Quantity calculation of duct and pipeline thermal insulation: formulas and BOQ listing (GB/T 50856-2024 Appendix M)
Insulation works are uniformly listed under GB/T 50856-2024 Appendix M (code 031208): insulation layers in m3, protective/vapor barriers in m2. Pipeline insulation volume V = π x (D + 1.033δ) x 1.033δ x L (the original adjustment coefficients in GB/T 50856-2024 M.11.10 problem note 6 are 1.03 and 2.1; TB/T 10833-2024 uses 1.033 — the same caliber expressed with different precision); duct insulation is computed as developed area x calculated thickness, the developed area by centerline length including bends, tees and other fittings but excluding components, without deducting inspection holes and supply outlets; multi-layer work is computed layer by layer, heat-traced pipes first derive the comprehensive value D', and derusting/painting before insulation are listed separately under Appendix M.1.
Applicable Codes
- GB/T 50856-2024 通用安装工程工程量计算标准 App. M 刷油、防腐蚀、绝热工程(Table M.8.1 绝热工程 031208、Table M.11.10 问题说明第1~14条)
- TB/T 10833-2024 铁路工程预算定额 Vol. 12 机务车辆机械工程 册说明四、工程量计算规则第1~6条及Ch. 7第四节绝热
- TB/T 10824-2024 铁路工程预算定额 Vol. 3 隧道工程 册说明第五节工程量计算规则第1、2条
- DB11/T 2382-2024 建设工程施工消耗量标准 第6.12.34~6.12.39条
Topic Positioning
This card covers the quantity calculation methods and BOQ listing calibers of duct insulation and pipeline insulation (insulation works), applicable to installation works listing BOQs per GB/T 50856-2024 and taking off quantities with the accompanying quotas.
Core Conclusions
- Listing: insulation works are uniformly listed under GB/T 50856-2024 Appendix M "painting, anti-corrosion, and insulation works" (code 031208), with equipment insulation, other pipeline insulation, and ventilation duct insulation separately coded; insulation layers in m3, vapor barriers/protective layers in m2. Insulation and protective-layer installation of equipment, pipelines, and components are all listed under Appendix M (HVAC see Clause G.5.5).
- Pipeline insulation layer volume: V = π x (D + 1.033δ) x 1.033δ x L (D = pipe outer diameter, δ = insulation thickness, L = centerline linear meters). Note the coefficient caliber: GB/T 50856-2024 Appendix M Table M.11.10 problem note 6 (formulas for equipment shells or pipeline insulation, vapor barriers, and protective layers) gives adjustment coefficients of "1.03, 2.1"; TB/T 10833-2024 Volume 12 volume explanation quantity rule 5 uses 1.033 — the same calculation caliber expressed with different precision; keep coefficient use consistent when reconciling BOQ with quota. With multi-layer work, quantities are computed layer by layer, executing the corresponding thickness items.
- Protective/vapor barriers by the post-insulation outer surface: single-layer protection area = the protected pipe's outer-surface perimeter x installed length; multi-layer protection = single-layer area x number of layers (TB/T 10833-2024 volume explanation rule 6).
- Duct insulation: in m3, computed as duct developed area x insulation calculated thickness. The developed area is computed by centerline length, including the lengths of bends, tees, reducers, and round-to-rectangular transitions, excluding the lengths of valves, outlets and other components; without deducting the areas of inspection holes, measuring holes, supply outlets, and suction openings; tapered round ducts by average diameter, rectangular by average perimeter. Rectangular duct developed area S = 2 x (A + B) x L (A, B = side lengths).
- Heat-traced pipes per M.11.10 notes 7~9 first derive the comprehensive traced value D' (three cases: single pipe / double pipes same diameter angle < 90°, double pipes same diameter angle > 90°, double pipes different diameters angle < 90°; substituting D' yields the insulation layer, vapor barrier, and protective layer quantities); insulation boxes at flanges and valves are computed from Table M.11.10-1 (protective layer, m2) and Table M.11.10-2 (insulation layer, m3); derusting and painting before insulation are listed separately under the Appendix M.1 painting items (M.11.10 problem note 14).
Applicable Boundaries
Applies to GB/T 50856-2024 BOQ measurement calibers and the accompanying quotas (e.g., TB/T 10833-2024); L is the pipeline centerline length, without deducting the lengths of valves, flanges, or fittings, and bends are computed at the intersection of the crossing centerlines (TB/T 10833-2024 volume explanation rule 1). Painting and anti-corrosion quantities are computed by design area, without counting the areas of fittings, flanges, valves and other irregularities (volume explanation rule 4). Civil projects select insulation thickness per GB 50736-2012 Appendix K economic thickness; industrial projects by the economic-thickness method; where the design states a thickness, take the design value. Regional quotas (e.g., municipal consumption standards) may treat protective layers and additional lengths differently — the current local quota of the project prevails.
Further Reading
See GB/T 50856-2024 Appendix M: Table M.8.1 insulation works (code 031208, BOQ item setting and calculation rules), Table M.11.10 insulation calculation formulas and problem notes (notes 1~14: equipment forms, layers, objects, structural forms, multi-layer notation, the equipment-shell or pipeline insulation/vapor-barrier/protective-layer formulas with the 1.03 and 2.1 adjustment coefficients, the single- and double-pipe heat-tracing comprehensive value D', the equipment head and dome formulas, and the flange/valve insulation-box tables); Appendix G Table G.2.1 ventilation duct fabrication and installation problem note 1 (duct developed area rules); TB/T 10833-2024 Volume 12 volume explanation quantity rules 1~6 (pipeline length, valves and flanges by count/pair, painting area, insulation volume V = π x (D + 1.033δ) x 1.033δ x L, protective layer area); GB 50736-2012 Appendix K (insulation thickness selection tables and thickness correction formulas).
Keywords
- 绝热工程
- 管道保温
- 绝热层体积
- 保护层面积
- 镀锌铁皮展开量
- 阀门法兰绝热盒
- GB/T 50856-2024
- TB/T 10833-2024