Railway 2024 quota volume boundaries: Volume 13 station yard works vs Volume 1 subgrade and Volume 10 buildings — scopes and fallback paths for missing items (TB/T 10822/10831/10834-2024)
The railway 2024 budget quotas draw boundaries by volume notes: Volume 13 station yard works (TB/T 10834-2024) covers railway station yards and locomotive/car/machinery works contents, with missing items filled per its notes — pit and trench excavation and track strengthening/protection -> Volume 1 subgrade / Volume 2 bridge and culvert works; canopies, static signage, ready-mixed mortar, wall capping -> Volume 10 buildings; car retarder installation -> Volume 12 locomotive/car/machinery works; Volume 1 subgrade (TB/T 10822-2024) covers subgrade works, relocated roads, level crossings, relocated ditches (rivers), and other earthworks; Volume 10 buildings (TB/T 10831-2024) covers railway building works (column-free platform canopies and cantilevered platform canopies belong here, with their floor-area rules). Volume conclusions: platform walls -> station-yard volume (capping from the buildings volume); station-ground earthworks body -> subgrade volume (estimates list "station-yard earthworks" separately) + station-ground rolling -> the station-yard volume's rolling chapter; station-yard roads -> the station-yard volume's road chapter; relocated roads -> subgrade volume.
Applicable Codes
- TB/T 10834-2024 铁路工程预算定额 Vol. 13 站场工程
- TB/T 10822-2024 铁路工程预算定额 Vol. 1 路基工程
- TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程
- TB 10801-2024 铁路基本建设工程设计概(预)算编制办法
Topic Positioning
The boundaries among Volume 13 station yard works, Volume 1 subgrade works, and Volume 10 building works in the railway 2024 budget quota system (TB/T 10821~10834 series): each volume's scope, the fallback paths for the station-yard volume's missing items, and how to decide "which volume" for platform walls, station-ground rolling, station-yard roads, platform canopies, and relocated roads. For fast volume location when compiling railway estimates (budgets).
Core Conclusions
The three scopes (each volume's notes as written) (1) Volume 13 station yard works (TB/T 10834-2024): "This volume applies to contents related to railway station yards and locomotive, car, and machinery works (inspection pits, machinery travel tracks, etc.)." Scaffolding costs are already in the relevant items and must not be added; precast concrete and rebar fabrication assume factory production and exclude transport from the yard to the installation point — off-site transport per the relevant items of Volume 1 subgrade and the Basic quotas. (2) Volume 1 subgrade works (TB/T 10822-2024): "This volume applies to railway subgrade works, relocated roads, level crossings, relocated ditches (rivers), and other earth and rock works." (3) Volume 10 building works (TB/T 10831-2024): "This volume applies to works related to railway buildings."
Fallback paths for the station-yard volume's missing items (TB/T 10834-2024 volume notes 4, 5, 6 as written)
- No pit/trench excavation or track strengthening/protection items -> use the relevant items of Volume 1 subgrade and Volume 2 bridge and culvert works;
- No canopies, static signage, ready-mixed mortar, wall capping, etc. -> use the relevant items of Volume 10 building works;
- No car retarder installation -> use the relevant items of Volume 12 locomotive/car/machinery works. (Correspondingly, the subgrade volume notes: pit excavation and demolition works not contained are per Volume 2 bridge and culvert works and Volume 13 station yard works; subgrade items marked "HT-0" for concrete exclude mixing and materials — the excluded contents per the Basic quotas.)
Platform canopies belong to the buildings volume, with its floor-area rules (TB/T 10831-2024 volume note 2 as written) (1) The floor area of column-free platform canopies is the horizontal projection of the canopy's outer edge, without deducting structurally open areas; (2) Cantilevered platform canopies at railway stations: bounded by the outer line of the station building's external walls, computed by projected area and counted into the canopy floor area; (3) Otherwise, railway building floor areas follow GB 55031 "General code for civil buildings". Platform canopies are buildings-volume works; the station-yard volume has no canopy items — do not apply them there.
Estimate chapter attribution (TB 10801-2024, Appendix A)
- Under the subgrade chapter, "section earthworks" and "station-yard earthworks" are parallel items: earthworks within station yards are listed as "station-yard earthworks" and priced with subgrade-volume earthworks quotas, not merged with section subgrade earthworks;
- "Earth and rock excavation related to masonry and other works has its cost included in the main works" (a retaining wall's pit excavation and backfill into the retaining wall; bridge/culvert open-cut foundation excavation and backfill into the foundation masonry) — pit excavation and backfill of masonry such as platform walls likewise enter the main works, not listed separately;
- Terminal projects compile the composite estimate (budget) per "track-km laid" instead of "main-line km"; logistics-park composite indices may be compiled per warehouse floor area in square metres.
- Volume conclusions for typical works
- Platform wall -> Volume 13 station yard works: cast-in-place platform walls, precast wall and cap setting, wall reinforcement, wall foundations, platform surfacing, etc. are all in this volume; but wall capping is not — per volume note 5 use the buildings volume's "wall capping" items;
- Station-ground rolling -> two layers: the station-ground earthworks body (cut, haul, fill) uses subgrade-volume earthworks quotas (LY/QY series), listed as "station-yard earthworks"; rolling uses the station-yard volume's rolling chapter (original-ground rolling, fill rolling, etc.). Easily confused: the subgrade volume's Chapter 1 "site clearing, spoil spreading and rolling" is for spoil grounds — not station grounds;
- Station-yard roads -> the station-yard volume's "roads and hardened surfaces" chapter (cast-in-place concrete pavements, pavement reinforcement, tie and dowel bars, bedding, asphalt surfaces, etc.); but relocated roads (highway relocations, rebuilt roads) belong to Volume 1 subgrade — not the station-yard volume; the subgrade filling part of station-yard roads likewise uses subgrade-volume earthworks quotas.
Applicable Boundaries
- For the 2024 railway budget quota system (TB/T 10822, TB/T 10831, TB/T 10834-2024, etc.); not for old editions (volume divisions and items may differ);
- Boundaries follow each volume's notes as written; item numbers cited are examples — compile per the actual item numbers in each volume's tables;
- This card only locates "which volume"; consumption and pricing details, and excluded contents such as concrete mixing and off-site transport, follow the Basic quotas;
- The buildings volume has special provisions (telecom repeater stations, base stations, and signal relay stations: labor and plant x 1.25 when using building quotas; boilers, oil tanks, and sodium-ion softeners per Volume 12) — related but not developed here; consult as needed.
Further Reading
- Volume 13 station yard works, Part 1 general notes: TB/T 10834-2024 "Railway works budget quota, Volume 13: station yard works";
- Volume 1 subgrade works, Part 1 general notes: TB/T 10822-2024;
- Volume 10 building works, Part 1 general notes: TB/T 10831-2024;
- Chapter attribution: TB 10801-2024 "Measures for compiling design estimates (budgets) of railway capital construction projects", Appendix A composite chapter table;
- The specific fallback items (pit/trench excavation, track strengthening -> Volumes 1/2; canopies, capping -> Volume 10; car retarders -> Volume 12): see the corresponding volumes' chapters.