Whether actual purchase quantities can directly serve as the material adjustment quantity: triple filtering of contract agreement + employer confirmation + not exceeding rational consumption (GB/T 50500-2024)
The purchase quantity cannot directly serve as the adjustment quantity Q; it must pass triple filtering: (1) the contract/special clauses expressly agree the purchase-quantity caliber (A.2.1, Note 2 of Table G.2.1-1); (2) submission to the employer for verification and confirmation before purchase, deemed accepted upon overdue silence, batch purchases averaged by weight (A.2.5); (3) capped by the rational consumption of works completed in the period — the excess is borne by the contractor per 3.6.3, and the appraisal caliber is "actual consumption = requisition quantity − inventory" (T/ZBD 100.4-2023 Clause 4.5.7). Safest: currently measured quantities × quota consumption (including loss).
Applicable Codes
- GB/T 50500-2024 App. A.2.1、A.2.5、App. GTable G.2.1-1、第3.6.3条、第8.7.2条
- T/ZBD 100.4-2023 第4.5.7条
Topic Positioning
"Can actual purchase quantities directly serve as the quantity Q subject to material price adjustment?" No — they must pass a triple filter of "contractual agreement + employer confirmation + not exceeding reasonable consumption" (GB/T 50500-2024, adjustment based on published price information).
Core Conclusions
The rule for determining Q is that contractual agreement takes precedence: Appendix A.2.1 provides that quantities are determined according to the calculation rules agreed in the contract, and other methods such as the purchase-quantity method must be detailed in the tender documents and special clauses; Note 2 of Table G.2.1-1 is to the same effect. Using the purchase-quantity method requires all of the following: (1) the contract expressly agrees that the basis is the actual purchase quantity in the current period; (2) before purchase, quantities and unit prices are submitted to the employer for verification and confirmation; upon lapse of the response period, this is deemed approval; batch purchases are averaged by weight (A.2.5); (3) capped by the reasonable consumption of works completed in the current period — Clause 3.6.3 makes clear that requisitioned quantities exceeding drawing quantity × (1 + effective wastage rate) are borne by the contractor, and the appraisal basis is "actual consumption = requisitioned quantity − inventory quantity" (T/ZBD 100.4-2023 Clause 4.5.7); without verification against consumption, no adjustment may be made. Safest: measured quantities for the current period × norm resource consumption (including wastage).
Applicable Boundaries
Applies only to determining Q for adjustable main materials under adjustment based on published price information (Appendix A.2); index-based (formula) adjustment uses weights/amounts as factors and follows different logic; materials for which price adjustment is not agreed or is agreed not to be adjusted are not covered.
Further Reading
GB/T 50500-2024 Appendix A.2.1, A.2.5, Table G.2.1-1, Clauses 3.6.3, 8.7.2; T/ZBD 100.4-2023 Clause 4.5.7.