Splitting equipment from piping in insulation works and selecting items: equipment versus pipe insulation by insulated object, and the volume of the insulation layer and area of the cladding of box-type equipment (bolted panel tanks)
Insulation items divide by 'insulated object', not by bore or material: GB/T 50856-2024 Appendix M Table M.8.1 (code 031208) lists equipment insulation, other piping insulation, ventilation duct insulation, and valve and flange insulation. Equipment insulation must describe the equipment form (vertical / horizontal / spherical) and pipe insulation the pipe outside diameter - the description items and consumptions differ and the two classes are not interchangeable. Rectangular bolted box equipment such as stainless panel tanks is itemised as equipment insulation under equipment items; the insulation layer is by volume m3 (outer surface area x thickness; cylinders by pi x (D+1.03d) x 1.03d x L), cladding and vapour barriers by the outer area of the insulation m2, lap and seam wastage already inside the item materials. The GB 50264-2013 clause 5.7.3 commentary line 'pipes over 720mm count as equipment for insulation and cladding' is a banding reference only.
Applicable Codes
- GB/T 50856-2024 通用安装工程工程量计算标准 App. M Table M.8.1、Table M.11.10 问题说明
- GB 50264-2013 工业设备及管道绝热工程设计规范 第 5.7.3 条及条文说明
- HG/T 20692-2014 化工企业热工设计施工图内容和深度统一规定 第 18.8.2 条
- TB/T 10833-2024 铁路工程预算定额 Vol. 12 机务车辆机械工程 册说明四
Positioning
In installation insulation (hot / cold), how the insulated object is classified and which item class applies: the BOQ split and quota volume basis of equipment versus pipe insulation, the item level for box / shell / dished equipment (bolted stainless panel tanks), and the measurement of insulation volume and cladding area.
Core conclusions
1) The split is by 'insulated object' - not bore, not material. GB/T 50856-2024 Appendix M Table M.8.1 governs the item setting, descriptions, units and rules of insulation works (code 031208), listed by object: equipment insulation, other piping insulation, ventilation duct insulation, plus valve and flange insulation. Table M.11.10 notes: item 3 - 'the object means equipment, piping, ventilation ducts, valves, flanges, steelwork'; item 1 - 'equipment form means vertical, horizontal or spherical'; item 2 - 'layers mean one-cloth-two-oil, two-cloth-three-oil etc.'; item 4 - 'structural form means steelwork: general, H-beam, pipe-rack'; item 5 - 'state if the design requires layered hot / cold application'. Equipment insulation must describe the form, pipe insulation the outside diameter - different description items and different labour-material-plant contents are exactly why the two classes are not interchangeable.
2) The operational band between equipment and pipe. GB 50264-2013 clause 5.7.3 commentary item (1): 'Pipes over 720mm in diameter count as equipment for insulation and cladding.' It sits in the explanation of the unit cost PT formula, serving economic-thickness estimation; the trade widely borrows it as the banding reference for whether a cylindrical object is 'pipe' or 'equipment' - it is not a mandatory measurement rule; where a dedicated item exists (tank insulation items in some provincial water / heating volumes), the dedicated item prevails.
3) Box-type equipment (assembled / bolted rectangular panel tanks etc.). Non-cylindrical, panel-assembled, insulated with board or roll material plus fasteners and cladding - unlike pipe-shell banding; itemise under equipment insulation (banded by material -> form -> thickness), and the box size sits far above the 720mm line. Roof and floor panels, where insulated per design, merge into the same material and thickness items on developed area.
4) Volume and cladding measurement
- Cylinder / pipe formula (Table M.11.10 note 6): 'D - diameter; 1.03, 2.1 - adjustment factors; d - insulation thickness; L - shell or pipe length.' Volume = pi x (D+1.03d) x 1.03d x L; vapour barrier and cladding = pi x (D+2.1d) x L. The railway TB/T 10833-2024 Volume 12 quantity rule 5 uses the same algorithm with 1.033: 'pipe insulation V = pi x (D+1.033d) x 1.033d x L, pi the circumference ratio, D the pipe outside diameter, 1.033 the factor, d the thickness, L the extended metres.' One document, one factor - never mix.
- Rectangular boxes: no dedicated formula exists (only shells, dished ends and dome-roof ends have them); volume = the insulation-contacting surface area x thickness: V = A x d, A the developed outer face (sides = (length + width) x 2 x height; top and bottom extra); cladding area = the developed face of the finished insulation (each edge + 2d), lap and seam wastage already inside the cladding item materials - no further factor, in the same spirit as the 2.1d rule for pipes (TB/T 10833-2024 rule 6: 'cladding is computed by design area in m2; single-layer cladding = the protected pipe's outer circumference x installed length; multi-layer x the number of layers').
- Dished ends and dome ends have their own formulas (notes 10-11); layered application 'computes by layer and applies the item of the required thickness'; single / double trace-heated pipes first derive the combined D' per notes 7-9, then enter the formulas.
- Equipment insulation material tables (HG/T 20692-2014 clause 18.8.2): insulation in m3, cladding in m2; 'the quantities entered carry no factor - net values only'; hot and cold totalled separately; circular equipment lists outside diameter and equivalent height, rectangular equipment length x width x height.
5) Units and conversion. Insulation by volume m3, barriers / cladding by area m2; item base prices usually per 10m3 / 10m2 (valves per 10, flanges per 10 pairs) - convert design quantities to the multiple units; never multiply base prices by 1m3 / 1m2 / 1 unit.
6) Accompanying and excluded items. Derusting and painting before insulation are itemised separately under Appendix M.1 painting (note 14); connected pipes, valves and flanges take their own items, never merged into the equipment quantity.
7) Gap items. Where the volume truly lacks the form / material / thickness band, compile a supplementary unit-rate build-up schedule per quota principles and get approval - never force a pipe insulation item (banded by bore, compiled on pipe shells; borrowing distorts the contents and will not survive audit).
Applicable boundaries
For equipment, piping, duct, valve and flange insulation take-off and item selection in industrial and building installation; BOQ per GB/T 50856-2024 Appendix M, quotas per the applicable painting / anti-corrosion / insulation volume (sector volumes such as TB/T 10833-2024). The '720mm band' is from a GB 50264-2013 commentary serving economic-thickness estimation - a reference, not a measurement clause, and never the sole basis for itemisation. The rectangular-box V = A x d and cladding on developed insulation faces is derived from the cylinder rules and material-table practice; not directly interchangeable with the 2.1 factor (which already covers laps and tolerance); the national 1.03 and the railway 1.033 must not mix. Bolted stainless panel tanks are rectangular - this card's box basis applies; a vertical cylindrical tank within 720mm might take pipe insulation (rare). Material, hot / cold and layering change only the description and band, not the formulas; layered work enters the outer formula with the D of the finished inner layer. Local item numbers must be checked in the executing volume - this card gives the volume and item-level basis only.
Further reading
GB/T 50856-2024 Appendix M (Table M.8.1, code 031208; Table M.11.10 notes 1-14 with formulas, end formulas, trace heating, valve / flange boxes in Tables M.11.10-1/-2, derusting and painting listed apart); GB 50264-2013 clause 5.7.3 and commentary (PT, factors Fi = 1.10~1.13, F1 = 1.0324, F9 = 1.20~1.30, the 720mm band); HG/T 20692-2014 clause 18.8.2 (material table format); TB/T 10833-2024 Volume 12 volume notes, quantity rules 1-6.
Keywords
- 设备绝热
- 管道绝热
- 绝热工程 031208
- 水箱保温
- 保护层面积
- 绝热层体积
- 设备形式
- 720mm 分界