How to compile the insulation (hot service / cold service) quantity summary table when multiple pipe diameters and insulation thicknesses coexist: the minimum row unit (material type x thickness x diameter band x hot/cold service), the four-step workflow (band and group -> calculate segment by segment -> coefficient check -> totals reconciliation), the header field composition, and the layered treatment of BOQ versus quota coverage (GB/T 50856-2024 Annex M code 031208, GB 50264-2013, HG/T 20692-2014, TB/T 10833-2024)

The key to multi-diameter, multi-thickness insulation quantities is layering, not formulas. At the BOQ layer, per GB/T 50856-2024 Table M.8.1 'other pipeline insulation' 031208002, the item descriptions are insulation material type, insulation thickness, pipe outside diameter and cork type, unit m3; only rows identical in all three may be merged, and rows must never merge across outside diameters. At the quota layer, rows merge by the budget base-price line item's 'outside-diameter band x thickness band'; identical bands may be combined. The minimum row unit of the summary table = material type x thickness d x diameter band D x hot/cold service (x piping system). Compile in four steps: (1) band and group (D always the outside diameter, jacketed pipes take the jacket outside diameter, traced pipes fill the main pipe diameter only; d banded per 10mm; d over 80mm split into two or more layers; hot and cold totalled separately) (2) calculate segment by segment (unit-length quantity first, then multiply by length) (3) coefficient check (quantities entered at calculated net values, no coefficients included) (4) totals reconciliation (length, volume and area tied out three ways, hot and cold listed separately).

Applicable Codes

  • GB/T 50856-2024 · Standard for measurement of general mechanical, electrical, plumbing and fire services App. M Table M.8.1(code 031208)、问题说明第5~14条、Table M.11.10-1、Table M.11.10-2
  • GB 50264-2013《工业设备及管道绝热工程设计规范》第6.2.3条、第6.2.4条
  • HG/T 20692-2014《化工企业热工设计施工图内容和深度统一规定》第18.6.2条
  • TB/T 10833-2024 · Budget Quota of Railway Engineering (Volume 12: Locomotive and Rolling Stock Machinery Works) 册说明四.1~四.6
  • 北京市2021预算消耗量标准(京建发〔2021〕201号)通用安装第十二册 刷油防腐蚀绝热工程 第五章

Topic positioning

This card addresses how to compile the insulation quantity summary table in building services works (Annex M, insulation works code 031208) when multiple pipe diameters and several hot/cold insulation thicknesses appear together: fix the coverage layering first, then the four-step compilation workflow and header field design, and finally the closing direction of the footer reconciliation. It serves cost estimating, BOQ itemisation and quantity review.

Core conclusions

I. Layer first, then order the rows

One summary table must satisfy three coverage regimes at once; the most common error is not a wrong formula but mixing the BOQ layer and the quota layer in the same row:

Layer Itemisation granularity Basis Treatment principle
BOQ layer (external) Rows may merge only where insulation material type + insulation thickness + pipe outside diameter are all identical GB/T 50856-2024 Table M.8.1; the item descriptions of other pipeline insulation 031208002 are '1. insulation material type 2. insulation thickness 3. pipe outside diameter 4. cork type', unit of measurement m3 No merging across outside diameters; crossing them leaves the item description incomplete
Quota layer (rate build-up) Merge by the bands of the budget base-price / consumption line items (e.g. outside-diameter bands no more than 133 and no more than 325 combined with thickness bands into one band) Line items in each volume are set on the dual bands 'pipe outside diameter x insulation thickness' Identical bands may merge; the merged band row maps back to the line-item code
Reconciliation layer (footer) Banded subtotals and grand totals in three directions: length, volume, area Net-value coverage Only rounding differences allowed; no balances left hanging

Hence the summary table's minimum row unit = insulation material type x insulation thickness d x diameter band D x hot/cold service (x piping system); every row must carry its detailed calculation basis and be tagged with the BOQ code and the quota line-item code.

The BOQ description entries must also be written out in full per the standard: equipment insulation (031208001) must additionally describe the equipment form (vertical, horizontal or spherical); the descriptions of vapour barrier and protective layer (031208007) are material, thickness, number of layers, object and structural form, where 'object' means equipment, piping, ventilation ducting, valves, flanges or steelwork, and 'structural form' means general steelwork, H-section steelwork or pipe-rack steelwork; where the design requires hot and cold insulation in layers, this must be noted in the description; where derusting and painting are needed before insulation, list separately under the painting items of Annex M.1.

II. Summary table compilation steps

Step What is done Key rules and basis Common mistakes
(1) Band and group Extract outside diameter D, length L, medium temperature and insulation code from the pipe data sheets and the spool erection material lists; sort and group by (material type, d, D band, hot/cold) and sum lengths within each group D is always the outside diameter: jacketed pipes take the jacket outside diameter, traced pipes fill the main pipe diameter only; d is banded in 10mm steps (minimum thickness 20mm for rigid foam plastics, 30mm for other rigid insulation products); insulation over 80mm thick is applied in two or more layers; pipe data must be totalled, hot and cold separately Mixing nominal diameter with outside diameter; counting DN100 and d108 as two duplicate bands; forcing systems with different medium temperatures into one row
(2) Calculate segment by segment Compute unit-length quantities first (v, m3/m; s, m2/m), then multiply by length for V and S; for layered application calculate layer by layer and apply each layer's design-thickness line item Pipe: V = pi x (D + 1.033d) x 1.033d x L; S = pi x (D + 2.1d + 0.0082) x L (0.0082 is the tie-wire diameter or strapping thickness); vessel shells use the same formula; vessel heads use the dedicated head formula (with the 1.5 factor and the head count N); dome-roof tank heads V = 2pir x (h + 1.033d) x 1.033d, S = 2pir x (h + 2.1d); valves V = pi(D + 1.033d) x 2.5D x 1.033d x 1.05 x N, S = pi(D + 2.1d) x 2.5D x 1.05 x N, or read the flange and valve insulation-box quantity tables per design count (protective layer m2 and insulation m3 in separate tables); pipe erection length on the centreline, no deduction for valves, flanges or fittings Using 'bare-pipe circumference x d' as the volume (missing the 1.033d self-increment of thickness); deducting valve and flange lengths from the length; adding fittings as a percentage
(3) Coefficient check For each band check the geometric coefficient version, whether layering applies, whether quota material contents were double-counted, whether erection conversion coefficients leaked into quantities Quantities in the table are entered at calculated net values without coefficients; the coefficient version must be uniform within one project Multiplying 1.033 twice (once in the formula and again in the unit rate); re-multiplying quota material contents as a quantity coefficient
(4) Totals reconciliation Tick off the three lines and close the footer with banded subtotals plus the grand total Length line: the sum of banded L ties to the total erected pipe length (centreline, no deduction for valves, flanges or fittings); volume line: the sum of banded V ties to the layered, banded calculations, hot and cold totalled separately; area line: the sum of protective-layer S ties to the insulation outer surface, multi-layer protection converted as single-layer area x number of layers Reconciling totals only, not bands; mixing hot and cold into one total

Traced piping must first compute the combined value D' and then enter the V and S formulas: single-pipe tracing and double-pipe tracing (equal diameters, included angle under 90 degrees) D' = D1 + D2 + (10~20mm); double-pipe tracing (equal diameters, angle over 90 degrees) D' = D1 + 1.5D2 + (10~20mm); double-pipe tracing (unequal diameters, angle under 90 degrees) D' = D1 + D2 + (10~20mm). D1 is the main pipe diameter, D2 the tracing pipe diameter, and 10~20mm the gap between the main and tracing pipes.

III. Header field composition

Set the columns in the following order so that 'detail traceability, band-level rate build-up, and reconcilable totals' all hold at once:

  1. Locating columns: item no., pipe tag / system name, medium temperature, insulation code (hot/cold), remarks (for layered application note the number of layers and each layer's thickness).
  2. Parameter columns: pipe outside diameter D (mm, always the outside diameter), pipe length L (m, extended metres, on the centreline, no deduction for valves, flanges or fittings), insulation thickness d (mm, banded per 10mm), number of insulation layers.
  3. Material columns: insulation material name and type (e.g. cork type per the item description).
  4. Calculation columns: unit-length volume v (m3/m), insulation volume V (m3), unit-length protective-layer area s (m2/m), protective-layer area S (m2).
  5. Rate build-up columns: BOQ item code / name (e.g. 031208001 equipment insulation, 031208002 other pipeline insulation, 031208007 vapour barrier and protective layer) and the combinable budget base-price (consumption) line-item codes.
  6. Total rows: subtotals per band plus the grand total for the whole table, hot and cold totalled separately; insulation material volume (m3) and protective-layer area (m2) reported separately.

Applicable boundaries

  • Applies to quantity summary and BOQ compilation for insulation (hot and cold) of equipment, piping, ventilation ducting, valves, flanges and steelwork in industrial and civil building services works; building envelope and roof insulation follow the relevant annexes of the building and decoration works measurement standard, not this table.
  • The summary table is a net-value table: quantities are entered at calculated net values without coefficients; erection wastage, procurement quantities and quota material contents must not enter this table - they are handled at the rate build-up stage.
  • Coefficient versions differ and must be unified within one project: the variable table in GB/T 50856-2024 Table M.11.10 notes '1.03, 2.1 - adjustment coefficients' and omits the 0.0082 term; railway TB/T 10833-2024 volume notes use 1.033; some local consumption standards use 1.033 and state 0.0082 as the tie-wire diameter or strapping thickness. Mixed coverage is the first cause of summary tables not tying out.
  • Insulation over 80mm thick must be calculated in layers; for the same material the inner and outer layer thicknesses should be roughly equal, and for different materials the inner/outer thickness ratio must keep the absolute value of the interface temperature within 0.9 times the absolute value of the outer material's recommended service temperature (for cold service, 0.9 times the lower limit of the recommended service temperature). Design thicknesses not banded per 10mm must be converted to the adjacent band before applying line items and noted in remarks.
  • Valve and flange insulation boxes are counted per unit / per pair by design quantity and must not be spread into pipe extended metres; deducting valve and flange lengths from the pipe length is an unlawful deduction.

Further reading

  • GB/T 50856-2024 'Quantity take-off standard for general building services works', Annex M painting, anti-corrosion and insulation works: Table M.8.1 insulation works (code 031208) item setting and measurement rules; Annex M explanatory notes 5-14 (layered application notation, shell and pipe formulas, traced-pipe combined value D', vessel heads and dome-roof tank heads, layered calculation formulas, Table M.11.10-1 flange and valve insulation box protective-layer quantity table, Table M.11.10-2 flange insulation box insulation-layer quantity table, derusting and painting to Annex M.1).
  • GB 50264-2013 'Code for design of insulation of industrial equipment and pipes', cl. 6.2.3 (thickness banded per 10mm and minimum thickness), cl. 6.2.4 (over 80mm layered, thickness ratios for same and different materials, alternate hot/cold insulation layers).
  • HG/T 20692-2014 'Unified specification for content and depth of thermal engineering design working drawings of chemical plants', cl. 18.6.2 (content and format of the pipe insulation material table: outside-diameter convention, m3 basis, net values without coefficients, main insulation material volume and protective-layer area computed separately, hot and cold totalled separately, parameters extracted from pipe data sheets and spool erection material lists).
  • TB/T 10833-2024 'Railway works budget quota manual, Volume 12, locomotive depot and rolling stock machinery works', volume notes IV 'quantity take-off rules' cl. 1-6 (pipe length on the centreline without deduction for valves, flanges or fittings, valves per unit, flanges per pair, coating and anti-corrosion per design area ignoring irregularities, insulation volume formulas, protective layer single- and multi-layer algorithms).
  • Beijing 2021 budget consumption standard (Jing Jian Fa [2021] No. 201), general building services Volume 12, painting, anti-corrosion and insulation works Chapter 5, with complete formulas for vessel shells and pipes, vessel heads, dome-roof tank heads, traced pipes, valves and flange insulation (including the 0.0082 tie-wire term), usable to verify the formula version.
  • Local BOQ pricing guides list for each Table M.8 item the codes of its 'combinable budget base-price line items' (pipe and equipment insulation, valve insulation, flange insulation, vapour barrier and protective layer, insulation boxes, insulation trays); the summary table's rate build-up columns can hook directly onto them.