Cross-sector comparison of pile-head removal measurement and pricing: railway per pile or m3; highways embedded in the pile-concrete item; municipal/rail-transit per broken volume m3; BOQ layer folded into pile-item work contents
Whether head removal is a separate item and its unit is the biggest cross-sector difference: railway bridges (TB/T 10823-2024) QY-229~231 by diameter tier, per "pile", excluding haul-off; railway buildings (TB/T 10831-2024) FY-185~189 by m3 (precast 40d default, cast-in-place over-grout 0.5m default); highways (JTG/T 3832-2018) not separate - removal is inside the bored-pile concrete item's work contents, so applying another item double-prices; Beijing municipal/transit (DB11/T 2382-2024) separate by broken volume m3; the BOQ layer (GB/T 50857/50861-2024) folds "head treatment/cropping and leveling" into precast pile-item work contents.
Applicable Codes
- TB/T 10823-2024 铁路工程预算定额 Vol. 2 桥涵工程
- TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程
- JTG/T 3832-2018 公路工程预算定额
- DB11/T 2382-2024 建设工程施工消耗量标准(北京:市政册/轨道册/房屋建筑册)
- GB/T 50857-2024 市政工程工程量计算标准
- GB/T 50861-2024 城市轨道交通工程工程量计算标准
- SJG 111.1-2022 城市地下综合管廊工程消耗量标准
- DB14/T 1319-2021 公路工程标准工程量清单及计量规范(地方对照)
Topic Positioning
Cross-sector rules for pile-head removal (cropping/cutting/ring-cutting) of cast-in-place and precast piles at the quota and BOQ layers: railway bridges per pile, railway buildings per m3 (40d/over-grout), highways embedded in the concrete item, Beijing municipal and transit per broken volume, and the BOQ layer folding head treatment into pile work contents - for estimating, BOQ pricing, and double-pricing checks.
Core Conclusions
[Railway bridges, TB/T 10823-2024 Vol.2 (Sec.4)] Removal items QY-229~231 by diameter tier (<=1.0/2.0/3.0m), unit "1 pile"; contents: ring-cut, break, strip rebar, dress, lift out of pit. Notes, original: "ring-cut pile-head quantity is by pile diameter per the design pile count"; "the ring-cut item excludes head haul-off, priced separately with reference to rock haul." Anti-double-counting: shaft concrete "(design length + 1m) x area, over-break excluded" - over-grout material is in the pour item; removal mainly prices the breaking labor and machinery. Precast boundary: "square and (prestressed) pipe pile items include amortization of leaders, followers, and head removal" - no QY-229~231.
[Railway buildings, TB/T 10831-2024 Vol.10 (Sec.2)] FY-185 cropping square (m3), FY-186 pipe (pile), FY-187 removal precast (m3), FY-188 removal cast-in-place (m3), FY-189 rebar dressing (10 piles). Rules, original: "precast removal length, design silent, 40d (d = main bar diameter, largest where different)"; "cast-in-place removal by design over-grout height (0.50m if silent) x design shaft area"; "precast cropping <=1m: no deduction from driving quantity; >1m: deduct the excess but not the pile price."
[Highways, JTG/T 3832-2018] Not separate: the bored-pile concrete item (unit 10 m3 solid, rebar and test tubes in the same item) lists among its contents "1) fix/remove tremie and hopper; 2) place concrete or underwater concrete; 3) remove the concrete pile head" - head-removal resources are embedded; a separate item would double-price. Underwater concrete quantity is design area x design length, over-break excluded (over-break and over-grout are embedded, not computed separately).
[Municipal/transit quotas (Beijing DB11/T 2382-2024 consumption standards)] Separate by broken volume m3: municipal D3-1-21 removal of cast-in-place (reinforced) heads, D1-2-18 plain-concrete (CFG) heads; transit G1-2-45/46/47 head removal in m3 tiers (with/without in-pit transfer and hoisting), G1-3-16 cement-pile heads; buildings A-3-19 reinforced heads (contents: break head concrete, cut rebar, dress head bars). Shenzhen SJG 111.1-2022 utility-tunnel standard likewise: "removal of pile-top reinforced concrete measured by the volume removed in cubic meters."
[BOQ layer] GB/T 50857-2024 municipal Table C.1.1 (code 040301 piles): precast square/pipe pile work contents include "pile head treatment"; GB/T 50861-2024 rail-transit Table B.1.1 (080201): precast piles include "cropping and leveling", with "pile length including the tip (if any) but not the length into the cap or crown beam; empty-bore length = hole depth - pile length". So at the BOQ layer, head cropping is folded into pile items (unlisted contents are not priced separately); when pricing from quotas, merge bases to avoid duplication.
Applicable Boundaries
- Rules and item bases only - no amounts; item prices are base-period, adjusted for current pricing per the compilation method.
- Railway bridge items suit cast-in-place (bored) piles; precast head amortization is embedded in driving items.
- Beijing 2021 and 2024 consumption standards coexist with different codes - verify the current version.
- Highway BOQ follows the project's tender documents (2018 standard documents); DB14/T 1319-2021 (Shanxi) is a local reference only.
- "Out of pit / haul-off" boundaries differ by volume (railway bridges reference rock haul; Beijing transit tiers partly include in-pit tricycle transfer) - check each volume's notes against omission and duplication.
Further Reading
- Railway: TB/T 10823-2024 Vol.2 Sec.4 (XI) QY-229~231 and notes X/XI; TB/T 10831-2024 Vol.10 FY-185~189 and notes XVIII (I)(II).
- Highways: JTG/T 3832-2018 Ch.4 bored-pile concrete "work contents"; with JTG 3830-2018 compilation method.
- Municipal/transit/buildings: DB11/T 2382-2024 D3-1-21, D1-2-18, G1-2-45~47, G1-3-16, A-3-19; Shenzhen SJG 111.1-2022 Clause 3.2.4.
- BOQ: GB/T 50857-2024 Table C.1.1 (040301); GB/T 50861-2024 Table B.1.1 (080201) and B.9.1 (cf. old GB 50861-2013 Table B.1).
- Highway BOQ cross-check: DB14/T 1319-2021 Table 405 (bored piles, local standard).
Keywords
- pile head cropping
- 凿除混凝土桩头
- 桩头处理
- 计量规则
- QY-229
- TB/T 10823-2024