Railway tunnel waterproof board/geotextile/insulation quantity rules: lap and slack allowances enter the quantities; the quota carries operating waste only (TB/T 10824-2024 tunnel volume)
Waterproof board, geotextile, and insulation quantities are computed per the design laid area plus the lap and slack requirements (TB/T 10824-2024 Volume 3, waterproofing and drainage quantity rules, item 1), on the developed area along the lining inner profile, not the horizontal projection; the quota allows for operating waste only and excludes lap and slack increases (note 2 of the same section) — so lap and slack increments must enter the quantities and be booked; "the quota already includes it" is no excuse to omit them. Mining-method items SY-155/156 (waterproof board), SY-157/158 (geotextile), SY-159 (insulation, unit 100 m2); materials not matching the quota may be swapped; waterstops, blind drains, and permeable hoses per design length.
Applicable Codes
- TB/T 10824-2024 · Budget Quota of Railway Engineering (Volume 3: Tunnel Works)
- TB 10417-2018 · Standard for Construction Quality Acceptance of Railway Tunnel Works
Topic Positioning
Under the railway 2024 quota system: the quantity rules and quota-content boundary for tunnel waterproof boards, geotextiles, and insulation — do lap and slack increments go into the quantities or into the quota consumptions? Developed area or projected area? Per TB/T 10824-2024 "Railway works budget quota, Volume 3: tunnel works".
Core Conclusions
Computation rule (tunnel volume notes, Section 5 waterproofing and drainage, "4. quantity rules", item 1, as written): "Waterproof board, geotextile, and insulation quantities are computed per the design laid area and the lap and slack requirements."
Quota content boundary (same section note 2, as written): "The waterproof board, geotextile, and insulation quotas allow only for operating waste and exclude lap and slack increases." Read together: lap and slack increments must enter the quantities (booked separately) — they are not in the consumptions; when applying the quota, the quantities themselves already carry the increments — do not omit them on the ground that "the quota includes waste"; conversely the lap/slack is not in the consumptions either — no double counting; the two calibers neither overlap nor omit.
Area caliber: per the design laid area — the developed area of the waterproof board/geotextile hung over the full section along the lining inner profile (arch and walls + invert and the parts the design requires), not the horizontal projection of the inner profile; the developed area of arched crown segments markedly exceeds the projection — never take projected values.
Items and swapping: mining-method tunnels — waterproof board SY-155 (gantry laying) / SY-156 (automatic laying); geotextile SY-157 (gantry) / SY-158 (automatic); insulation SY-159 (50 mm thick); all units 100 m2; the automatic (carriage) items carry very little labour — choose per the project execution plan (construction methodology and site organization). The same note 2 permits swapping when the design materials (board, geotextile, insulation, permeable pipe, waterstop) differ from the quota.
Where the design is silent on lap widths, refer to the acceptance-standard workmanship: waterproof board lap >=15 cm, lap reserve at lining ends >=100 cm; geotextile (buffer layer) joint lap >=5 cm (TB 10417-2018 "Standard for constructional quality acceptance of railway tunnel works", Section 10.3).
Applicable Boundaries
- The rules come from the "waterproofing and drainage" section of TB/T 10824-2024 and apply to its board, geotextile, and insulation items; the open-cut tunnel self-adhesive waterproof board is another item (unit 10 m2) with its own application, outside this card's area caliber.
- "Design laid area" follows the design drawings: parts not laid are not counted; lap and slack increments enter per the design, or per the acceptance-standard workmanship parameters where the design is silent.
- The "operating waste only" boundary covers the board/geotextile/insulation items; waterstops, blind drains, and permeable hoses are per design length (quantity rule item 2) — not the area caliber.
- Haulage (transport) quantities follow the lining and structures caliber — materials per required weight in t (Section 6); do not confuse with laid area.
Further Reading
- TB/T 10824-2024 "Railway works budget quota, Volume 3: tunnel works": volume notes Section 5 "waterproofing and drainage" (quantity rules and quota-content boundary), and Chapter 1 mining-method tunnels Section 5 items SY-155~SY-159 (unit 100 m2 — the physical evidence that contents carry operating waste only).
- Lap-width workmanship basis: TB 10417-2018, Section 10.3 (board lap >=15 cm; reserve at lining ends >=100 cm; geotextile buffer joint lap >=5 cm).
- Same-system cards: subgrade controlled blasting (TB/T 10822-2024); double-wall cofferdam infill and bottom seal (TB/T 10823-2024); bridge pit vs subgrade earthworks boundary.