Developed area measurement of damp-proof courses and protective cladding (jacketing) in thermal insulation works and the levels at which seam laps and material wastage are taken: full form and version differences of the formula S=pi x (D+2.1d+0.0082) x L, separate measurement of equipment heads and dome-tank crowns, layer-count and sheet-thickness conversions, and companion itemisation with the insulation layer volume (GB/T 50856-2024 Table M.11.10, GB 50264-2013 Clause 5.7.3, TB/T 10833-2024 volume notes, local consumption standard insulation chapter)
Damp-proof courses and protective cladding are measured in m2 on the outer surface area of the insulation layer, the full formula being S=pi x (D+2.1d+0.0082) x L (D pipe outside diameter, d insulation thickness, L extended metres, 2.1 adjustment coefficient, 0.0082 binding wire diameter or steel strap thickness). In GB/T 50856-2024 Table M.11.10, notes on issues, item 6, the variable table reads '1.03, 2.1 - adjustment coefficients' and omits 0.0082, a scope difference within the same algorithm against the 1.033 + 0.0082 of the 2013 edition, the railway quota manuals and the local consumption standards (about 0.3% on volume, about 3.9% on cladding area); a single take-off file may adopt only one of them. Seam laps and wastage must attract no further coefficient at the measurement level (already embodied in the 2.1 coefficient and in the material consumption of the cladding quota line items, about 2.4% above the pure geometry pi(D+2d)L); they are considered separately only in the design economic-thickness calculation (GB 50264-2013 cladding material wastage and overlap coefficient F9=1.20~1.30) and at the procurement and cutting level. Equipment heads: V=[(D+1.033d)^2/2] x pi x 1.033d x 1.5 x N and S=[(D+2.1d)^2/2] x pi x 1.5 x N; dome-tank crowns: V=2 x pi x r(h+1.033d) x 1.033d and S=2 x pi x r(h+2.1d). On the same pipe section the insulation layer is measured in m3 while the damp-proof course and the cladding are each measured in m2, sharing D/d/L and itemised separately without duplication.
Applicable Codes
- GB/T 50856-2024 通用安装工程工程量计算标准 App. M Table M.8.1、Table M.11.10
- GB 50264-2013 工业设备及管道绝热工程设计规范 第5.7.3条
- TB/T 10833-2024 铁路工程预算定额 Vol. 12 册说明四
- 京建发〔2021〕201号 2021预算消耗量标准 通用安装第十二册 第四章、第五章
Topic positioning
This card answers the three questions in insulation works where measurement scopes are most easily crossed: (1) by what formula and in what unit the developed area of damp-proof courses and protective cladding (jacketing) is measured; (2) at which level - measurement, economic-thickness calculation, or procurement and cutting - seam laps and material wastage actually appear; (3) how equipment heads, dome-tank crowns and multi-layer insulation are each measured, and how they are itemised alongside the insulation layer volume without duplication. Applicable scenarios: separating the three data-taking scopes of BOQ preparation, quota pricing, and galvanised sheet procurement and cutting.
Core conclusions
1) Measurement scope and itemisation. GB/T 50856-2024, the national measurement standard for general installation works, Appendix M 'painting, anti-corrosion and insulation works', Table M.8.1 provides that 'the setting of BOQ items for insulation works, the content of item descriptions, the units of measurement and the measurement rules shall follow Table M.8.1' (Table M.8.1 insulation works, code 031208). The insulation layer is measured by volume in m3; damp-proof courses and protective cladding are measured by area in m2; for the same pipe section the volume and the area are two independent quantities, each itemised separately, neither offset against nor duplicated by the other. Where derusting and painting precede insulation, the items are coded under the corresponding items of Appendix M.1 painting works of this standard (Table M.11.10 notes on issues, item 14).
2) Full form of the area formula for pipes and equipment shells. S = pi x (D + 2.1d + 0.0082) x L (m2)
- D - pipe outside diameter or equipment diameter (m); take the actual outside diameter, not the nominal diameter (a DN100 seamless steel pipe is d108, i.e. 0.108m; a DN100 galvanised steel pipe has an outside diameter of 0.1143m; results differ by 3%~4%);
- d - insulation thickness (m); the design thickness, excluding rendering coats and the cladding sheet thickness;
- L - equipment shell or pipe length (extended metres, m); along the centre line, without deducting the length taken by valves, flanges and fittings; bends measured to the intersection of the crossing centre lines;
- 2.1 - adjustment coefficient (covering cladding laps, seam folds and thickness tolerance);
- 0.0082 - binding wire diameter or steel strap thickness (m). Source basis: GB/T 50856-2024 Table M.11.10, 'notes on issues in Table M.8.1 insulation works (code 031208)', item 6, 'calculation formulas for insulation, damp-proofing and protective cladding of equipment shells or pipes'; its variable table reads 'D - diameter; 1.03, 2.1 - adjustment coefficients; d - insulation thickness; L - equipment shell or pipe length'. The Appendix 1 variable table of the local consumption standards, by contrast, expressly lists '1.033, 2.1 - adjustment coefficients' and '0.0082 - binding wire diameter or steel strap thickness'. That is, the 2024 edition lists only the three symbols D, d and L, records the coefficient as 1.03, and omits the 0.0082 term.
3) The version differences must be settled first.
- Insulation layer volume: V = pi x (D + 1.033d) x 1.033d x L (2013 edition / railway quota scope); the 2024 edition coefficient is 1.03. The effect on volume is about 0.3%.
- Cladding / damp-proof course area: including the 0.0082 term (2013 edition and local consumption standards) versus excluding it (the 2024 edition variable-table form) differs by about 3.9% in area - at DN100 (d108), d=50mm, L=100m: 69.492 m2 with the term, 66.916 m2 without.
- 1.03 / 1.033 and 'with or without 0.0082' must not be mixed within one take-off, reconciliation or settlement file; adopt whichever matches the pricing-basis edition agreed in the contract.
4) Seam laps and material wastage are taken at three separate levels - neither duplicated nor omitted.
- Measurement level (BOQ / quota quantities): no further lap, seam-fold or wastage coefficient is applied. The enlargement of 2.1d over the pure-geometric 2d is itself the lap and thickness-tolerance allowance already built into the rule - at DN100, d=50: pi(D+2.1d)L = 0.669 m2/m against the pure geometry pi(D+2d)L = 0.653 m2/m, the rule value being about 2.4% higher; the seam, lap and operating wastage of the cladding material is further embodied in the material consumption of the cladding quota line items. Multiplying the rule value by a further wastage coefficient is duplicate take-off.
- Design economic-thickness level: GB 50264-2013, the design code for insulation of industrial equipment and pipes, Clause 5.7.3, in its unit-cost formula for insulation structures, gives the cladding material wastage and overlap coefficient F9=1.20~1.30, the insulation material wastage and tax-and-fee coefficient Fi=1.10~1.13 and the tax-and-fee coefficient F1=1.0324; that formula is expressly 'for calculating economic thickness only and shall not serve as the basis for budgets or final accounts' (same clause, commentary item 7).
- Procurement / cutting level: purchases and cutting quantities of metallic cladding (galvanised sheet, aluminium sheet, stainless sheet) follow the geometric developed area or the rule area plus wastage (site practice commonly uses the 1.2-times basis, matching the lower bound of F9=1.20). On the material consumption of the cladding items in the local consumption standards, each 1 m2 of measured area consumes about 1.20 m2 of galvanised sheet - a typical procurement-to-measurement ratio of about 1.2; this guides procurement only and does not change the measurement rule.
5) Conversions of layer count, sheet thickness and item attribution (local consumption standard, general installation Volume 12 'painting, anti-corrosion and insulation works', Chapter 4 insulation works - 9 sections and 265 quota line items covering equipment, pipes, ducts, valves and flanges, sprayed and daubed insulation, pipe damp-proof courses, cladding and anti-condensation).
- Note 10, source wording: the glass-cloth and plastic-sheet cladding items are compiled for one wrapping layer - 'if the design requires two wrapping layers, the quantity is multiplied by 2' - it is the quantity that doubles, not the material consumption; a measurement-scope adjustment, not a quota conversion.
- Note 9: the galvanised sheet, aluminium sheet and stainless sheet cladding items allow comprehensively for sheet thickness below 0.5mm; where a thickness above 0.5mm is used, the main material is converted and the labour is multiplied by 1.2.
- Note 5: insulation of pipes, valves and flanges larger than DN900 follows the corresponding equipment insulation items.
- Note 4: equipment and pipe insulation is compiled on an install-first, insulate-after basis on site; where insulation precedes installation, the labour is multiplied by 0.9.
- Note 6: where a code or the design requires equipment insulation in layers, the quantities are calculated layer by layer (consistent with Table M.11.10 item 5, 'where the design requires layered thermal or cold insulation, this shall be noted', and item 11's layered formulas).
- Note 7: duct insulation items exclude duct flange insulation, which is calculated separately; insulation of duct flanges, valves and fittings follows the corresponding duct insulation items.
- Note 8: field insulation of pipe joints applies to joints of directly buried pre-insulated pipes; tee-joint insulation follows the elbow insulation item with the consumption multiplied by 1.3.
- Note 3: pipe insulation items already allow for fittings other than flanges and valves; equipment insulation items already allow for heads other than flanges and manholes - integral equipment insulation therefore carries no separate head item.
- Measurement rules of the chapter: equipment insulation, by material and insulation thickness, on the volume shown on the design drawings; pipe insulation, by material and pipe size, on the volume shown on the design drawings; duct insulation, by material and insulation thickness, on the net duct area; valve and flange insulation, by material, on the volume shown on the design drawings - the Appendix 2 tables (volume take-off tables for steel pipes with insulation, and valve and flange insulation tables) may be used, and where they carry no matching size, the Appendix 1 formulas apply.
6) Equipment heads and dome-tank crowns (Table M.11.10 items 10 and 11; the same formulas in Appendix 1 of the local consumption standards).
- Equipment heads (dished / elliptical; N = number of heads): V = [(D + 1.033d)^2 / 2] x pi x 1.033d x 1.5 x N; S = [(D + 2.1d)^2 / 2] x pi x 1.5 x N (m2). 1.5 is the head surface development coefficient; D is the nominal head diameter.
- Dome-tank crowns: V = 2 x pi x r x (h + 1.033d) x 1.033d; S = 2 x pi x r x (h + 2.1d), where r is the spherical radius of the dome and h the dome height.
- Where the BOQ requires split items, the shell and the heads are measured separately and added; but under the local consumption standards the equipment insulation items already include the heads (other than flanges and manholes), so when applying the quota the heads must not be split out as a separate item.
7) Companion correspondence with the insulation layer volume. On the same pipe section: insulation layer as V (m3), damp-proof course as S (m2), cladding as S (m2) - all three share the same D, d and L. Even where the damp-proof course and the cladding form two build-ups (e.g. damp-proof course + metallic cladding), the area algorithm is identical (both take the outer surface area of the insulation layer) and the items are set separately by material and thickness; material and thickness are item description content, not formula variables. With multi-layer insulation built layer by layer, D in the outer-layer formula is the outside diameter after the inner layers are complete; quantities are calculated layer by layer against the items for the design thickness.
Boundaries of applicability
- 1.03 (GB/T 50856-2024) and 1.033 (2013 edition, railway TB/T 10833-2024, local consumption standards), and 'with or without the 0.0082 term', are mutually exclusive scopes; a single take-off or reconciliation file adopts only one. Under the 2024 edition the formula is carried in figure form - coefficients and variables must be verified against the official figure, not applied from memory of the 2013 edition.
- The 2.1 coefficient already carries the laps and thickness tolerance: rule value multiplied by a further wastage coefficient = duplicate take-off; procurement on pure geometric development with no wastage = certain shortfall.
- Duct insulation is measured on the net duct area (m2) and does not take the pipe shell formula; valve and flange insulation boxes are taken from Table M.11.10-1 (cladding, m2) and Table M.11.10-2 (insulation layer, m3) multiplied by count and merged in - not by a percentage on pipe length, and the shell formula does not apply either.
- Heat-traced pipes first derive the combined diameter D' under Table M.11.10 items 7-9, then enter the formula: single-pipe tracing, or two-pipe tracing with equal sizes and an included angle under 90 degrees, D' = D1 + D2 + (10~20mm); two further cases exist (two pipes, equal sizes, angle over 90 degrees; two pipes, unequal sizes, angle under 90 degrees). D1 is the main pipe diameter and D2 the tracing pipe diameter.
- The batch of local quota conversion factors in point 5 (two wrapping layers: quantity x 2; sheet over 0.5mm: labour x 1.2; insulation before installation: labour x 0.9; tees on elbow items: x 1.3; over DN900: equipment insulation items) reflects that region's consumption standard; across regions or industries the local quota volumes govern - no cross-volume borrowing.
- This card does not deal with unit rates or cost figures for insulation volume or cladding area; pricing follows the governing quota volume and market prices.
Further reading
- GB/T 50856-2024, national measurement standard for general installation works, Appendix M: Table M.8.1 insulation works (code 031208); Table M.11.10, 'notes on issues in Table M.8.1 insulation works', items 1-5 (features to be described: equipment form, layer count, object, structural form), item 6 (formulas for shell insulation, damp-proofing and cladding), items 7-9 (combined value D' of heat-traced pipes, gap 10~20mm), item 10 (equipment heads), item 11 (dome-tank crowns and layered formulas), items 12-13 (Table M.11.10-1 flange and valve insulation-box cladding, m2; Table M.11.10-2 flange insulation-box insulation layer, m3), item 14 (derusting and painting first: itemise under Appendix M.1).
- GB 50264-2013, design code for insulation of industrial equipment and pipes, Clause 5.7.3 (unit-cost formula for insulation structures and the commentary on F9=1.20~1.30, Fi=1.10~1.13, F1=1.0324), Tables F.0.1-F.0.3 (construction cost values); note that pipes over 720mm in diameter count their insulation and cladding as equipment.
- TB/T 10833-2024, railway works budget quota manual, Volume 12 'locomotive and rolling stock machinery works', volume notes 'IV. Measurement rules', items 1, 4, 5 and 6 (pipe centre-line length without deducting valves, flanges and fittings; painting and anti-corrosion on outer surface area; insulation volume formula; single- and multi-layer cladding algorithms).
- Local consumption standards (e.g. the Beijing 2021 budget consumption standard), general installation Volume 12 'painting, anti-corrosion and insulation works': Chapter 4 insulation works, notes 3-10 and the measurement rules, Appendix 1 (insulation quantity formulas), Appendix 2 (take-off tables for steel pipes with insulation volume, valve insulation and flange insulation); Chapter 5 'pipe field-joint coating and repair', with the source formulas for insulation volume, damp-proofing and cladding, equipment heads, dome-tank crowns and heat-traced pipes (the 1.033 / 2.1 / 0.0082 variable table).
Keywords
- 绝热保护层
- 防潮层面积
- 咬口搭接
- 材料损耗系数
- 0.0082捆扎线直径
- 设备封头绝热
- 调整系数2.1
- 031208