Identifying abnormal over-consumption in material requisitions: verification paths and an anomaly signal checklist

Five steps to identify abnormal over-consumption: set the baseline (planned quantity = net quantity x (1 + quota wastage rate)) -> back-calculate actual consumption by inventory (opening stock + period entry - closing stock - returns - scrap recovery) -> requisition-slip field checks -> cross-footing against completed quantity x quota content -> assign liability per GB/T 50500-2024 Clauses 3.6.2/3.6.3; empirical red lines: over-consumption > 5% attention, > 10% key verification; over-limit requisition without approval, requisition dates inconsistent with construction logs, and unrecovered scrap are all anomaly signals.

Applicable Codes

  • GB/T 50500-2024 第3.6.2、3.6.3条
  • GB/T 50875-2013 第2.3.16条
  • T/ZBD 100.4-2023 第4.5.7条
  • ZJKX-ZHJZ001-2021 第7.6.3条

Topic Positioning

The verification path and anomaly signal checklist for identifying abnormal over-consumption in material requisitions (set baseline -> back-calculate -> check requisition slips -> quantity cross-footing -> assign liability), for use by material staff, auditors, and construction cost expert assessment.

Core Conclusions

(1) Set the baseline: planned consumption = net quantity x (1 + quota wastage rate); material consumption = net quantity + unavoidable loss (GB/T 50875-2013, Clause 2.3.16); over-consumption rate = (actual consumption - planned consumption) / planned consumption x 100%; empirical red lines: > 5% attention, > 10% key verification. (2) Back-calculate the actual quantity: actual consumption = opening stock + period entry - closing stock - returns - scrap recovery; ledger requisition quantity is not actual consumption — returns and scrap recovery not offset inflate the books. (3) Requisition slip checks: slips without constructor issuance/crew receipt, over-limit requisition without approval, the same crew repeatedly requisitioning the same material on the same day, requisition dates mismatching construction logs/pouring records, and requisitioned specifications mismatching the drawings are all anomaly signals; material ledgers should cover four categories — stock/transfers/scrap and waste/loss and write-off (ZJKX-ZHJZ001-2021, Clause 7.6.3); scrap of unknown whereabouts may be double-counted as consumption. (4) Quantity cross-footing: compare requisitions of each period with that period's completed quantity x quota content, cross-verified with pouring and concealed-work acceptance records, to identify phantom requisitions and diversion. (5) Liability: the employer should specify effective wastage rates in tender documents (GB/T 50500-2024, Clause 3.6.2); over-requisition caused by the contractor is borne by it and deducted from the settlement price; over-consumption caused by employer-supplied material specification mismatch is borne by the employer (Clause 3.6.3); free-issue materials disputes are assessed as actual consumption = requisitioned quantity - stock quantity, with surpluses not returned deducted per contract (T/ZBD 100.4-2023, Clause 4.5.7).

Applicable Boundaries

Applies to requisition checks for conventional main materials under quota management (rebar, concrete, blocks, etc.); the 5%/10% red lines are empirical engineering values, not mandatory norms, to be adjusted per project reality; new materials without quota basis need dedicated consumption measurement before setting a baseline; free-issue materials rules apply only where materials are supplied by the employer.

Further Reading

See GB/T 50500-2024 Clauses 3.6.2, 3.6.3; GB/T 50875-2013 Clause 2.3.16; T/ZBD 100.4-2023 Clause 4.5.7; ZJKX-ZHJZ001-2021 Clause 7.6.3; wastage-rate baselines in TB/T 10821-2024 Appendix "Material handling and operation wastage rates on site", taken per the project's applicable industry quotas.