Treatment of insulation breaks at supporting points of equipment and pipes - fixed supports, sliding / guide supports, pipe shoes, hangers: construction requirements (expansion joints, expansion clearances, insulation inserts, anti-thermal-bridge insulating blocks, riser load-bearing trays) and measurement and pricing treatment (no deduction of insulation quantity at supports, the test for separately charging insulating blocks, and the measurement split at heat-tracing crossovers)
The insulation break at pipe shoes, supports and hangers is constructional accommodation and packing blocks, not an 'uninsulated gap': insulation quantities are calculated by the volume shown on the design with the extended metres of the pipe as the base, and apart from valves and flanges (which have separate insulation items) and pipe sections expressly left uninsulated by the design, the length occupied by supports and fittings is never deducted. Rigid insulation leaves expansion joints under support rings and between fixed supports (preferably 20 mm for pipes, 25 mm for equipment) filled tight with soft material of similar thermal conductivity, and the joints and clearances are not deducted from the volume. Fixed supports are wrapped and made up as a whole and thermal bridges are cut off with insulating blocks; sliding / guide supports leave an expansion clearance on the displacement side and the insulation accommodates the movement (mandatory where the sliding support height is less than the insulation thickness); all three support types require heat-insulating measures, and load-bearing points in cold service need rigid cold-conservation blocks. Whether insulating blocks (hardwood / packing blocks) are charged separately as materials depends on the work content of the quota line item applied - where included, no separate charge is allowed; only where the quota expressly says 'main materials charged separately' may they be listed separately. At heat tracing, the insulation layer and protective covering are calculated once on the combined tracing diameter D', not measured separately and twice; heat loss checks at breaks belong to design insulation calculation and form no measurement deduction or separate charge.
Applicable Codes
- GB/T 50856-2024 通用安装工程工程量计算标准 App. M Table M.8.1(编码 031208)、Table M.11.10 问题说明
- GB 50264-2013 工业设备及管道绝热工程设计规范 第 6.2.9 条、第 6.2.13 条
- GB 50126-2008 工业设备及管道绝热工程施工规范 第 4.3.3 条、第 5.1.10 条、第 5.3.12 条、第 5.13.12 条
- GB/T 50185-2019 工业设备及管道绝热工程施工质量验收标准 第 6.2.7 条
- CJJ 28-2014 城镇供热管网工程施工及验收规范 第 7.2.9 条
- GB 50738-2011 通风与空调工程施工规范 第 7.1.3 条
- T/CDHA 504-2021 长输供热热水管网技术标准 第 5.6.5 条
- CJJ/T 104-2014 城镇供热直埋蒸汽管道技术规程 第 6.2.3 条
- DB11/T 1832.13-2022 建筑工程施工工艺规程 第13部分 第 14.4.4 条
- DB11/T 2382-2024 建设工程施工消耗量标准 第 6.10.43 条
- 京建发〔2021〕201号 预算消耗量标准 通用安装第十二册第四章、第十册第四章
- TB/T 10833-2024 铁路工程预算定额 Vol. 12 册说明四
Topic positioning
How the 'breaks' (accommodation, expansion joints, expansion clearances) of equipment and pipe insulation at fixed supports, sliding / guide supports, pipe shoes and hangers are treated: how they are wrapped in construction, whether measurement deducts them, how insulating inserts and load-bearing trays are charged, and how quantities are split at crossovers with heat tracing. Comparative conclusions for budget preparation, settlement checking and insulation work acceptance.
Core conclusions
1. Measurement basis: no deduction of insulation quantity at supports and pipe shoes
- BOQ basis: GB/T 50856-2024 Annex M, 'Table M.8.1 insulation works (code: 031208)', provides that the item set-up, the content of item descriptions, the units of measurement and the quantity take-off rules for insulation works follow that table; the insulation layer is measured in m3 and the moisture barrier / protective covering in m2.
- Volume base = extended metres of pipe: TB/T 10833-2024, Volume 12, volume notes item IV.5: 'pipe insulation quantity is calculated as V = pi x (D + 1.033 delta) x 1.033 delta x L, where pi is the circumference ratio, D the pipe outside diameter, 1.033 the adjustment factor, delta the insulation thickness and L the extended metres of the pipe'; item IV.1 of the same notes for pipe erection gives 'no deduction of the length occupied by valves, flanges and fittings'.
- Local consumption standards agree: pipe insulation is 'calculated by the volume shown on the design, by material and pipe size' (Jing Jian Fa [2021] No. 201, general installation, Volume 12, chapter 4, measurement rules II); and 'apart from flanges and valves, all other fittings are already allowed for in the pipe insulation items' (same chapter, notes III).
- Conclusion: only valves and flanges (with separate insulation items, volumes from the flange / valve insulation box calculation tables) and pipe sections expressly left uninsulated by the design can be deducted. Pipe shoes, supports and hangers are only constructional accommodation or packing, not 'uninsulated gaps'; neither length nor volume is deducted.
2. Original wording on break construction: expansion joints and expansion clearances
CJJ 28-2014 clause 7.2.9: rigid insulation work shall leave expansion joints as required by the design; where the design is silent, the following apply: 1 at least one expansion joint on the horizontal pipe between two fixed supports; 2 on vertical equipment and vertical pipes, an expansion joint below the support ring; 3 preferably one expansion joint on each of the straight sections at both ends of a bend; 4 where two bends are less than 1 m apart, one expansion joint may suffice; 5 pipes over DN 300 carrying media over 120 C shall have an expansion joint at mid-bend; 6 expansion joint width: preferably 20 mm for pipes and 25 mm for equipment; 7 expansion joints shall use soft insulation material of thermal conductivity close to that of the insulation material, filled tight and bound securely.
GB/T 50185-2019 clause 6.2.7 (dominant item): acceptance of expansion joints and expansion clearances in rigid insulation products on equipment and pipes shall satisfy the design and the following: 1 at least one joint in the insulation of the horizontal pipe between two fixed supports; 2 one below the supports and flanges of vertical equipment or vertical pipes; 3 one at each end straight section as warranted by the distance between two bends; 4 cold-conservation layers shall have cold compensation applied outside the expansion joint; 5 joints of successive layers shall be staggered, preferably by more than 100 mm. Inspection: observation and tape measurement.
GB 50126-2008 clause 5.13.12: expansion clearance work - an expansion clearance must be left on the side opposite to the direction of expansion movement in any of these cases: 1 packed-type and bellows compensators; 2 where the sliding support height is less than the insulation thickness; 3 between the insulation structures of adjacent pipes; 4 between the insulation structure and fixed members such as walls, beams, railings, platforms and supports, and the openings the pipes pass through.
Measurement treatment: joint width and clearances are constructional gaps and are not deducted from the insulation volume. The insulation quota items themselves are priced on completed volume and already include operating wastage and binding materials (e.g. the rock wool product erection item of Volume 12 lists rock wool pipe shell 1.0300 m3/m3 and galvanised wire 13#~17#, with other material costs at 2% of material cost), so the soft filler and the bindings form no separate items.
3. Insulation practice at fixed and sliding / guide supports compared
| Item compared | Fixed support | Sliding / guide support |
|---|---|---|
| Displacement relation | No relative movement between pipe and support; the insulation structure moves with the pipe | The pipe slides axially over the support; the insulation must accommodate |
| Insulation wrap | Wrapped and made up as a whole, no joints | Expansion clearance on the displacement side; clearance mandatory per GB 50126-2008 clause 5.13.12 where the support height is less than the insulation thickness |
| Thermal bridge cut-off | Insulating blocks (hardwood / rigid blocks) at the bearing face cut off heat transfer | An insulation insert between support and pipe, the insert doubling as the sliding face |
| Common requirement | T/CDHA 504-2021 clause 5.6.5 item 3: 'guide supports, sliding supports, fixed supports and the like shall all take heat-insulating measures' | Same as left |
| Cold service points | GB 50264-2013 clause 6.2.13 (added provision): at load-bearing points such as supports, hangers and brackets within the cold-conservation layer, rigid cold-conservation blocks shall be provided | Same as left |
Construction details (citable for checking):
- Insulation inserts (supports and hangers of air-conditioning ducts and chilled / hot water pipes): GB 50738-2011 clause 7.1.3 - insert thickness shall be no less than the pipe insulation thickness and width greater than the bearing face width of the support or hanger; inserts shall be intact and tight against the insulation material without gaps; they shall bear the pressure without deforming after installation; timber shall be anti-rot treated; regular in shape, flat in surface, without defects.
- Cold-service attachments: GB 50126-2008 clause 5.1.10 - skirts, supports, lifting lugs, instrument nozzles and hangers on cold-conservation equipment and pipes must be cold-insulated; the cold layer length shall be no less than 4 times the cold layer thickness or run up to the blocks, and its thickness shall be 1/2 of the adjacent cold layer but not less than 40 mm; equipment skirts shall be insulated inside and out.
- Support members themselves: GB 50264-2013 clause 6.2.9 - the bearing face width of support members shall be 10~20 mm less than the insulation thickness, thickness preferably 3~6 mm; spacings: 1.5~2 m for vertical equipment and risers insulated on flat walls; 2~3 m for cylinders with medium temperature no less than 350 C and 3~5 m below 350 C; no more than 5 m for flat walls and cylinders in cold service; horizontal equipment of outside diameter D0 over 2 m using rigid insulation products shall have support brackets at the horizontal centreline; positions shall avoid flanges, fittings or valves, and supports of vertical equipment and pipes shall be above valves and flanges without hindering bolt removal; stainless and alloy steels should preferably use clamp types, parts welded directly onto stainless steel shall be of stainless steel and carbon steel parts shall have stainless backing pads welded on; support welding shall be done before the internal corrosion protection, lining and strength testing of the equipment or pipe, and welded supports on equipment requiring post-weld heat treatment shall be pre-welded at the maker's works. GB 50126-2008 clause 4.3.3 is to the same effect: supports shall not be placed where attachments exist, ring faces shall be set horizontal, the installation deviation of bracket gussets shall not exceed 10 mm, clamp-type supports shall be used where welding directly onto equipment is not allowed, and the bearing face width shall be 10~20 mm less than the insulation thickness.
- Riser load-bearing trays: DB11/T 1832.13-2022 clause 14.4.4 item 6 - one support tray per storey where the storey height is no more than 5 m, and no fewer than 2 per storey where it exceeds 5 m; the trays shall be welded to the pipe wall at 200 mm above the riser clamp, and the tray diameter shall not exceed the insulation thickness. Tray 'quantity follows storeys / points'.
- Directly buried steam pipes: CJJ/T 104-2014 clause 6.2.3 distinguishes inner-sliding from outer-sliding insulation structures - inner-sliding supports are fixed on the insulation layer and give support and guidance, requiring rigid insulation material; outer-sliding supports are fixed on the service pipe and move with it, for which soft insulation material is recommended; an oversized air gap causes convective heat transfer and weakens the insulation performance.
4. Whether insulating blocks and inserts are charged separately as materials
Test order: (1) first check whether the work content and item description of the quota line item applied already include the block / insert (items whose content includes 'cork product erection' merge it with the insulation item and forbid a separate charge); (2) then check whether the quota or standard expressly provides 'main materials charged separately'. One express case: where pipe supports are of the timber-insert type or the spring type, the pipe support fabrication and erection items apply and 'anti-rot timber inserts and spring vibration dampeners are charged separately as main materials' (Jing Jian Fa [2021] No. 201, general installation, Volume 10, chapter 4, notes III). Related sleeve basis: where insulated pipes pass through walls or floors with sleeves, the sleeve items apply by insulation outside diameter (same volume, notes VIII); DB11/T 2382-2024 clause 6.10.43 is to the same effect and provides that the sleeve packing is oil-hemp yarn and the consumption already covers hole reservation and hole sealing.
5. Heat loss checks are not a pricing matter (management boundary)
Heat loss and condensation checks at breaks and thermal bridges belong to design-stage insulation calculation and energy verification (see the insulation structure design and insulation calculation chapters of GB 50264-2013); they form no deduction item in measurement and attract no separate charge; only where the design changes the insulation thickness, construction or layering accordingly do the quantities and the quota items applied adjust with it.
6. Measurement split where insulation breaks cross heat tracing
- Construction: GB 50126-2008 clause 5.3.12 - where steam tracing pipes are insulated with soft products, the tracing pipes shall first be wrapped onto the main pipe with galvanised wire mesh or 'V'-shaped metal tracing covers and tied tight, without blocking the heating space, and then insulated; where electric tracing uses rigid products, the product size may be enlarged on site to suit the number of tracing runs.
- Measurement: GB/T 50856-2024 Table M.11.10 problem notes 7~9 - single-pipe or double-pipe tracing (same diameter, included angle under 90 degrees) is calculated on the combined tracing value D' (the gap between main and tracing pipes taken as 10~20 mm); double-pipe tracing (same diameter with angle over 90 degrees, different diameters with angle under 90 degrees) uses the respective formulas for D'; the resulting D' is then substituted into formulas (M.11.10-1) and (M.11.10-2) for the insulation, moisture barrier and protective covering quantities of the traced pipe. That is, traced sections are measured once on the enveloped combined diameter for insulation and covering, not measured separately and twice for main and tracing pipes; constructional 'enlarged product size / local thickening' adds no volume.
- Electric tracing allowances: DB11/T 1832.13-2022 clause 14.4.4 item 7 - electric tracing should not be installed below 10 C ambient; 0.5~1 m of slack at pipe accessories; 1 m of slack at the power end and the tail end and 0.5 m at each leg of tees.
Applicability boundaries
- Measurement bases differ by sector and local quota system: the BOQ follows GB/T 50856-2024 Annex M; railways follow TB/T 10833-2024 Volume 12; localities follow their own consumption standards (Jing Jian Fa [2021] No. 201 and DB11/T 2382-2024 cited here are Beijing practice; other provinces must check the notes and measurement rules of their insulation chapters and must not apply the factors and item division directly).
- Layered work: where the design or a code requires equipment insulation in layers, the quantities are calculated layer by layer and the quota items of the design thickness apply (Jing Jian Fa [2021] No. 201 Volume 12 notes VI; GB/T 50856-2024 Table M.11.10 problem note 11, which also gives the layered calculation formulas).
- Derusting and painting before insulation are itemised separately under the painting items (GB/T 50856-2024 Annex M.1) and are not merged into the insulation volume.
- Not applicable to: insulation fitted in the works on equipment bodies; the body of factory-insulated buried prefabricated pipe sections (only the field-insulated joints are listed separately, tee joints following the bend insulation items with the consumption x 1.3); and the dedicated insulation code systems of the nuclear and chemical industries.
- Development areas of protective covering, moisture barrier areas and the charging layers of seams, laps and material wastage are outside this card.
Further reading
- BOQ: GB/T 50856-2024 Annex M Table M.8.1 (insulation works, code 031208), Table M.11.10 problem notes 6~14 (formulas for cylinder and pipe insulation / moisture barrier / covering, the combined tracing value D', equipment heads and dome roof tank heads, layered calculation, and the flange and valve insulation box calculation tables M.11.10-1 / M.11.10-2).
- Design: GB 50264-2013 clause 6.2.9 (support members) and clause 6.2.13 (cold-conservation blocks).
- Construction and acceptance: GB 50126-2008 clauses 4.3.3, 5.1.10, 5.3.12 and 5.13.12; GB/T 50185-2019 clause 6.2.7; CJJ 28-2014 clause 7.2.9; GB 50738-2011 clause 7.1.3; DB11/T 1832.13-2022 clause 14.4.4.
- Networks and burial: T/CDHA 504-2021 clause 5.6.5; CJJ/T 104-2014 clause 6.2.3.
- Quota bases: Jing Jian Fa [2021] No. 201 general installation Volume 12 chapter 4 notes I~X and measurement rules I~IV, Volume 10 chapter 4 notes III / VIII; DB11/T 2382-2024 clause 6.10.43; TB/T 10833-2024 Volume 12 volume notes IV.
Keywords
- 绝热断点
- 管托绝热
- 支座隔热措施
- 伸缩缝
- 膨胀间隙
- 保冷垫块
- 绝热工程量不扣支座
- 伴热管绝热计量