The shell-versus-head split in the insulation quantity take-off of equipment vessels: side-by-side formulas for insulation volume and protective-covering area, the adjustment-coefficient versions, the boundary of application of the head surface development factor 1.5, and the treatment in measurement of supports, skirts and other attachments and of manhole and nozzle openings (GB/T 50856-2024 Table M.11.10; GB 50126-2008 Articles 5.1.9 and 5.1.10; the insulation chapters of local consumption quota standards)
Equipment insulation is measured in volume (m3) and damp-proof and protective coverings in area (m2), both under the same rule, 'calculated on the design surface area plus the insulation thickness and the adjustment coefficients'. Shell: V = pi x (D + 1.033d) x 1.033d x L, and S = pi x (D + 2.1d + 0.0082) x L; for N elliptical (dished) heads: V = [(D + 1.033d)^2/2] x pi x 1.033d x 1.5 x N, and S = [(D + 2.1d)^2/2] x pi x 1.5 x N, where 1.5 is the head surface development factor and applies only to standard elliptical or dished heads. Openings for manholes, nozzles, flanges and the like are not deducted from the developed area of the shell or the heads (the measurement rule sets no deduction provision); for skirts, supports, lifting lugs, instrument stubs, pipe supports and hangers and other attachments, GB 50126-2008 Article 5.1.9 provides 'thermal insulation shall be applied; where the design is silent, it may be omitted', and Article 5.1.10, for cold-service attachments: 'cold insulation is mandatory; its length shall be no less than 4 times the cold-insulation thickness or extend to the bearing blocks, and its thickness shall be 1/2 of the adjacent cold-insulation thickness but no less than 40mm'.
Applicable Codes
- GB/T 50856-2024 通用安装工程工程量计算标准 App. M Table M.8.1(code 031208)、Table M.11.10 问题说明第1~14条
- GB 50126-2008 工业设备及管道绝热工程施工规范 第5.1.9条、第5.1.10条
- 京建发〔2021〕201号 2021年预算消耗量标准 通用安装工程第十二册 第四章 绝热工程
- 天津市安装工程工程量清单计价指引(2025)表M.8 绝热工程(编码031208)
Positioning
This card addresses the split in the insulation quantity take-off of equipment (vessels): how the insulation volume and the damp-proof and protective-covering area are calculated separately for the shell and the heads, the side-by-side formulas and adjustment-coefficient versions, the boundary of the head surface development factor 1.5, and the treatment in measurement of supports, skirts and other attachments and of manhole and nozzle openings. For use when compiling BOQs, applying quota items and reconciling quantities, where a vessel is split into shell lengths plus heads calculated one by one.
Core conclusions
1) Measurement basis and itemisation. GB/T 50856-2024, Standard for Measurement of Construction Quantities of General Installation Works, Annex M, Table M.8.1 insulation works (code 031208): equipment insulation (031208001) is measured in m3, and damp-proof and protective coverings (031208007) in m2, both carrying the same measurement rule, 'calculated on the design surface area plus the insulation thickness and the adjustment coefficients'. The item description must state the insulation material, the insulation thickness and the equipment form (vertical, horizontal or spherical); Table M.11.10 note 1 states verbatim 'the equipment form means vertical, horizontal or spherical'. Current local pricing guides use the same wording (e.g. the Tianjin Installation Works BOQ Pricing Guide 2025, Table M.8). Where derusting and painting are required before insulation, itemise under the corresponding codes of the painting works of Annex M.1 (note 14).
2) Side-by-side formulas for the shell and head split (GB/T 50856-2024 Table M.11.10 notes 6 and 10; the full formula shapes and the 0.0082 term from the calculation rules of Chapter 4 of Volume 12, general installation works, of Jing Jian Fa [2021] No. 201)
| Part | Insulation volume V (m3) | Damp-proof / protective area S (m2) | Key variables |
|---|---|---|---|
| Shell (cylindrical section) | V = pi x (D + 1.033d) x 1.033d x L | S = pi x (D + 2.1d + 0.0082) x L | D = outside diameter of the equipment; d = insulation thickness; L = shell length; 0.0082 = binding-wire diameter or steel-strap thickness (m) |
| Elliptical / dished head (N off) | V = [(D + 1.033d)^2/2] x pi x 1.033d x 1.5 x N | S = [(D + 2.1d)^2/2] x pi x 1.5 x N | 1.5 = head surface development factor; N = number of heads; D = nominal diameter of the head |
| Dome-roof tank head | V = 2 x pi x r x (h + 1.033d) x 1.033d | S = 2 x pi x r x (h + 2.1d) | r = radius of the dome sphere; h = dome height |
The variables of note 6, verbatim: 'D, diameter; 1.03 and 2.1, adjustment coefficients; d, insulation thickness; L, length of the equipment shell or pipe'. The local consumption quota standards and the railway quota manuals expressly list '1.033 and 2.1, adjustment coefficients' and '0.0082, binding-wire diameter or steel-strap thickness' in their variable tables.
3) Points of use.
- Choose one coefficient version; never mix them. GB/T 50856-2024 note 6 gives 1.03 and 2.1 and omits the 0.0082 term; the 2013 edition, Jing Jian Fa [2021] No. 201 Volume 12, the railway quota manuals and most local consumption quota standards give '1.033 and 2.1 plus 0.0082'. The difference between 1.03 and 1.033 affects the volume by about 0.3%; the 0.0082 term affects the area by 0.0082/(D + 2.1d), growing as D shrinks: about 0.4% at D = 2.0m and d = 80mm, and about 3.9% at DN100 (d108) with d = 50mm. A single take-off, reconciliation or settlement document may adopt only one set.
- D is the actual outside diameter. Take the actual outside diameter of the pipe or equipment, not the nominal diameter (a DN100 seamless steel pipe is d108, and galvanised steel pipe has an outside diameter of 0.1143m; the difference can reach 3% to 4%).
- The boundary between L and the heads. L is the shell length; the heads (including their straight flanges) are calculated as N off by the head formulas, to avoid double counting or omission of the straight flanges.
- 1.5 is valid only for standard elliptical or dished heads. It corresponds to the surface development of a standard elliptical head with Di/2hi of about 2; spherical heads, conical heads and deep or shallow dished heads must not take 1.5 directly but should be calculated from the developed area given in the design or by geometry. GB/T 50856-2024 note 10 carries the formulas graphically in the official edition; the coefficients must be verified against those figures before use.
- Multi-layer insulation is calculated layer by layer. Table M.11.10 note 11, verbatim: 'where insulation is applied in layers, the quantities are calculated layer by layer against the item of the thickness required by the design'; in the outer-layer formula D is the outside diameter after completing the inner layer; the volumes and areas are calculated layer by layer and summed.
4) Openings and attachments: two classes, two rules.
- Openings in the body: no deduction. The measurement rule for equipment insulation and coverings is 'calculated on the design surface area plus the insulation thickness and the adjustment coefficients'; the expression is built only from D, d, L and N, and the rule itself sets no provision for 'deducting the area occupied by manholes, nozzles and flanges'; hence manholes, nozzles, connections and other openings are not deducted from the developed area of the shell or the heads. A sibling rule corroborates: GB/T 50856-2024 Table M.2.1, anti-corrosion painting works, note 10, verbatim: 'the quantities of anti-corrosion of equipment, of buried pipeline anti-corrosion, of pipeline anti-corrosion and of the internal walls of metal oil tanks against static are deemed to include the quantities of the various fittings, valves, manholes and irregular parts of the surfaces to which they are applied'.
- Attachments: judged separately under GB 50126-2008. Article 5.1.9, verbatim: 'skirts, supports, lifting lugs, instrument stubs, pipe supports and hangers and other attachments on heat-insulated equipment and piping shall be insulated; where the design is silent, they need not be'; Article 5.1.10, verbatim: 'skirts, supports, lifting lugs, instrument stubs, pipe supports and hangers and other attachments on cold-insulated equipment and piping must be cold-insulated; the length of their cold insulation shall be no less than 4 times the cold-insulation thickness or extend to the bearing blocks, and the thickness of the cold insulation shall be 1/2 of the adjacent cold-insulation thickness but no less than 40mm. Equipment skirts shall be cold-insulated inside and out.' The cold side is mandatory; the heat side is conditional on the design. The quantities at the attachments are taken together with the developed area of the equipment body, without deduction from the body area; demountable valves, flanges and the like are treated under the insulation-box approach: in Table M.8 the insulation box (031208008) is 'calculated on the design surface area', and the valve and flange insulation boxes have their own Tables M.11.10-1 (covering, m2) and M.11.10-2 (insulation, m3), calculated singly by size from the tables.
5) Worked example (basis illustration; D = 2.0m, d = 80mm, L = 6m, 2 elliptical heads).
- Shell covering (with 0.0082): S = pi x (2.0 + 2.1 x 0.08 + 0.0082) x 6 = approx. 41.02 m2; without the 0.0082 term: approx. 40.87 m2 (a difference of about 0.4%).
- Head covering: S = [(2.0 + 2.1 x 0.08)^2/2] x pi x 1.5 x 2 = approx. 22.15 m2.
- Total covering = approx. 63.17 m2.
- Shell insulation volume: V = pi x (2.0 + 1.033 x 0.08) x 1.033 x 0.08 x 6 = approx. 3.244 m3; head insulation volume: approx. 1.689 m3; total = approx. 4.933 m3.
- Within one calculation D, d and N are shared; volume and area are itemised separately and not offset against each other.
Boundaries of application
- This card is the take-off basis for equipment (vessels, shell plus heads); pipeline insulation uses the same formulas, but L is taken in extended metres with no deduction for the length occupied by valves, flanges and fittings; HVAC duct insulation is measured on the net duct area in m2 and does not take this card's shell formula.
- The coefficient versions 1.03 (GB/T 50856-2024 variable table) and 1.033 (Jing Jian Fa [2021] No. 201, the railway quota manuals and the local consumption quota standards) are mutually exclusive, as are 'with or without the 0.0082 term'; adopt one according to the version of the pricing basis agreed in the contract; never mix or compare across versions.
- 1.5 is an empirical surface-development factor for elliptical and dished heads and does not apply to spherical, conical or other special heads; note 10 of the 2024 edition carries the formulas graphically in the official edition, so the coefficients and variables must be verified against those figures.
- Attachment insulation and cold insulation are constructional requirements (GB 50126-2008) and do not mean 'the attachments must be itemised separately'; whether to itemise separately depends on the design (insulation boxes, insulation trays) and on what the applicable quota volume already includes.
- The no-deduction rule for equipment insulation and coverings is not the same system as the general building-works threshold 'deduct single openings over 0.3m2'; habits from building measurement must not be carried into the take-off of installation insulation.
Further reading
- Formulas and note texts: GB/T 50856-2024, Standard for Measurement of Construction Quantities of General Installation Works, Annex M 'painting, anti-corrosion and insulation works', Table M.8.1 (code 031208), Table M.11.10 'notes on questions in the insulation works of Table M.8.1', notes 1 to 14 (note 6, the shell and pipeline formulas; notes 7 to 9, the three cases of the composite diameter D' for heat-traced pipelines; note 10, equipment heads; note 11, dome-roof tank heads and layered calculation; notes 12 and 13, the calculation tables for flange and valve insulation boxes); the basic area formulas are also in Table M.2.1 notes 3 to 9 of the same standard.
- Full formula shapes and the 0.0082 term: Jing Jian Fa [2021] No. 201, 2021 budget consumption quota standards, general installation works, Volume 12, 'painting, anti-corrosion and insulation works', Chapter 4, insulation works, calculation rules (that chapter also provides that the equipment insulation items already allow for the heads except flanges and manholes, and that pipelines, valves and flanges above DN900 take the equipment insulation items for heat insulation).
- Attachment insulation and cold-insulation construction: GB 50126-2008, Code for Construction of Industrial Equipment and Pipeline Insulation Works, Articles 5.1.9 and 5.1.10 and their expositions.
- BOQ item descriptions and combinable items: Tianjin Installation Works BOQ Pricing Guide (2025), Table M.8 insulation works (code 031208), with the measurement units and the ranges of combinable budget base-price items for equipment insulation, damp-proof and protective coverings, insulation boxes and insulation trays.
Keywords
- 设备绝热
- 保护层面积
- 筒体
- 封头曲面展开系数1.5
- 调整系数1.033
- 0.0082捆扎线
- 接管开孔扣减
- 裙座保冷4倍