Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-04

Measuring and pricing pile-head removal (cropping) in the railway 2024 quotas: bridge volume by diameter tier per pile (QY-229~231), buildings volume by 40d/over-grout height (FY-185~189)

Two regimes in the 2024 railway quotas: bridges (TB/T 10823-2024 Vol.2) bored/hand-dug pile head removal QY-229~231 in three diameter tiers priced per "1 pile"; ring-cut quantity by design pile count; the item excludes head haul-off (reference rock haul); and it applies only to cast-in-place piles - precast square/pipe piles already embed head-removal amortization. Buildings (TB/T 10831-2024 Vol.10) FY-185~189: precast head cropping length 40d of the main bar if design is silent; cast-in-place head removal by over-grout height (0.50m default) x design shaft area.

Applicable Codes

  • TB/T 10823-2024 铁路工程预算定额 Vol. 2 桥涵工程
  • TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程

Topic Positioning

Measurement and pricing rules for pile-head removal (cropping/cutting) in railway works under the 2024 quotas - bridges (TB/T 10823-2024 Vol.2, bored/hand-dug piles) by diameter tier per pile; buildings (TB/T 10831-2024 Vol.10, station-building piles) by pile type with 40d for precast and over-grout height for cast-in-place - for item selection and quantity takeoff in railway estimates.

Core Conclusions

I. Bridges (TB/T 10823-2024 Vol.2 Ch.1 Sec.4, (XI) removal of concrete pile heads)

  1. Work contents (original): "ring-cutting the head, breaking concrete, stripping rebar, dressing the head, lifting it out of the pit."
  2. Three diameter tiers, unit "1 pile": QY-229 <=1.0m, QY-230 <=2.0m, QY-231 <=3.0m. Base price of labor + machinery, materials negligible (breaking consumes almost none).
  3. Rule (notes XI item 7, original): "ring-cut pile-head quantity is by pile diameter per the design pile count" - per pile, not by volume or length.
  4. Haul boundary (note X): "the ring-cut item excludes head haul-off, which is priced separately with reference to rock haul" - contents stop at lifting out of the pit.
  5. Anti-double-counting: shaft concrete is "(design length top-to-bottom + 1m) x design area" (XI item 2) - the over-grout 1m is already priced in the pour item; the removal item carries no material - no duplication.
  6. Precast piles in this volume: Section 5 states the square and (prestressed) pipe pile items "already include amortization of leaders, followers, and pile-head removal" - do not apply QY-229~231 to them (these items are for bored/hand-dug cast-in-place piles only).

II. Buildings (TB/T 10831-2024 Vol.10 Ch.1 Sec.2 piles and ground works, (IV) others)

  1. Items and units: FY-185 cropping square piles (m3), FY-186 cropping pipe piles (pile), FY-187 removal precast (m3), FY-188 removal cast-in-place (m3), FY-189 head rebar dressing (10 piles).
  2. Work contents (original): cropping = "cut concrete, clean, haul blocks out of pit, weld rebar (pile bars to foundation bars)"; removal = "pre-cut then break concrete, haul blocks out, weld rebar"; dressing = "comb and reshape head bars." FY items include the rebar welding - a boundary difference from QY items.
  3. Rules (notes XVIII): (1) Precast removal: "where design is silent, head length is taken as 40d (d = main bar diameter, largest where different)" - volume = head length x shaft area; (2) Cast-in-place removal: "by design over-grout height (0.50m if silent) times design shaft area" - same basis as the pour quantity's added over-grout length; no extra concrete material; (3) Precast cropping: "length <=1m: no deduction from driving quantity; >1m: deduct the excess from driving quantity but not the pile price"; (4) Pipe-pile cropping per pile; rebar dressing per 10 piles.

Applicable Boundaries

  • 2024 railway system only; bored/hand-dug heads take QY-229~231 (bridges); station-building piles take FY-185~189 - select the volume by work type; codes and units must not be mixed.
  • Bridge head-removal items apply only to cast-in-place piles; precast square/pipe head amortization is already in the driving items.
  • FY-185~188 include hauling blocks out of the pit and rebar welding; haul-off beyond the pit is separate (bridges expressly reference rock haul).
  • General code knowledge - no item prices or examples; price with the quota base and adjust differences per the railway method.

Further Reading

  • TB/T 10823-2024 Vol.2: notes X (haul-off), XI items 2 and 7; Sec.4 (XI) QY-229~231; Sec.5 precast piles (amortization embedded).
  • TB/T 10831-2024 Vol.10: notes XVIII (40d, 0.50m, <=1m no deduction); Ch.1 Sec.2 (IV) FY-185~189.
  • Whether head removal is priced separately in general (five classes: empty bore, rock, slurry, cages, heads) - cited card; hole items QY-88~147 and casing amortization QY-222~228 - cited cards.

Keywords

Cited By