phase.
  • Issued quantity: accumulated on quota-based material issue slips; per-issue limit = planned quantity x work completed this period / total work quantity; cumulative issues must not exceed the planned quantity—over-limit issues require written reason and separate approval.
  • Actual consumption: back-calculated from inventory = opening stock + current intake - closing stock - returns - scrap recovery.
  • Over/under-consumption assessment: variance = actual consumption - planned quantity; over-consumption split into management loss, excess operation loss, and waste. Supporting measures: three-way matching of delivery notes, issue slips, and inventory records; compare planned vs actual usage of main materials by progress and plot curves to locate high-loss operations; periodic inventory counts for correction; adhere to "plan management, tracking checks, total-quantity control, over/under-consumption incentives and penalties."

Applicable Boundaries

Applies to quota-managed conventional construction materials (rebar, concrete, formwork, aggregates); planned-quantity accuracy depends on consumption quota and wastage rate values (which differ by industry). Not applicable to new or experimental materials without quota basis—establish baselines after dedicated consumption measurement. Under green construction evaluation, these systems and records also serve as scoring verification items.

Further Reading

See GB/T 50326-2017 Code for Construction Project Management, Article 14.4.4 (four principles of resource management assessment); GB/T 50640-2023 Evaluation Standard for Green Construction of Building and Municipal Engineering, Article 5.1.2 (quota-based issue system); DB11/T 513-2018 Green Construction Management Regulation, Article 5.4.4 (consumption control by construction budget); Hunan Technical Rules for Green Construction Evaluation, Articles 9.1.1 and 9.3.9; Guide for Quality Management of Utility Tunnel Construction, Article 4.3.4 (issue slip workflow); railway consumption baselines in TB/T 10821-2024 Railway Engineering Basic Quota Chapter 9 (amortization of auxiliary structural materials and semi-finished products) and the material handling/operation wastage rate appendix.

Keywords

Cited By