Four-layer make-up of pipeline (equipment) insulation structures and functional determination: functions, positions and common materials of the anti-corrosion layer, insulation layer, moisture barrier and protective layer, and the code basis for 'the moisture barrier is indispensable in cold insulation' and for failure chains when a layer is missing
GB 50264-2013 prescribes the mandatory layers separately for heat and cold insulation: Clause 6.1.1 'a heat insulation structure shall consist of the heat insulation layer and the protective layer'; Clause 6.1.2 'a cold insulation structure shall consist of the cold insulation layer, the moisture barrier and the protective layer'; GB 50349-2015 Clause 8.3.2 adds 'an anti-corrosion layer shall be provided beneath the heat insulation layer or the cold insulation layer'. The failure chain when a cold insulation structure lacks the moisture barrier: outside water vapour migrates inward with the heat flow -> condensation or even icing -> thermal conductivity rises and the structure cracks, admitting more moisture in a vicious cycle -> cold insulation fails. For pipes laid in trenches the outer surface of the insulation layer should also carry a moisture barrier, while a general above-ground heat insulation structure needs none for practical adequacy. Omitting the protective layer leaves 'the service life of the vast majority of insulation layers very short'. The anti-corrosion layer is not a layer of the insulation structure and must be listed separately under the painting (031201) or anti-corrosion coating (031202) BOQ items; insulation itself is 031208.
Applicable Codes
- GB 50264-2013《工业设备及管道绝热工程设计规范》第 4.2.1、4.3.1、6.1.1、6.1.2、6.3.1、6.4.1、6.4.5 条
- GB 50349-2015《气田集输设计规范》第 8.3.2 条
- GB 50126-2008《工业设备及管道绝热工程施工规范》第 6.1.1 条
- GB 50019-2015《工业建筑供暖通风与空气调节设计规范》第 13.1.3 条
- GB 50738-2011 · Code for construction of ventilation and air-conditioning works 第 13.3.1 条
- GB 50185-93《工业设备及管道绝热工程质量检验评定标准》第 5.0.1 条
- GB/T 50856-2024 · Standard for measurement of general mechanical, electrical, plumbing and fire services App. M Table M.1.1(031201)、M.2.1(031202)、M.8.1(031208)
- GB/T 8175《设备及管道绝热设计导则》
- SH 3010《石油化工设备和管道隔热技术规范》
Topic positioning
This card addresses the layer make-up of insulation structures on industrial equipment and pipelines: the function, position and common materials of the anti-corrosion coating, the insulation layer (heat insulation / cold insulation), the moisture barrier and the protective layer, the failure consequences of omitting each layer, and the code clauses for the determination. It resolves structure and provision only; measurement yardsticks (volume, developed area, itemisation) are on a companion card.
Core conclusions
I. The codes prescribe the mandatory layers separately for heat and cold insulation
- Heat insulation structure: GB 50264-2013 Clause 6.1.1, original text: 'A heat insulation structure shall consist of the heat insulation layer and the protective layer.' Commentary: 'This clause is a revision... In a heat insulation structure the heat flow runs outward, and outside moisture and water generally do not penetrate the insulation layer. Clauses 4.3.1, 6.4.1 and 6.4.4 of this code already impose watertightness requirements on the selection and installation of protective layer materials. Hence a general heat insulation structure without a moisture barrier already satisfies practical requirements. Insulated pipes in trenches mostly work in damp conditions and the insulation layer is often wetted, so a moisture barrier is required in the structure and water-repellent insulation materials are preferred.'
- Cold insulation structure: Clause 6.1.2, original text: 'A cold insulation structure shall consist of the cold insulation layer, the moisture barrier and the protective layer.' Commentary: 'This clause is a revision. The anti-rust layer in a cold insulation structure is designed under the relevant anti-corrosion codes and is outside the scope of this code; this revision deletes the anti-rust layer. The cold insulation structure now consists of the cold insulation layer, the moisture barrier and the protective layer, consistent with the current industry standard SH 3010, Technical specification for thermal insulation of petrochemical equipment and piping.'
- Anti-corrosion layer: GB 50349-2015 'Code for design of gas field gathering', Clause 8.3.2, original text: 'A heat insulation structure shall consist of the heat insulation layer and the protective layer. A cold insulation structure shall consist of the cold insulation layer, the moisture barrier and the protective layer. An anti-corrosion layer shall be provided beneath the heat insulation layer or the cold insulation layer.'
- Layer order (inside out): anti-corrosion coating on the pipe outer surface -> insulation layer (heat / cold) -> moisture barrier (mandatory for cold insulation; recommended for trench heat insulation) -> protective layer (always mandatory).
- One hard boundary for pricing: GB 50264-2013 has deleted the 'anti-rust layer' from the insulation structure in this revision, anti-corrosion being designed separately under the anti-corrosion codes, so the anti-corrosion layer is not a layer inside the insulation items; when building the BOQ or applying quotas it is listed separately under painting (code 031201) or anti-corrosion coatings (code 031202), insulation works being 031208 (GB/T 50856-2024 Appendix M, Tables M.1.1 / M.2.1 / M.8.1).
II. Four-layer comparison of function / position / common materials
| Layer position | Layer name | Function (mechanism) | Location | Common materials and requirements | Code status |
|---|---|---|---|---|---|
| (1) Innermost | Anti-corrosion coating | Isolates external corrosive media from the steel substrate (media corrosion of the pipe bore is handled by internal corrosion protection or lining and is outside the insulation structure) | Pipe outer surface, beneath the insulation layer | Selected per the anti-corrosion codes; GB 50738-2011 Clause 13.3.1 makes 'anti-corrosion of steel pipes completed' a precondition before insulation work | Outside the scope of GB 50264-2013; required beneath the insulation layer by GB 50349-2015 Clause 8.3.2 |
| (2) | Insulation layer (heat insulation / cold insulation) | The core functional layer: cuts heat loss (heat insulation) or cold loss (cold insulation), holds process temperature, prevents burns and condensation; cold insulation thickness design must also keep the moisture barrier surface above dew point even under severe ambient temperature and humidity | Outside the anti-corrosion layer, inside the moisture barrier, wrapping the pipe | GB 50738-2011 Clause 13.3.1 lists boards (rock wool board, foil-faced rock wool board, superfine glass wool felt / board, self-extinguishing polystyrene foam board, flame-retardant polyurethane foam board, foamed elastomeric board, aluminium-magnesium insulation board etc.), shell products (rock wool / slag wool / glass wool, rigid polyurethane shells, foamed elastomeric shells, polystyrene shells, foamed concrete / perlite / vermiculite precast blocks), rolls (polystyrene, rock wool, foamed elastomer, foil-faced superfine glass wool); water-repellent materials preferred for trench heat insulation | Mandatory (Clauses 6.1.1 / 6.1.2) |
| (3) | Moisture barrier (vapour barrier) | Blocks ingress of outside water vapour inward, keeps the insulation layer dry and holds the design thermal conductivity; must be complete and tight, uniform in thickness, free of cracks, pores and blisters | Outside the insulation layer, inside the protective layer | GB 50264-2013 Clause 4.2.1: 'Moisture barrier materials shall be chosen for good resistance to vapour permeation, waterproofness and damp-proofing, and with water absorption no more than 1.0%.' GB 50738-2011 Clause 13.3.1 lists resin-bonded glass cloth, polyethylene film, reinforced aluminium foil (doubles as protective layer) etc. | Mandatory for cold insulation (Clause 6.1.2); recommended at the outer surface of trench pipe heat insulation (Clause 6.3.1) |
| (4) Outermost | Protective layer | Mechanical protection, waterproofing, resistance to atmospheric corrosion and light ageing, extending insulation life; must be integrally waterproof | Outermost layer of the insulation structure | GB 50738-2011 Clause 13.3.1 lists galvanised steel wire mesh, glass cloth, aluminium sheet, galvanised iron sheet, stainless steel sheet, aluminium foil paper etc.; outdoor above-ground pipes preferably metal, FRP or foil-FRP thin sheet (GB 50019-2015 Clause 13.1.3 item 4) | Mandatory (Clause 6.4.1 'a protective layer shall be provided on the outside of the insulation structure') |
III. Consequences of omitting a layer (failure chains)
- Cold insulation without a moisture barrier -> insulation failure. GB 50264-2013 Clause 6.3.1 commentary, original text: 'In a cold insulation structure the direction of heat flow is the reverse of a general heat insulation structure; outside moisture (water vapour) migrates with the heat flow into the cold insulation layer, producing condensate or even ice, raising the thermal conductivity of the cold insulation material, and cracking and damaging the structure - hence a moisture (vapour) barrier must be provided in cold insulation structures. The thickness design of the cold insulation layer must keep the temperature of the moisture barrier surface above the dew point even under very adverse ambient temperature and humidity, that is, the moisture barrier must have good gas tightness and weather resistance. The moisture barrier is the key to waterproofing and damp-proofing in the cold insulation structure and to maintaining its insulating effect, so the moisture barrier must be complete and tight, uniform in thickness, and free of cracks, pores, blisters and similar defects.' GB 50126-2008 Clause 6.1.1 commentary further gives the vicious-cycle mechanism: 'Moisture in the air entering the cold insulation layer condenses or even freezes and destroys the cold insulation structure; the damaged structure lets in more humid air, and this vicious cycle severely impairs the cold insulation effect. Therefore a moisture barrier must be provided outside the cold insulation layer.'
- The boundary for omitting the moisture barrier in heat insulation. In a general (above-ground) heat insulation structure the heat flow runs outward and outside moisture generally does not penetrate; omitting the moisture barrier already satisfies practical requirements. But 'trenches are mostly damp with varying degrees of water ingress. Insulated pipes are often wetted, so a moisture barrier should also be provided on the outer surface of the insulation layer of pipes in trenches' (Clause 6.3.1 commentary; GB 50126-2008 Clause 6.1.1 to the same effect).
- Omitting the protective layer -> service life collapses. Clause 6.4.1, original text: 'A protective layer shall be provided on the outside of the insulation structure. The protective layer shall be tight and waterproof; it shall resist atmospheric corrosion and light ageing; installation shall be convenient, the appearance neat; it shall have adequate mechanical strength and a long service life. Under environmental change and vibration it shall not leak, crack, open at joints or fall off.' Commentary: 'Without a protective layer, the service life of the vast majority of insulation layers is very short. Although the composite silicate coatings now in use may dispense with a protective layer when installed indoors, waterproofing and similar treatment is still required outdoors.'
- Protective layer openings not sealed -> local water ingress defeats the integral waterproofing. Clause 6.4.5, original text: 'The protective layer shall have an integral waterproofing function and shall prevent water and water vapour from entering the insulation layer. Points where water and water vapour easily penetrate into the insulation layer shall be sealed with mastic or sealant.'
- Secondary risk of omission: material compatibility. Clause 4.3.1, original text: 'Protective layer materials shall be waterproof, damp-proof, resistant to atmospheric corrosion and chemically stable, and shall not corrode or dissolve the moisture barrier materials or the insulation layer materials.'
- Layering requirements for non-closed-cell materials. GB 50019-2015 Clause 13.1.3, original text: '3 With non-closed-cell materials for cold insulation, a vapour barrier and a protective layer shall be provided on the outer surface; with non-closed-cell materials for heat insulation, a protective layer shall be provided. 4 For outdoor above-ground pipes a protective layer shall be provided outside the insulation layer, preferably metal, FRP or foil-FRP thin sheet.' Items 1 and 2 of the same clause: '1 The outer surface of the cold insulation layer shall not produce condensate. 2 Between pipes and supports, and where pipes pass through walls or floors, measures against cold bridges and thermal bridges shall be taken.'
IV. Scope of moisture barrier quality inspection
GB 50185-93 Clause 5.0.1: 'This chapter applies to quality inspection of moisture barriers over the cold insulation layers of equipment and pipes and over the insulation layers of pipes laid in trenches... This clause provides that a moisture barrier be added over the cold insulation layers of equipment and pipes and over the insulation layers of pipes laid in trenches. It does not cover moisture barriers of heat insulation of equipment and pipes above ground... but where the engineering design documents so require, quality inspection and evaluation shall follow this clause.' That is, above-ground heat-insulated pipes without a design requirement may have no moisture barrier inspection item.
Applicable boundaries
- This card follows GB 50264-2013 'Code for design of insulation works of industrial equipment and pipelines' (industrial equipment and pipelines). Insulation structures of HVAC water pipes and ducts in civil buildings additionally follow GB 50019-2015 Clause 13.1.3 and the building-energy yardsticks of GB 50736 etc., with finer material and anti-condensation requirements.
- 'Mandatory anti-corrosion plus waterproofing' for buried pipes is not a structural conclusion of GB 50264-2013: that code states only which layers make up the insulation structure; the anti-corrosion class and the outer waterproofing (protective) layer of buried pipes are governed by the anti-corrosion and waterproofing codes and the design documents - keep the code boundaries clear when citing.
- 'Simplified protective layer indoors' applies only to indoor installation of specific materials such as composite silicate coatings (Clause 6.4.1 commentary) and is not a licence to omit the protective layer generally; outdoors, waterproofing treatment is mandatory.
- Providing a moisture barrier does not equal providing waterproofing: the protective layer itself must remain integrally waterproof and be sealed at openings (Clause 6.4.5).
- GB 50185-93 is an early quality inspection and evaluation standard; construction acceptance is now governed by GB 50185-2010 'Code for acceptance of construction quality of insulation works of industrial equipment and pipelines' - check the edition and the current effective wording when citing Clause 5.0.1.
- Quantities of each layer must be listed separately (insulation 031208, painting 031201, anti-corrosion coatings 031202); the computation rules sit in GB/T 50856-2024 Appendix M and the companion computation cards - formulas are not covered here.
Further reading
- Layer make-up of insulation structures: GB 50264-2013 Clause 6.1.1 (heat insulation structure), Clause 6.1.2 (cold insulation structure), Clause 6.3.1 (moisture barrier provision and commentary), Clauses 6.4.1 and 6.4.5 (protective layer provision and integral waterproofing).
- Material requirements: GB 50264-2013 Clause 4.2.1 (moisture barrier materials, water absorption no more than 1.0%, consistent with GB/T 8175 'Guide for design of thermal insulation of equipment and pipelines'), Clause 4.3.1 (compatibility of protective layer materials).
- Related industry and acceptance codes: GB 50349-2015 Clause 8.3.2 (anti-corrosion layer beneath the heat or cold insulation layer), GB 50126-2008 Clause 6.1.1 (scope of moisture barrier work and structural forms: adhesion, wrapping, coating or film), GB 50738-2011 Clause 13.3.1 (conditions for insulation work and common insulation / moisture barrier / protective layer materials), GB 50019-2015 Clause 13.1.3 (anti-condensation for cold insulation, cold and thermal bridges, vapour barrier for non-closed-cell materials), GB 50185-93 Clause 5.0.1 (scope of moisture barrier quality inspection).
- Pricing itemisation: GB/T 50856-2024 Appendix M Table M.1.1 painting works (031201), Table M.2.1 anti-corrosion coating works (031202), Table M.8.1 insulation works (031208).
Keywords
- 绝热结构
- 保温结构
- 保冷结构
- 防潮层
- 保护层
- 防腐层
- GB 50264-2013
- 结露失效