Applying the railway subgrade controlled-blasting quota: class A/B/C judgment conditions and item selection (TB/T 10822-2024, Volume 1, Chapter 1)
The controlled-blasting quota applies only to rock excavation "near an existing railway where a second track is added and blasting must be controlled", classed A/B/C by construction conditions (A strictest: line spacing <=5 m, cut height >=8 m, cut thickness <=4 m, existing slope >1:0.5, sub-hard rock or harder; B: spacing <=10 m, thickness <=10 m, existing slope <=1:0.5; C: neither A nor B, but no natural screen within 50 m of the existing cut slope crest), judged in A->B->C order. The quota already includes possession-caused efficiency loss — no train-interference construction additional fee. Without an existing line (e.g., near villages only), controlled blasting does not apply: use deep/shallow-hole blasting (spoil or requiring crushing: LY-46/47/48/52/53/54; direct cut-to-fill: LY-49/50/51/55/56/57) or static blasting + rock breaking, plus the blast-coverage quota per the blast design.
Applicable Codes
- TB/T 10822-2024 铁路工程预算定额 Vol. 1 路基工程(Ch. 1 路基土石方 章说明)
Topic Positioning
The application rules of the rock blasting quota in Chapter 1 "subgrade earth and rock" of TB/T 10822-2024 "Railway works budget quota, Volume 1: subgrade works": the judgment conditions and classing order of the A/B/C controlled-blasting classes, and the fallback paths where there is no existing line (villages only): deep/shallow-hole blasting, static blasting + rock breaking, and blast-body coverage.
Core Conclusions
Scope of the controlled-blasting quota (chapter note (7), as written): "The controlled-blasting quota applies to rock excavation near an existing railway where a second track is added and blasting must be controlled." It further states that "the quota already allows for the efficiency loss caused by railway possessions; the train-interference construction additional fee is not booked again."
Table 1 "controlled blasting classes" (as written, classes A, B, C by construction conditions):
- Class A: line spacing <=5 m, excavation height >=8 m, excavation thickness <=4 m, existing slope steeper than 1:0.5, rock sub-hard or harder;
- Class B: line spacing <=10 m, excavation thickness <=10 m, existing slope <=1:0.5;
- Class C: not meeting A or B, but rock blasting with no natural screen within 50 m of the existing cut slope crest.
- Table note (as written): "Excavation height is from shoulder level to the highest point of the cut slope; excavation thickness is the average thickness of the blasted body."
- Judgment order: A to C progressively relaxed — test A first, then B, then C; after classing, select the controlled-blasting item by rock hardness (soft/sub-hard/hard rock) and height step (<=8 m / >8 m).
- Fallback paths without an existing line (e.g., near villages only) (chapter notes (4)(5)(6)(8)(9)(10)):
- Deep/shallow-hole blasting: as spoil or requiring crushing before filling, use LY-46, 47, 48, 52, 53, 54 (crushing per the fill-crushing items separately); for direct cut-to-fill, use LY-49, 50, 51, 55, 56, 57.
- Smooth (pre-split) blasting: "quota unit per design slope area; to be used in addition to other rock-excavation quotas. Smooth blasting applies only to non-controlled blasting."
- The static-blasting quota works with the rock-breaking quota; manual or mechanical breaking is chosen per site conditions.
- The blast-body coverage quota is applied in addition per the coverage combination and layer count fixed by the blast design; the flexible-net coverage quota already allows for overlap and waste in net consumption; the sandbag coverage quota excludes the sandbag fill — fill cost per the blast design.
- Related measurement rules (chapter note (12)): excavation and haulage quantities are measured in natural in-situ (undisturbed) volume; smooth (pre-split) blasting per design slope area; blast-body coverage per covered area in 100 m2; cut excavation per the design excavation line.
Applicable Boundaries
- Table 1's A/B/C classes target only the "second track added near an existing railway" scenario — all conditions revolve around the existing line (spacing, existing slope, distance to the existing cut crest) with no village factor; they cannot grade ordinary rock blasting.
- Near villages AND a second-track addition: still class A/B/C per Table 1, but the village side adds the blast-body coverage quota per the blast design (flexible nets/rubber blast blankets/sandbags/steel mesh, layered per the combination; sandbag fill booked separately).
- Near villages without an existing line: controlled blasting does not apply — use deep/shallow-hole blasting (LY-46~57 by spoil/crush or cut-to-fill); where ordinary explosives are unsuitable near residential areas and buildings, use the static-blasting quota together with rock breaking.
- Smooth (pre-split) blasting applies only to non-controlled blasting and only in addition to other rock-excavation quotas — never priced alone.
- Other haulage rules of the chapter (notes (2)(3)): loader haul of loose soil applies only within 20 m; truck incremental-haul items apply only within 10 km; beyond 10 km multiply by 0.85.
Further Reading
- TB/T 10822-2024 "Railway works budget quota, Volume 1: subgrade works", Chapter 1 "subgrade earth and rock", chapter notes (4)-(7) (deep/shallow-hole; smooth/pre-split; static blasting; controlled blasting), (8)-(10) (blast-body coverage), (12) (measurement rules), and "Table 1 controlled blasting classes" (A/B/C conditions and table note).
- Items: deep- and shallow-hole blasting LY-46~57 under "earth and rock excavation and haulage"; controlled blasting (A/B/C steps); static blasting and rock breaking; blast-body coverage (flexible net, rubber blast blanket, sandbag, steel mesh).
- Companion cards: the railway quota system and base-period price mechanism (TB 10801/10811/10813/10814-2024); quota-item selection decision path; red lines on non-adjustable consumptions; earth-rock volume conversion coefficients and spoil disposal estimation.
Keywords
- 控制爆破
- TB/T 10822-2024
- subgrade earthworks (earth and rock)
- A类B类C类
- 既有线
- 深孔浅孔爆破
- 静态爆破
- 爆破体覆盖
- railway works budget quota manual (China Railway)